Water Sustainability Act 2014

statreg 14015

British Columbia — Consolidated Statutes

Water Sustainability Act 2014

statreg 14015

British Columbia — Consolidated Statutes

May 29, 2014

901199259/1401584569/140152185469

E4tlc14015

Interpretation and Application

Definitions

In this Act:

agricultural land reserve has the same meaning as in the Agricultural Land Commission Act ;

alter , in relation to a well, means

undertake a structural change to a well related to the well's depth, diameter or screen assembly,

install a surface seal in a well that does not have one, or

hydrofracture a well to enhance groundwater supply from the well;

appeal board means the Environmental Appeal Board continued under

section 93 of the Environmental Management Act ;

applicant means a person applying for

an authorization, an amendment to an authorization, a transfer of the appurtenancy of an authorization or an apportionment of the rights under a licence,

a change approval, an amendment to a change approval or the transfer of the appurtenancy of a change approval,

a drilling authorization, an amendment to a drilling authorization or the transfer of the appurtenancy of a drilling authorization,

the transfer of an application for an authorization, or

the abandonment of all or some of the person's rights under an authorization;

aquatic ecosystem , in relation to a stream, means the natural environment of the stream, including

the stream channel, the vegetation in the stream and the water in the stream, and

fish, wildlife and other living organisms insofar as their life processes

are carried out in the stream, and

depend on the natural environment of the stream;

aquifer means

a geological formation,

a group of geological formations, or

a part of one or more geological formations

that is groundwater bearing and capable of storing, transmitting and yielding groundwater;

authorization , except in references to drilling authorization, means a licence or use approval;

beneficial use ,

in relation to a use of water under an authorization, means using the water

as efficiently as practicable,

in accordance with any applicable regulations, and

iii

for the water use purposes, in the manner and in the period or at the times, authorized by the authorization, and

in relation to a use of water other than under an authorization, means using the water for a water use purpose

as efficiently as practicable,

in accordance with any applicable regulations, and

iii

in accordance with the provisions of this Act or the regulations that apply in relation to the use of water without an authorization;

beneficial use declaration means a declaration described in

section 30 (2) [beneficial use] ;

change approval means an approval, to make changes in and about a stream, issued under

section 11 (1) [changes in and about a stream] or a similar approval issued under a former Act;

changes in and about a stream means

any modification to the nature of a stream, including any modification to the land, vegetation and natural environment of a stream or the flow of water in a stream, or

any activity or construction within a stream channel that has or may have an impact on a stream or a stream channel;

compliance agreement means an agreement described in

section 102 (1), (2) and (3) [compliance agreements] ;

comptroller means the person designated as the Comptroller of Water Rights under

section 114 (1) [administration] ;

conditional licence means a licence, issued under this or a former Act, that authorizes the licensee to construct works, or divert and use water, before the issue of a final licence;

construct , in relation to a well, means

drill the well,

alter the well,

develop the well,

repair or maintain the well,

inject water or any other substance into the well, or

construct, install, replace, repair, alter or remove works that relate to groundwater or the well;

critical environmental flow threshold , in relation to the flow of water in a stream, means the volume of water flow below which significant or irreversible harm to the aquatic ecosystem of the stream is likely to occur;

Crown land means land, whether or not it is covered by water, that is vested in the government;

date of first use , in relation to a use of groundwater from an aquifer for a water use purpose, means the date from which the comptroller, a water manager or an engineer is satisfied in accordance with the regulations that groundwater from the aquifer has been used

regularly and beneficially on an ongoing basis,

for the water use purpose, and

on land, or for a mine or undertaking, to which, if the water use purpose were licensed, the licence would be appurtenant;

deactivate , in relation to works, means take the works out of service temporarily;

debris means

clay, silt, rock or similar material, or

any material, natural or otherwise, from construction or demolition;

decision maker , in relation to a decision under this Act, means

the person authorized to make the decision, and

if more than one person is authorized to make that decision, the person who is making or has made that decision,

whether on application or on the person's own initiative;

decommission , in relation to works, means take the works out of service permanently;

dedicated agricultural water means water that is dedicated under

section 82 (1) [plan regulations — dedicated agricultural water] for qualifying agricultural use on qualifying agricultural land;

development district has the same meaning as "district" in

section 58 [definitions] of the Drainage, Ditch and Dike Act ;

divert means,

in relation to water in a stream, cause the water to leave the stream channel, whether to cause the water to flow into another stream channel or a reservoir or otherwise, and

in relation to water in an aquifer, cause the water to leave the aquifer,

and includes extract or impound water from a stream or an aquifer;

drill , in relation to a well, means make the well by drilling, boring, driving, jetting or excavating;

drilling authorization means an authorization issued under

section 62 [drilling authorizations] ;

drinking water officer has the same meaning as in

section 1 [definitions] of the Drinking Water Protection Act ;

engineer , except in the definition of "professional" in

section 48 [definitions for Division 3 of

Part 3] , means a person designated as an engineer under

section 114 (5) [administration] ;

environmental flow needs , in relation to a stream, means the volume and timing of water flow required for the proper functioning of the aquatic ecosystem of the stream;

farm use , subject to the regulations, has the same meaning as in

section 1 (1) [definitions] of the Agricultural Land Commission Act ;

final licence means a licence, issued under this or a former Act, that authorizes the diversion and use of water but does not authorize the construction of works;

former Act means any Act containing provisions respecting the diversion and use of water that came into force before the date this definition comes into force;

geotechnical well means a well, other than a monitoring well or a well that is used to divert groundwater, that is drilled for the purpose of obtaining geotechnical, hydrological, hydrochemical or stratigraphical information;

government corporation has the same meaning as in

section 1 [definitions] of the Financial Administration Act ;

government water record means information, respecting the quality or quantity of water in a stream or aquifer, a person's use of water from a stream or aquifer, or works, that is in the records of

the minister,

the provincial health officer appointed under the Public Health Act ,

a regional health board designated under the Health Authorities Act ,

a prescribed minister, or

a prescribed government corporation;

groundwater means water naturally occurring below the surface of the ground;

improvement district means, as the context requires,

the corporation into which the residents of an area are incorporated as an improvement district under the Local Government Act or a former Act, or

the geographic area of the improvement district corporation;

licence means a conditional licence or a final licence;

local trust committee has the same meaning as in

section 1 [definitions] of the Islands Trust Act ;

mine includes a placer or mineral claim or land held or occupied for the purpose of winning a mineral from the claim or land, whether held in fee simple or by virtue of a record, registration, lease or licence;

mineral means

an ore of metal or a natural substance capable of being mined

that is in the place or position in which the ore or substance was originally formed or deposited or is in talus rock, and includes

rock and other materials from mine tailings, dumps and previously mined deposits of minerals, and

dimension stone, or

that is either loose, or found in fragmentary or broken rock that is not talus rock and occurs in loose earth, gravel and sand, and includes rock or other materials from placer mine tailings, dumps and previously mined deposits of placer minerals, or

coal,

but does not include petroleum or natural gas;

monitoring well means a well that

is used or intended to be used for the purpose of monitoring, observing, testing, measuring or assessing

