© Published by Alberta King’s Printer Alberta King’s Printer Suite 700, Park Plaza 10611 - 98 Avenue Edmonton, AB T5K 2P7 Phone: 780-427-4952 E-mail: kings-printer@gov.ab.ca Shop on-line at kings-printer.alberta.ca Province of Alberta Extract Alberta Regulation 32/2024 Filed on March 5, 2024, in force March 6, 2024 HYDRO AND ELECTRIC ENERGY ACT HYDRO AND ELECTRIC ENERGY REGULATION
Copyright and Permission Statement The Government of Alberta, through the Alberta King’s Printer, holds copyright for all Alberta legislation. Alberta King’s Printer permits any person to reproduce Alberta’s statutes and regulations without seeking permission and without charge, provided due diligence is exercised to ensure the accuracy of the materials produced, and copyright is acknowledged in the following format: © Alberta King’s Printer, 20__.* *The year of first publication of the legal materials is to be completed.
Note All persons making use of this document are reminded that it has no legislative sanction. The official Statutes and Regulations should be consulted for all purposes of interpreting and applying the law.
(no amdt) ALBERTA REGULATION 32/2024 Hydro and Electric Energy Act HYDRO AND ELECTRIC ENERGY REGULATION Table of Contents 1
Definitions 2 Alterations 3 Exclusions for small power plants and small energy storage facilities 4 Exclusions for isolated generating units 5 Connections 6 Repeal 7 Expiry 8 Coming into force
Definitions 1 In this Regulation, (a) “Act” means the Hydro and Electric Energy Act; (b) “AUC Rule 007” means AUC Rule 007: Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations, Hydro Developments, Energy Storage Facilities, and Gas Utility Pipelines, as published by the Commission and amended from time to time; (c) “AUC Rule 012” means AUC Rule 012: Noise Control, as published by the Commission and amended from time to time; (d) “Commission” means the Alberta Utilities Commission under the Alberta Utilities Commission Act.
Alterations 2(1) Subject to subsection (2), unless the Commission directs otherwise, a person who proposes to make alterations to a power plant, energy storage facility, transmission line or electric distribution system must apply to the Commission in accordance with AUC Rule
Section 3 AR 32/2024 HYDRO AND ELECTRIC ENERGY REGULATION 2 (2) Subsection (1) does not apply to a power plant, energy storage facility, transmission line or electric distribution system if the alteration (
a) does not directly and adv ersely affect any person, (
b) does not have any adve rse environmental impact, (
c) does not result in non-compliance with AUC Rule 012, and (
d) does not require a change to the terms or conditions of an y existing approval, permit or licence. Exclusions for small power plants and small energy storage facilities 3(1) In this section, (a) “small energy storage fac ility” means an energy storage facility (
i) consisting of all of the energy storage resources that are or will be located at a site, and (ii) that has or will have a t otal capability of less than one megawatt but does not include an energy storage facility to which
section 25.1 of the Act applies; (b) “small power plant” means a power plant (
i) consisting of all of the generating units that are or will be located at a site, and (ii) that has or will have a t otal capability of less than one megawatt.
(2) Subject to subsection (3), unless the Commission directs otherwise, a small power plant or small energy storage facility that is or is intended to be connected to a transmission line or electric distribution system is excluded from the application of sections 11, 13.01 and 18 of the Act. (3) Subsection (2) does not apply unless (
a) the construction or operation of the small power plant or small energy storage facility, as the case may be, (
i) does not directly and adversely affect any person, and (ii) does not have any adve rse environmental impact,
Section 4 AR 32/2024 HYDRO AND ELECTRIC ENERGY REGULATION 3 a n d (
b) the small power plant or s mall energy storage facility is constructed or operated, as the case may be, in compliance with AUC Rule 012. Exclusions for isolated generating units 4(1) In this section, the following words and phrases have the meanings given to them in the Isolated Generating Units and Customer Choice Regulation (AR 165/2003): (
a) industrial area; (
b) isolated community; (
c) isolated generating unit.
(2) Subject to subsection (3), unless the Commission directs otherwise, where, in order to maintain a reliable supply of electric energy or to provide more electric energy to an isolated community or industrial area, (
a) an isolated generating unit is to be replaced, or (
b) an additional generating unit or energy storage resource i s required, an owner of the electric distribution system in whose service area the isolated community or industrial area is located may replace an isolated generating unit or add a generating unit or energy storage resource without an application to the Commission under
section 11 or 25.1 of the Act. (3) Subsection (2) does not apply unless (
a) either (
i) the total generating capability of the power plant, (ii) the total storage capability of the energy storage facility, or (iii) where a power plant and an energy storage facility are located on a common site, the combined total generating and storage capability including any replacement or addition, as the case may be, is less than 10 megawatts, and (
b) the replacement or addition
Section 5 AR 32/2024 HYDRO AND ELECTRIC ENERGY REGULATION 4 (
i) does not directly and adversely affect any person, (ii) does not have any advers e environmental impact, and (iii) is constructed and operated in compliance with AUC Rule 012. Connections 5 Notwithstanding
section 18(1) of the Act, unless the Commission directs otherwise, the owner or operator of a power plant, energy storage facility, transmission line or electric distribution system may connect its works with other works that it owns or operates, as the case may be, without an order referred to in that section. Repeal 6 The Hydro and Electric Energy Regulation (AR 409/83) is repealed.
Expiry 7 For the purpose of ensuring that this Regulation is reviewed for ongoing relevancy and necessity, with the option that it may be repassed in its present or an amended form following a review, this Regulation expires on January 31, 2033. Coming into force 8 This Regulation comes into force on the coming into force of
section 3 of the Electricity Statutes (Modernizing Alberta’s Electricity Grid) Amendment Act, 2022.