the level, quantity or quality of groundwater, or

subsurface conditions, including geophysical conditions, and

is not used or intended to be used for the purpose of

exploring for or diverting groundwater for a water use purpose, or

injecting water or any other substance into groundwater on an ongoing basis;

natural boundary has the same meaning as in

section 1 [definitions] of the Land Act ;

officer means

a person designated as an officer under

section 114 (6) [administration] of this Act, or

a conservation officer as defined in

section 1 (1) [definitions] of the Environmental Management Act ;

order includes a decision or direction, whether or not the decision or direction is given in writing, but does not include a request;

owner , in relation to land, a mine or an undertaking in British Columbia, means a person who

is entitled to possession of the land, mine or undertaking, or

has a substantial interest in the land, mine or undertaking;

permit means a permit issued under

section 24 [permits over Crown land] or an authority, issued under a former Act, to flood, or to construct, maintain or operate works on, Crown land;

personal information has the same meaning as in

Schedule 1 of the Freedom of Information and Protection of Privacy Act ;

plan area means the area designated under

section 65 [order designating area for planning process] for the development of a water sustainability plan;

precedence , in relation to rights to divert and use water, means the precedence of those rights in accordance with

section 22 [precedence of rights] ;

private dwelling means a structure, or a part of a structure, that is occupied as a private residence;

production casing , in relation to a well, means the innermost pipe, tubing or other material installed in the well to support the sides of the well, but does not include a well liner or surface casing;

prospecting for a mineral means searching for a mineral

using hand-held tools in a manner that does not involve mechanical disturbance of the surface, or

in a prescribed manner;

protected fish population , in relation to a sensitive stream, means the population of fish in relation to which the stream has been designated as a sensitive stream;

public officer includes a member of the executive council, a public service employee and any other person, other than a judicial officer, who, under an enactment, has authority to make a decision affecting the rights of another person;

public personal information means any of the following:

the name, address, telephone number and other personal information of a subscriber that appears in a telephone directory, in either printed or electronic form, or is available through a directory assistance service, if

the directory or the directory assistance service is available to the public, and

the subscriber is permitted to refuse to have the subscriber's personal information included in the directory or made available by the directory assistance service;

personal information that appears in a professional or business directory, listing or notice that is available to the public, if the individual is permitted to refuse to have the individual's personal information included in the directory, listing or notice;

personal information that appears in a printed or electronic publication that is available to the public, including a magazine, book or newspaper in printed or electronic form, unless

a court has prohibited the publication or continued publication of the personal information by the source, or

the Information and Privacy Commissioner has made an order stating that the information was published contrary to the Personal Information Protection Act ;

public service employee has the same meaning as "employee" in

section 1 [definitions] of the Public Service Act ;

qualifying agricultural land means all or the part of a plan area, to which a regulation under

section 82 (1) [plan regulations — dedicated agricultural water] applies, that is

in the agricultural land reserve, or

zoned to permit the use of the land for farm use under

a municipal or regional district bylaw under Divisions 5 and 12 to 14 of

Part 14 [Planning and Land Use Management] of the Local Government Act or

Part XXVII [Planning and Development] of the Vancouver Charter , or

a bylaw made by a local trust committee under

section 29 [land use and subdivision regulation] of the Islands Trust Act ;

qualifying agricultural use means the use of water for

an irrigation purpose,

a prescribed industrial purpose, or

a storage purpose associated with a purpose described in paragraph (

a) or (b);

recorded water means water the right to the diversion or use of which is held under an authorization or another enactment;

registrar , in relation to land, means the registrar appointed under the Land Title Act for the land title district in which the land is located;

sensitive stream means a stream designated by regulation as a sensitive stream;

stream means

a natural watercourse, including a natural glacier course, or a natural body of water, whether or not the stream channel of the stream has been modified, or

a natural source of water supply,

including, without limitation, a lake, pond, river, creek, spring, ravine, gulch, wetland or glacier, whether or not usually containing water, including ice, but does not include an aquifer;

stream channel , in relation to a stream, means the bed of the stream and the banks of the stream, both above and below the natural boundary and whether or not the channel has been modified, and includes side channels of the stream;

take action ,

in relation to water, includes allow, start, stop, restrict or prohibit the diversion, use, including storage, carriage or distribution of the water, and

in relation to works, includes allow, start, stop, restrict, shut or prohibit their construction or operation;

undertaking means a project, including all land and other property acquired or to be acquired in connection with the project, and the general scheme for the acquisition, maintenance and operation of the works for the project, for

the diversion, carriage, use and sale of water, or

the sale of power produced from water,

the water use purpose of which water is referred to in an application or authorization;

unrecorded water means water in a stream or an aquifer that is not recorded water;

use approval means an approval issued under

section 10 [use approvals] or written approval, other than a licence, to divert and use water, given under a former Act;

water district means a water district prescribed by regulation;

water manager means a person designated under

section 114 (3) [administration] as a water manager;

water objective means an objective established by regulation under

section 43 [water objectives] ;

water source well has the same meaning as in

section 1 [definitions] of the Petroleum and Natural Gas Act ;

water sustainability plan means a water sustainability plan accepted under

section 75 (1) or (3) [acceptance of plan] ;

water use purpose means a purpose defined in

section 2 [water use purposes] or a subset of a purpose defined in

section 2;

water users' community has the same meaning as in

section 1 (1) [definitions] of the Water Users' Communities Act ;

well means an artificial opening in the ground made for the purpose of

exploring for or diverting groundwater,

testing or measuring groundwater,

recharging or dewatering an aquifer,

groundwater remediation,

use as a monitoring well,

use as a closed-loop geoexchange well, or

use as a geotechnical well,

but does not include

an artificial opening, other than a water source well, to which the Geothermal Resources Act or the Energy Resource Activities Act applies, or

an artificial opening of a prescribed class, made for a prescribed purpose or in prescribed circumstances;

well cap means a secure cap or lid that prevents vermin, contaminants, debris or other foreign objects or substances from entering the interior of the production casing, and includes a sanitary well seal;

well cover means a secure cover, lid or structure that prevents vermin, contaminants, debris or other foreign objects or substances from entering the well;

well pump means a pump that

is at or in a well, and

is used or intended to be used for the purposes of

diverting groundwater from a well,

adding water to a well to recharge the well or an aquifer, or

iii

dewatering an aquifer;

wellhead means

the physical structure, facility, well cover, adapter or device

that is at the top of, or at the side and near the top of, a well, and

from or through which groundwater flows or is pumped from the well, and

any casing, well cap, valve, grout, liner, seal, vent or drain relating to the well,

but does not include a well pump or a pump house;

wetland means a swamp, marsh, fen or prescribed feature;

wildlife means wildlife as defined in paragraph (

a) of the definition of "wildlife" in

section 1 (1) [definitions and

interpretation] of the Wildlife Act ;

works means

anything that can be or is used for

diverting, storing, measuring, conserving, conveying, retarding the flow of, confining or using water,

producing, measuring, transmitting or using electricity,

iii

collecting, conveying or disposing of sewage or garbage, or

preventing or extinguishing fires,

booms and piles placed in a stream,

obstructions placed in or removed from streams or the banks or beds of streams,

changes in and about a stream,

access roads to any of the works referred to in paragraphs (

a) to (

d) or (f) (i), and

wells and works related to wells, including

wellheads,

anything that can be or is used for injecting or otherwise adding water or any other substance to a well,

iii

anything that can be or is used for constructing, deactivating or decommissioning a well,

anything that can be or is used for exploring for, testing, diverting or monitoring groundwater,

anything that can be or is used for disinfecting a well,

an injection system attached to a work that is used for conveying, from a well, groundwater that will be used for applying fertilizers or pesticides, and

vii

anything that can be or is used in relation to a monitoring well or a well made for the purpose of groundwater remediation.

A reference in this Act to regulations or to anything as prescribed is a reference to regulations of the Lieutenant Governor in Council unless specifically provided otherwise in the applicable provision.

An authorization, change approval, permit or drilling authorization issued in substitution for

an original authorization, change approval, permit or drilling authorization, or

an original authorization, change approval, permit or drilling authorization as modified,

is conclusively deemed to be the original authorization, change approval, permit or drilling authorization as modified.

A reference in this Act

to an aquifer includes part of an aquifer, and

to a stream includes part of a stream.

Water use purposes

The following defined purposes are the purposes in respect of which water may be diverted from a stream or an aquifer:

conservation purpose means the diversion, retention or use of water for the purpose of conserving fish or wildlife and includes the construction of works for that purpose;

domestic purpose means the use of water for household purposes by the occupants of, subject to the regulations, one or more private dwellings, other than multi-family apartment buildings, including, without limitation, hotels and strata titled or cooperative buildings, located on a single parcel, including, without limitation, the following uses:

drinking water, food preparation and sanitation;

fire prevention;

providing water to animals or poultry kept

for household use, or

as pets;

irrigation of a garden not exceeding 1 000 m 2 that is adjoining and occupied with a dwelling;

industrial purpose means a use of water designated by regulation as a use for an industrial purpose, but does not include the use of water for any other water use purpose;

irrigation purpose means the use of water on cultivated land or hay meadows to nourish crops or on pasture to nourish forage;

land improvement purpose means the diversion or impounding of water to

protect land,

facilitate the development of a recreational facility or of a park or other protected area,

facilitate the reclamation, drainage or other improvement of land, or

carry out a project of a nature similar to a project described in paragraph (

b) or (c);

mineralized water purpose means

the bottling and commercial distribution of water so impregnated with mineral salts, elements or gases as to potentially give the water therapeutic properties, or

the use in commercial bathing pools of water that is

impregnated with mineral salts, elements or gases, or

naturally at a temperature suitable for that use;

mining purpose means

the use of water, including the use of water under pressure, for recovering minerals from the ground or from ore, or

the use of water under pressure to move earth, sand, gravel or rock;

oil and gas purpose means the use of water in the development of petroleum or natural gas wells or the production of petroleum or natural gas resources;

power purpose means the use of water in the production of electricity or other power;

storage purpose means the impounding and retention of water for subsequent use for a water use purpose;

waterworks purpose means the carriage or supply of water by one person or entity for the use in British Columbia of another person or entity.

Water Protection Act

Nothing in this Act authorizes a person to do anything prohibited by the Water Protection Act .

Geothermal resources

This Act does not apply to geothermal resources as defined in

section 1 (1) [definitions] of the Geothermal Resources Act .

Licensing, Diversion and Use of Water

Vesting water in government

The property in and the right to the use and flow of all the water at any time in a stream in British Columbia are for all purposes vested in the government, except insofar as private rights have been established under authorizations.

The property in and the right to the use, percolation and flow of groundwater, wherever groundwater is found in British Columbia, are for all purposes vested in the government and are conclusively deemed to have always been vested in the government except insofar as private rights have been

established under authorizations, or

deemed under

section 22 (8) [precedence of rights] .

No right to divert or use water may be acquired by prescription.

Use of water

Subject to this section, a person must not divert water from a stream or an aquifer, or use water diverted from a stream or an aquifer by the person, unless

the person holds an authorization authorizing the diversion or use, or

the diversion or use is authorized under the regulations.

A person is not prohibited from

diverting or storing and beneficially using water from a stream or an aquifer for extinguishing a fire, but if flow is diverted from a stream channel for that use, the flow must promptly be restored to that stream channel when the fire is extinguished, or

diverting water to test the quality or quantity of water or to conduct a flow test.

Unless regulations under

section 135 (5) [regulations closing or restricting access to water source] provide otherwise, a person is not prohibited from diverting, in accordance with any applicable regulations, and beneficially using unrecorded water

from a stream for domestic purpose or for prospecting for a mineral, or

from an aquifer for prospecting for a mineral.

A person may, in accordance with the regulations, divert, and beneficially use, including store, groundwater from an aquifer for domestic purpose unless

provided otherwise by regulations under

section 135 (6), or

this subsection does not apply to the applicable aquifer by regulations under

section 136 [regulations requiring authorizations for domestic use of groundwater] .

Rights acquired under authorizations

A licence entitles its holder to do the following in a manner provided in the licence:

divert and beneficially use the quantity of water specified in the licence;

construct, maintain and operate the works authorized by the licence and related works necessarily required for the proper diversion or use of the water or the power produced from the water;

make changes in and about a stream necessary for the construction, maintenance or operation of the works referred to in paragraph (

b) or to otherwise facilitate the authorized diversion;

construct fences, screens and fish or game guards across streams for the purpose of conserving fish or wildlife.

A use approval entitles its holder to do anything described in subsection (1) for the period or at the times and in the manner specified in the use approval.

Rights and permissions subject to Act

Licences

On application in accordance with

section 12 [application and decision maker initiative procedures] , the comptroller or a water manager may issue a licence, authorizing the diversion or use of water for one or more water use purposes, to any of the following:

an owner of land or a mine;

a holder of a certificate of public convenience and necessity issued under the Public Utilities Act , R.S.B.C. 1960, c. 323, the Utilities Commission Act or the Water Utility Act ;

a municipality, regional district, improvement district, development district or water users' community;

the government of British Columbia or Canada;

a commission, board or person having charge of the administration of Crown land or a mine or an undertaking on Crown land, administered by British Columbia or Canada or controlled by a ministry, department, branch or other subdivision of the government of British Columbia or Canada;

the Greater Vancouver Water District or any other water district incorporated by

an Act;

the British Columbia Hydro and Power Authority.

Use approvals

On application in accordance with

section 12 [application and decision maker initiative procedures] , the comptroller or a water manager may issue an approval for one or more water use purposes authorizing any of the following to divert or use water from a stream or an aquifer for a term not exceeding 24 months:

the government of British Columbia or Canada;

another person.

A use approval under this

section must not authorize

the diversion or use of more than the prescribed quantity of water,

the diversion or use of water for a prescribed water use purpose, or

the construction, maintenance or use of prescribed works.

For certainty, a use approval may be issued authorizing a person to divert water from a source of water supply for a water use purpose in relation to an appurtenancy, if any, specified in the use approval, whether or not a use approval was previously issued authorizing the person to divert water from the same water source supply for the same water use purpose in relation to the same appurtenancy.

Changes in and about a stream

On application in accordance with

section 12, the comptroller, a water manager or an engineer may issue an approval authorizing any of the following persons to make changes in and about a stream:

the government of British Columbia or Canada;

another person.

Changes in and about a stream may only be made in accordance with

the regulations,

an order.

Application and decision maker initiative procedures

An applicant may apply to a decision maker by

complying with any requirements prescribed in respect of the application, and

within the period, if any, prescribed by regulation,

complying with the decision maker's directions under

section 13 (1) or (9), if any,

paying the prescribed fees,

iii

providing in the form and manner specified by the decision maker any plans, specifications, reports of assessments and other information the decision maker requests, which information may include, but is not limited to, public personal information that is relevant to the application, respecting

the applicant,

existing water users, riparian owners, other applicants and other authorization holders, whose rights are likely to be detrimentally affected if the application is granted, and

land owners whose land is likely to be physically affected if the application is granted, and

providing in the form and manner specified by the decision maker the consents that are necessary for the decision maker to verify personal information relating to the applicant that is provided under subparagraph (iii).

For the purposes of subsection (1) (b) (iii), the decision maker may require that a specified assessment be performed, and a report of the assessment be prepared, by a person with the qualifications specified by the decision maker.

For the purpose of making a decision on an application, the decision maker may

collect contact information from the applicant, and collect public personal information and government water records, related to a person referred to in subsection (1) (b) (iii), and

verify information collected under this subsection or provided under subsection (1) or (2), including, in relation to

personal information of the applicant, by consent or by reference to public personal information or government water records, and

personal information of a person referred to in subsection (1) (b) (iii) (

B) or (C), by direct contact with the person or by reference to public personal information or government water records.

If works are required to be constructed in order for the applicant to obtain information required for the purposes of subsection (1) (b) (iii), the applicant may construct, in accordance with any applicable regulations, the works for that purpose, subject to any applicable requirement for a drilling authorization in relation to the works.

The decision maker may

shorten or extend the period prescribed for the purposes of subsection (1) (b), or

if no period has been prescribed, set a period for compliance with a direction or request, if any, referred to in subsection (1) (b).

A decision maker may exercise the powers under this

section in relation to an initiative of the decision maker under

section 21 [when final licence may be issued] , 26 [amendment or substitution of authorization, change approval or permit] , 28 [apportionment of rights under licences] or 62 [drilling authorizations] .

Objections to applications and decision maker initiatives

A decision maker must direct that an applicant for a licence, use approval or change approval, or for an amendment to any of them involving a change of works, give notice of the application in accordance with

section 117 [delivery and publication of documents and information] or the regulations to

any of the following whose rights the decision maker considers are likely to be detrimentally affected if the application is granted:

an authorization holder;

a change approval holder;

iii

an applicant for an authorization or change approval;

a riparian owner, and

a land owner whose land is likely to be physically affected if the application is granted.

A notice under subsection (1) must include the name of the decision maker and the address to which objections to the application may be delivered.

A person who is given notice under subsection (1) may deliver to the decision maker identified in the notice within the prescribed period any objection the person has to the granting of the application.

If an objection is delivered in accordance with subsection (3), the decision maker must decide whether or not the objection warrants a hearing.

If the decision maker decides to hold a hearing, the decision maker must

give notice to the applicant and to any person who delivered an objection under subsection (3) of

the date, time and location of the hearing, or

the date by which written submissions must be received by the decision maker, and

give the applicant and the objectors the opportunity to be heard in the hearing.

The decision maker may hold a hearing in writing, electronically or in person or by any combination of written, electronic or in-person hearings and, if the hearing is held orally, either in person or electronically, sections 95 [inquiry powers] , 96 [maintenance of order at hearings] and 97 [contempt proceeding for uncooperative person] apply.

The decision maker must give notice of the decision maker's decision on an application to any person who delivered under subsection (3) an objection in relation to the application.

For certainty, a decision maker need not give directions under subsection (1) if the decision maker is satisfied that, as a result of the decision maker's decision on an application referred to in that subsection,

no authorization holder's rights, no change approval holder's rights and no riparian owner's rights will be detrimentally affected,

no person's land will be physically affected, and

no person's application for an authorization or a change approval will be detrimentally affected.

A decision maker may direct that any applicant, and in the case of a transfer under

section 27 [transfer of appurtenancy] , the transferee, give notice in accordance with

section 117 or the regulations,

in the case of an apportionment under

section 28 [apportionment of rights under licences] , to the owner of each parcel affected by the apportionment,

in the case of an abandonment of rights under

section 31 [abandonment of rights under an authorization] , to anyone who is jointly using works with the applicant and any person whose land is physically affected by the existing works, and

in any case, to any person whose input into the decision the decision maker considers advisable.

Subsections (2) to (7) apply if notice is given under subsection (9) (

a) or (b).

Despite subsection (10), if a decision maker gives, or requires to be given, notice under subsection (9), the decision maker may specify how, and the date by which, a person given notice may object to the application.

A person given notice under subsection (9) (

c) is not entitled to be heard in a hearing under this section.

If a decision maker initiates the issuance of a final licence under

section 21 [when final licence may be issued] , a 30-year review under

section 23, an amendment under

section 26 [amendment or substitution of authorization, change approval or permit] or an apportionment under

section 28, subsections (9) to (12) of this

section apply unless the amendment requires a change of works, in which case subsections (1) to (8) and (14) of this

section apply.

Instead of requiring the applicant or a transferee to give a notice required under subsection (1) or (9), the decision maker may give the notice.

Powers respecting applications and decision maker initiatives

Whether or not notice is given, or objections are delivered, under

section 13 in relation to an application, the decision maker may, in accordance with this Act and the regulations,

refuse the application,

amend the application in any respect,

grant all or part of the application,

order the applicant to provide in the form and manner specified by the decision maker plans, specifications, reports of assessments or other information, which information may include, but is not limited to, public personal information that is relevant to the application, respecting

the applicant,

existing water users, riparian owners, other applicants and other authorization holders, whose rights are likely to be detrimentally affected if the application is granted, and

iii

land owners whose land is likely to be physically affected if the application is granted,

order the applicant to provide security to the decision maker in the amount the decision maker considers sufficient to ensure the performance of the applicant's obligations under this Act and the authorization, change approval or drilling authorization, as applicable, that is issued to the applicant, or

one or more conditional licences or final licences, or

a use approval, a change approval or a drilling authorization, as applicable.

An applicant must comply with an order made under subsection (1) (

d) or (

e) within the period specified by the decision maker.

For the purposes of subsection (1) (d), the decision maker may require that a specified assessment be performed, and a report of the assessment be prepared, by a person with the qualifications specified by the decision maker.

If an application is for the purpose of diverting water from an aquifer, the decision maker must take into account the quantity of water persons to whom

section 6 (4) [use of water — excluded groundwater users] applies are authorized to divert from the aquifer.

In considering an application for a new licence that relates to the region as defined by the Columbia Basin Trust Act , the decision maker must consider the current long term Columbia Basin Management Plan under

section 15 [Columbia Basin Management Plan] of that Act.

Without limiting subsection (1), the decision maker may refuse an application, or reject an application without considering it, if

the applicant fails to comply with

section 12 (1) [application and decision maker initiative procedures] ,

a direction under

section 13 (1) or (9),

iii

an order under subsection (1) (

d) or (

e) of this section, or

an order or a direction referred to in this paragraph within the required period,

in the case of an application for a use approval or change approval, the decision maker considers the proposed use of water or the proposed works would be more properly authorized by licence, or

the application is incomplete.

A decision maker must refuse to accept an application or a part of an application that would result in the issuance of an authorization to a person to whom

section 6 (4) [use of water — excluded groundwater users] applies.

A decision maker may not issue a licence authorizing the diversion or use of dedicated agricultural water unless the licence is for a qualifying agricultural use on qualifying agricultural land.

Despite subsection (8), a licence may be issued authorizing the diversion or use of unrecorded dedicated agricultural water for domestic purpose or a land improvement purpose.

A decision maker may exercise the powers under this

section in relation to an initiative of the decision maker under

section 21 [when final licence may be issued] , 26 [amendment or substitution of authorization, change approval or permit] , 28 [apportionment of rights under licences] or 62 [drilling authorizations] .

For certainty, a use approval may be issued authorizing the diversion or use of unrecorded dedicated agricultural water for any water use purpose on any land.

Environmental flow needs

Except in relation to an application exempted under the regulations, the decision maker must consider the environmental flow needs of a stream in deciding an application in relation to the stream or an aquifer the decision maker considers is reasonably likely to be hydraulically connected to that stream.

For an application in respect of which the decision maker must consider, or decides under subsection (4) to consider, the environmental flow needs of a stream,

the applicant must provide to the decision maker the information and reports of assessments the decision maker directs for the purposes of paragraph (

b) of this subsection, and

the decision maker must determine, in accordance with any applicable regulations, the environmental flow needs of the applicable stream.

For the purposes of subsection (2) (a), the decision maker may require that a specified assessment be performed, and a report of the assessment be prepared, by a person with the qualifications specified by the decision maker.

Despite subsection (1), a decision maker may take into account the environmental flow needs of any stream the decision maker considers may be affected by granting the application.

Mitigation measures

If the decision maker considers that the diversion and use of water, or changes in and about a stream, proposed by an application for an authorization, or the changes in and about a stream proposed to be made under a change approval, are likely to have a significant adverse impact on the water quality, water quantity or aquatic ecosystem of a stream or aquifer, a stream channel or other uses of water from the stream or aquifer to which the application relates, the decision maker may

require that the applicant submit a proposal for mitigation measures to address those effects, which mitigation measures must meet prescribed criteria, if any, and

Sensitive streams mitigation

If an application for an authorization or a change approval, or an amendment to an authorization or change approval, is in relation to a sensitive stream, the decision maker

may require that the applicant provide the prescribed plans, specifications, reports of assessments or other information, in addition to the other information required under this Act in relation to the application, and

must apply prescribed criteria, if any, in addition to the other criteria to be applied under this Act, in deciding whether to grant the application.

An application described in subsection (1) must include mitigation measures that meet the prescribed criteria, if any, and that the applicant proposes to take to mitigate any adverse impact on a protected fish population resulting from granting the application in relation to the sensitive stream.

The decision maker may grant an application described in subsection (1) only

if satisfied that

any adverse impact, resulting from granting the application, on the sustainability of any protected fish population of the sensitive stream is likely to be insignificant,

the mitigation measures proposed by the applicant, if carried out, would ensure that granting the application is not likely to cause a significant adverse impact on any protected fish population or the aquatic ecosystem of the sensitive stream, or

iii

compensatory mitigation measures that meet any prescribed criteria, whether or not proposed by the applicant, if carried out, in place of or supplemental to the proposed mitigation measures, will enhance or enable the enhancement of an aquatic ecosystem elsewhere that will fully compensate for the significant adverse impact on that protected fish population or aquatic ecosystem resulting from granting the application, and

If the decision maker considers that there is a reasonable alternative source of water reasonably available to an applicant making an application referred to in subsection (1), the decision maker may refuse to grant the application.

Not in force

[Not in force.]

Licences for power purposes

In this section:

operational term means the period beginning when

the activities described in the definition of "project development term" are completed, or

the period authorized for completion of those activities has ended,

whichever occurs earlier, during which power is, or is authorized to be, produced under a licence issued for a power purpose and during which a storage purpose authorized by a licence in relation to the power purpose may be exercised;

project development term means the period, following the issue of a licence for a power purpose but before the beginning of the operational term, during which activities required to prepare for power production under the licence are performed, including, without limitation, project design and engineering, securing construction and other contracts and constructing works.

This

section applies to

a licence issued for a power purpose on or after October 23, 2003, unless the licence is being issued in substitution for a licence that did not specify the term of the licence and was issued for a power purpose before that date,

a licence that is being amended, whether or not the licence is replaced, if

the licence was issued for a power purpose before October 23, 2003 and specified the term of licence, and

the amendment is for the purpose of extending the term of the licence, or

a licence that is being amended, whether or not the licence is replaced, if

the licence was issued for a purpose other than a power purpose, and

the amendment is for the purpose of authorizing the use of water for a power purpose.

The decision maker must not issue a licence to which this

section applies that has an operational term longer than 40 years.

The decision maker may provide in a licence described in subsection (2) (

a) or (

c) for a project development term of up to 10 years.

The holder of a licence issued to authorize the use of water for a power purpose may apply to renew the licence before the expiry of the operational term of that licence.

Despite

section 26 [amendment or substitution of authorization, change approval or permit] , this Act and the regulations apply to the following applications as if the application were for a new licence:

an application for an amendment referred to in subsection (2) (b) (ii);

an application for an amendment referred to in subsection (2) (c) (ii);

an application to extend the term of a licence to which this

section applies.

The rights exercisable under a licence to which this

section applies that is issued in substitution for or as a renewal of another licence have precedence from the same date as the rights under the licence that is replaced.

Despite subsection (3), if an application is made under subsection (5), the licence does not expire until the later of

the date the decision maker decides on the application, and

the expiry date of the operational term of the licence.

If a licensee fails to apply to renew a licence to which this

section applies before the expiry of the operational term of the licence and the failure, in the opinion of the decision maker, is not the fault of the licensee, the decision maker may extend the expiry date for not more than 6 months from the original expiry date and, if the expiry date is extended, the licence is deemed to be and to have been continuously in force from the date of issue until the new expiry date.

Subsection (9) does not apply to a licence for which the expiry date has been extended under that subsection.

A decision under subsection (9) of this

section to refuse to extend an expiry date is final and may not be appealed to the appeal board.

Purpose, precedence and appurtenancy

A decision maker must ensure that a licence that the decision maker issues specifies as the appurtenancy of the licence an appurtenancy

that, except in relation to a licence that is required to be registered under the Water Protection Act , is located entirely in British Columbia,

that consists of land, a mine or an undertaking, or any combination of those things, and

that is adequately described in the licence.

A decision maker who issues a use approval, change approval, permit or drilling authorization may specify an appurtenancy that meets the requirements of subsection (1) as the appurtenancy of the use approval, change approval, permit or drilling authorization, as applicable.

The decision maker must ensure that every authorization that the decision maker issues

specifies the date of precedence of the rights under the authorization,

specifies the maximum quantity of water that may be diverted and used for each water use purpose authorized by the authorization, and

is for the diversion of water for one or more water use purposes and those water use purposes are specified in the authorization.

When final licence may be issued

On application under

section 12 [application and decision maker initiative procedures] , or on the comptroller's or water manager's own initiative, the comptroller or a water manager may issue to the holder of a conditional licence a final licence authorizing the diversion or use of the quantity of water that the decision maker determines to have been beneficially used for the water uses purposes authorized under, and during the term of, the conditional licence, when

the licensee completes the works, or

the period for completing the works expires and, if any works have not been completed, the decision maker determines that the works that have not been completed are not required.

On the issue of a final licence, the conditional licence it replaces has no further effect.

Precedence of rights

The rights exercisable under an authorization that authorizes the diversion of water from a stream have precedence in relation to the rights of other authorization holders who divert water from

the stream,

a tributary of the stream, or

an aquifer the decision maker considers is reasonably likely to be hydraulically connected to that stream

according to the dates set out in the authorizations as the dates from which the rights take precedence.

The rights exercisable under authorizations described in subsection (1) that have precedence from the same date have precedence in accordance with the ranking under subsection (7) of the water use purposes in respect of which the authorizations are issued.

The rights exercisable under authorizations described in subsection (1) have equal precedence if the rights have precedence from the same date and are for the same water use purpose.

The rights exercisable under an authorization that authorizes the diversion of water from an aquifer have precedence in relation to the rights of other authorization holders who divert water from the aquifer, or another aquifer the decision maker considers is reasonably likely to be hydraulically connected to that aquifer, according to the date set out in the authorization as the date from which the rights take precedence.

The rights exercisable under authorizations described in subsection (4) that have precedence from the same date have precedence in accordance with the ranking under subsection (7) of the water use purposes in respect of which the authorizations are issued.

The rights exercisable under authorizations described in subsection (4) have equal precedence if the rights have precedence from the same date and are for the same water use purpose.

For the purposes of subsections (2) and (5), water use purposes are ranked, from highest to lowest as follows:

domestic;

waterworks;

irrigation;

mineralized water;

mining;

industrial;

oil and gas;

power;

storage;

conservation;

land improvement.

Despite subsections (1) to (6), a person to whom

section 6 (4) [use of water — excluded groundwater users] applies is deemed to have rights that have precedence under those subsections, as if the deemed rights were granted under an authorization that

sets out as the date of precedence the date of first use of the water, and

authorizes the use of the greater of

2 000 litres of water per day for each private dwelling on a parcel, or

the amount of water the engineer is satisfied the person has been using for domestic purposes.

Despite subsections (1) to (8), if an order under

section 86 (1) or (3) [declarations of significant water shortage] applies to a stream and the comptroller has determined the critical environmental flow threshold for the stream under

section 87 (1) [critical environmental flow protection orders] , the amount of that critical environmental flow threshold for the stream has precedence over the rights

under any authorization issued in relation to the stream or a hydraulically connected aquifer referred to in subsection (1) of this section, or

of a person described in subsection (8) of this section.

Despite subsections (1) to (9), if an engineer is taking action to enforce the precedence of rights to divert or use water from a stream or aquifer, a person must not be prohibited from diverting water from the stream or aquifer for essential household use.

For the purposes of this section, essential household use means the use by the occupants of one private dwelling of not more than 250 litres of water per day for

drinking water, food preparation and sanitation, and

providing water to animals or poultry that are kept

for household use, or

as pets.

This

section applies to a licence that

was issued on or before the date this

section comes into force for an unlimited period or that has, at that date, at least 30 years remaining in its term, or

is issued after the date this

section comes into force for an unlimited period or a term exceeding 30 years,

but does not apply to licences

issued for a power purpose, or a storage purpose related to a power purpose, on or after October 23, 2003,

issued under the Industrial Development Act , or

issued following a review, or reviewed, under the Water Use Plan directives published by the government and dated December 1998.

for a licence issued on or before the date this

section comes into force, any time that is at least 30 years after that date, and any time that is at least 30 years after the immediately preceding review under this section, and

for a licence issued after the date this

section comes into force, any time after the licence has been in effect for 30 years after its issue and any time that is at least 30 years after the immediately preceding review under this section.

A licensee who is given a direction under subsection (2) must, within the period specified in the direction, provide to the decision maker who gave the direction,

the information, plans, specifications and reports of assessments, including a water conservation audit carried out in accordance with and meeting the requirements of the regulations, specified by the decision maker, and

in the form and manner specified by the decision maker, the consents that are necessary for the decision maker to verify information provided under paragraph (a).

The decision maker may require that a specified assessment be performed, and a report of the assessment be prepared, by a person with the qualifications specified by the decision maker.

Section 12 (1) (b) (iii), (2) and (3) applies for the purpose of a review under this section.

the best available technology in respect of water use efficiency and water conservation,

best practices in respect of water use efficiency and water conservation,

any increase in knowledge respecting actual stream flow or aquifer conditions,

the effects of climate change,

the licensee's beneficial use of the water,

the use, operation or maintenance of works, and

prescribed factors.

reduce the maximum rate of diversion of water under the licence,

alter the time of diversion or use, including storage, of water under the licence,

construct, alter, install, replace, repair, maintain, improve, seal, deactivate, decommission or remove any works, or

adopt a more efficient practice.

A direction given under subsection (2) is final and may not be appealed to the appeal board.

Permits over Crown land

The comptroller or a water manager in the case of an authorization, or the comptroller, a water manager or an engineer in the case of a change approval or drilling authorization, may, on compliance by the holder of the authorization, change approval or drilling authorization with the regulations, issue to that holder one or more permits authorizing the flooding of Crown land or the construction, maintenance or operation on Crown land of works authorized under the authorization, change approval or drilling authorization.

A person must not, for the purposes of exercising rights or performing duties under an authorization, change approval or drilling authorization, construct, maintain or operate works on, or flood, Crown land unless the person

holds a permit under this section, or

has authority to do so under another enactment.

Transfer of authorization, change approval or permit

An authorization, change approval or permit that is made appurtenant to any land, mine or undertaking, and the rights granted and duties imposed under the authorization, change approval or permit, pass with a conveyance or other disposition of the land, mine or undertaking.

An owner conveying or otherwise disposing of land, a mine or an undertaking, to which an authorization, change approval or permit is appurtenant, must give written notice of the conveyance or other disposition to the comptroller or a water manager before completing the disposition.

In the case of a transmission or other disposition of land, a mine or an undertaking to which an authorization, change approval or permit is appurtenant to the personal representative or other person representing the owner of the land, mine or undertaking, the personal representative or other person must give to the comptroller or a water manager written notice

as soon as practicable after the transmission or disposition to the personal representative or other person, and

before completing a disposition by the personal representative or other person of the land, mine or undertaking to another person.

Amendment or substitution of authorization, change approval or permit

On application by the holder in accordance with

section 12 [application and decision maker initiative procedures] , or on the comptroller's or water manager's own initiative, the comptroller or a water manager may amend an authorization and a permit issued in relation to the authorization, and the comptroller, a water manager or an engineer may amend a change approval and a permit issued in relation to the change approval, to do any of the following:

extend the time set for beginning construction of works;

extend the time set for completion of works;

extend the time set for making beneficial use of water;

authorize additional or other works than those previously authorized;

correct an error in the authorization, change approval or related permit;

remove a provision of the authorization, change approval or related permit that is inconsistent with this Act;

authorize the use of water for a water use purpose other than a water use purpose specified in the authorization;

extend the term of the authorization, change approval or related permit;

increase or reduce the quantity of water authorized to be diverted if it appears to have been erroneously estimated.

On application, the comptroller or a water manager may amend an authorization and a permit issued in relation to the authorization, and the comptroller, a water manager or an engineer may amend a change approval and a permit issued in relation to the change approval, to make an amendment not referred to in subsection (1), other than an amendment that would increase the quantity of water authorized to be diverted.

Despite subsection (1) (g), a decision maker may not

authorize a change in water use purpose for dedicated agricultural water except to another qualifying agricultural use, or

issue a licence to a person to whom

section 6 (4) [use of water — excluded groundwater users] applies.

If an application is made under subsection (1) (

h) to extend the term of an authorization, change approval or permit before the date the authorization, change approval or permit expires, the authorization or change approval, as applicable, and any permit issued in relation to either, does not expire until the later of

the date the decision maker decides on the application, and

the expiry date of the authorization, change approval or permit, as applicable.

Despite subsection (1) (h), a decision maker may not amend a use approval to extend the term beyond 24 months from the date the use approval was issued.

Transfer of appurtenancy

to a person who is the owner of land, a mine or an undertaking and to whom the holder is transferring some or all of the rights granted and duties imposed under the authorization or change approval and related permit, determining as the appurtenancy for the rights and duties transferred the land, mine or undertaking of the transferee, or

to the holder, determining as the appurtenancy for some or all of the rights granted and duties imposed under the authorization or change approval and related permit land, a mine or an undertaking of that holder.

An authorization, change approval or permit issued under subsection (1) (

a) or (

b) has the same precedence as the original authorization, change approval or permit, or the original authorization, change approval or permit, as modified, as applicable.

Except in relation to a licence required to be registered under the Water Protection Act , a decision maker must not exercise the decision maker's discretion under subsection (1) of this

section to determine an appurtenancy that is not in British Columbia.

If the land, mine or undertaking to which an authorization, change approval or permit is appurtenant is mortgaged, and a copy of the mortgage, or particulars of the mortgage, is filed with the comptroller or a water manager, a transfer of the appurtenancy of the authorization, change approval or permit, as applicable, is not effective without the written consent of the mortgagee.

Despite subsection (1), the appurtenancy determined under subsection (1) for a licence issued in relation to dedicated agricultural water must be qualifying agricultural land.

Apportionment of rights under licences

If the land to which a licence, or a permit issued in relation to the licence, is appurtenant consists of more than one parcel owned by different persons, on application by an owner of a parcel of that land in accordance with

section 12 [application and decision maker initiative procedures] , or on the comptroller's or water manager's own initiative, the comptroller or a water manager may apportion among the owners of the parcels the rights granted and duties imposed under the licence or permit.

A licence or a permit issued under subsection (2) has the same precedence as the original licence or permit or the original licence or permit, as modified, as applicable.

Rights and responsibilities of applicants and holders

The following persons must exercise reasonable care to avoid damaging land, works, trees or other property of another person:

an applicant for an authorization, change approval, drilling authorization or permit;

the holder of an authorization, change approval, drilling authorization or permit;

a person who, in accordance with the regulations or an order of the comptroller, a water manager or an engineer, makes changes in and about a stream or diverts or uses, including stores, water.

A person referred to in subsection (1) (a), (

b) or (

c) must properly inspect, maintain and repair works constructed, operated or used by the person,

in accordance with any prescribed requirements,

in accordance with an order, and

in a manner that ensures that the works do not cause a significant risk of harm to public safety, the environment, land or other property.

When an authorization, change approval or permit that authorizes the construction or use of works is abandoned, cancelled or expires, the holder or former holder, as applicable, of the authorization, change approval or permit must ensure that the works are deactivated or decommissioned in accordance with the regulations and orders.

A person referred to in subsection (1) (a), (

b) or (

c) is liable to owners of land or premises for damage or loss resulting from the construction, maintenance, use, operation or failure of the person's works.

Subject to subsections (1) to (4), a holder of a licence for a power purpose, a storage purpose, a waterworks purpose or an irrigation purpose may fell and remove any tree, and remove any rock or other thing, that endangers the holder's works.

Beneficial use

A person who diverts water must make beneficial use of the water diverted.

A licensee must submit to the comptroller, a water manager or an engineer, as applicable, a signed declaration that complies with subsection (3) at the time directed to do this by the comptroller, water manager or engineer.

A declaration required under subsection (2) must

state whether the licensee has, during the 3 years preceding the date of the declaration,

made beneficial use of the quantity of water authorized to be diverted under the licence, and

include any other information, or consents required to verify the other information, required by the decision maker, and

be in the form required by the decision maker.

A direction under subsection (2) may require the licensee to provide with the beneficial use declaration the results of a water conservation audit carried out in accordance with and meeting the requirements of the regulations.

On receipt of a beneficial use declaration and, if required by the decision maker, the results of a water conservation audit, the decision maker may order the licensee to take measures to meet the level of efficiency of water use and conservation of water specified in the order.

On the direction of the comptroller, a water manager or an engineer, each of the following persons must provide information, or consents required to verify the information, in the time specified, respecting the quantity of water the person has beneficially used in the period specified by the comptroller, water manager or engineer, as applicable:

the holder of a use approval;

a person who diverts, stores or uses water under the regulations;

a person who diverts, stores or uses water as described in

section 6 (2) (b) [use of water — flow tests] or (3) [use of water — at sufferance] or as authorized by

section 6 (4) [use of water — excluded groundwater users] .

For the purpose of inquiring into or confirming beneficial use of water, the decision maker may

collect relevant public personal information or government water records related to a person referred to in subsection (2) or (6) or to the person's use of water, and

verify information collected under this subsection or provided under subsection (3) or (6), including, in relation to personal information, by consent or by reference to public personal information or government water records.

Subject to

section 117 (4) [delivery and publication of documents and information] , the comptroller may publish a beneficial use declaration or information provided under subsection (6).

A direction given under subsection (2) or (6) is final and may not be appealed to the appeal board.

Abandonment of rights under an authorization

requiring the repair, maintenance or removal of works or arrangements respecting responsibility for the repair, maintenance or removal of works with

other authorization holders who jointly use or used the works,

previous authorization holders who jointly used the works, or

iii

the owner of land on which the works are located, or

requiring deactivation or decommissioning of the works or arrangements respecting responsibility for deactivation or decommissioning of the works with one or more persons referred to in paragraph (a).

If there is more than one registered owner of the land, or more than one owner of a mine or undertaking, to which an authorization is appurtenant, an application under subsection (1) must have attached to it the written consent of all registered owners of the land or all owners of the mine or undertaking, as applicable, to the abandonment of rights.

If the land, mine or undertaking to which an authorization is appurtenant is mortgaged, and a copy of the mortgage, or particulars of the mortgage, is filed with the comptroller or a water manager, an application under subsection (1) must have attached to it the written consent of the mortgagee to the abandonment of rights.

Licensee's right to expropriate land

A licensee has the right to expropriate any land reasonably required for the construction, maintenance, improvement or operation of works authorized or necessarily required under the licence.

In addition to the right under subsection (1), the holder of a licence that authorizes the diversion of water for domestic purpose or a waterworks purpose has the right to expropriate any land the control of which by the licensee would help prevent pollution of the water authorized to be diverted.

In addition to the rights under subsections (1) and (2), with the consent of the Lieutenant Governor in Council, the holder of a licence that authorizes the construction or use of a dam has the right to expropriate any land that has been flooded by construction of the dam or that would be flooded if the dam were constructed and utilized to the maximum height authorized.

An expropriation under this

section must be made in accordance with the regulations and the licensee who expropriates the land must provide compensation to the owner of the land expropriated in the amount determined in accordance with the regulations.

If expropriation proceedings have been commenced by a licensee in relation to land on or in which works authorized under the licence are located, a person, including an owner of the land, must not interfere with the works or prevent the licensee from maintaining, operating, using or improving those works so long as the licensee diligently prosecutes the expropriation proceedings.

Licensee's rights when owner refuses compensation

an award of compensation is made in relation to land expropriated under

section 32,

the amount of the award is tendered to the owner of the expropriated land, and

that owner fails to execute and deliver to the licensee the required conveyance or other instrument,

the licensee is conclusively deemed to be the attorney of that owner for the purpose of executing the conveyance or instrument on that owner's behalf.

The registrar must register the licensee as owner of the land affected, or as holder of a charge on that land, as indicated in the award, if the licensee

pays the amount of compensation to the comptroller, or the part of that amount that is payable at the time, that has not been accepted by the owner,

files with the registrar

the executed conveyance or instrument,

a copy of the award, and

iii

a signed statement confirming the payment of the compensation to the comptroller and the failure of the owner to execute the conveyance or instrument, and

pays to the registrar the applicable fees under the Land Title Act .

Owner to give notice before interfering with works

Despite a right or title acquired or held under a statute or an indefeasible or absolute title held in relation to land, the owner of land or another person who proposes to alter, move, fill in, remove or otherwise interfere with works constructed or used under an authorization must, before doing so, give the holder of the authorization 180 days' written notice of the act or thing proposed to be done.

Entry on land in case of urgency

If the comptroller or a water manager considers that a delay in beginning the construction of authorized works, or works necessarily required for the proper diversion or use of water under a licence,

would not be in the public interest, or

would cause a hardship on the licensee,

the decision maker may authorize the licensee to enter on, occupy and use any land for constructing the works.

The decision maker under subsection (1) may require, as a condition of the authority given, that the licensee provide security to the decision maker in the amount the decision maker considers sufficient to indemnify the owner of the land for any damage that owner might sustain by reason of the construction.

On exercising an authority under subsection (1), the licensee must promptly take steps under

section 32 [licensee's right to expropriate land] to expropriate the land required.

A person, including the owner of the land, must not interfere with the construction of the works so long as the licensee diligently prosecutes the expropriation proceedings.

Joint construction or use of works may be ordered

Power to authorize extension of rights under licence

respecting the use of the water or works necessarily required to be used for that use,

providing for compensation as between the licensee and a person who is receiving the benefit of the extension, or

limiting the term of the extension.

Appointment of water bailiffs

operate and inspect the operation of specified works, and

perform routine repairs on and maintain specified works.

A water bailiff, under the direction of an engineer, which direction must be consistent with the directions given under subsection (1) or (2) and may be given by the engineer in person or through an officer, may

take action or measurements in respect of the diversion or use of water from the streams and aquifers specified in the water bailiff's appointment,

take action in respect of works related to the diversion or use of the water, and

inspect, operate, perform routine repairs on and maintain those works.

A water bailiff who takes action or measurements under subsection (2) or (3) must keep records of anything the water bailiff does under this section, including, without limitation, actions and measurements taken, work performed, hours of work and expenses incurred, and provide the records to the engineer.

Persons, whether or not those persons hold an authorization, who divert or use water from the streams or aquifers in respect of which a water bailiff exercises powers or performs duties under this

section are liable to

compensate the water bailiff in the amounts and at the times the engineer who directs the water bailiff orders, and

reimburse the water bailiff as directed by the engineer for the amounts that the engineer considers were reasonably incurred by the water bailiff in maintaining, operating or repairing the works.

A water bailiff may stop the diversion or use of water, and the operation of works, by or on behalf of a person who fails to pay amounts owing to the water bailiff under subsection (5).

If a water bailiff assigns to the government all the water bailiff's right, title and interest in and to the indebtedness for amounts payable to the water bailiff under subsection (5), those amounts may be recovered under

section 98 [recovery of amounts owing for work performed] as a debt of the persons liable under subsection (5) of this

section that is due to the government.

Water reservations

If the Lieutenant Governor in Council considers it advisable

to enable a specified person to investigate the suitability of a stream or an aquifer for a specified water use purpose,

to make provision for a water supply from a stream or an aquifer for a proposed waterworks, irrigation or power system or project of a specified person,

to ensure water from a stream or an aquifer is available for the benefit of the Crown, or

to retain the reserved water in a stream or an aquifer,

the Lieutenant Governor in Council may reserve all or part of the water that is in the stream or the aquifer, and that is unrecorded and unreserved and is not dedicated agricultural water, from being diverted or used under this Act except as provided by

section 6 (2), (3) or (4) [use of water] .

The minister must publish a notice in the Gazette giving particulars of a reservation established or amended under subsection (1).

A reservation under subsection (1) established

in relation to all the unrecorded water in a stream or an aquifer applies to water, other than dedicated agricultural water, that by reason of the expiry, abandonment or cancellation of all or part of the rights under an authorization becomes unrecorded water in the stream or aquifer during the existence of the reservation, and

in relation to a specified quantity of water in a stream or an aquifer applies to water that by reason of the expiry, abandonment or cancellation of all or part of the rights under an authorization issued under subsection (4) (

c) for water that is subject to the reservation becomes unrecorded water during the existence of the reservation.

The Lieutenant Governor in Council, in an order under subsection (1) or in a subsequent order, may provide that water reserved under subsection (1), despite the reservation, may be acquired under a licence,

for a reservation under subsection (1) (

a) or (b), by the specified person, or a person authorized by the specified person, for the water use purpose, or for the waterworks, irrigation or power system or project, as applicable, for which the water is reserved,

for a reservation under subsection (1) (c), by the Crown or a person authorized by the Crown,

for a reservation under subsection (1) (a), (

b) or (c), by any person for another water use purpose, but the rights under a licence issued under this paragraph must be given a later date of precedence than rights under any licence referred to in paragraph (

a) or (

b) of this subsection in respect of the water reserved, whether the licence for the other water use purpose is issued before or after the licence referred to in paragraph (

a) or (b), and

for a reservation under subsection (1) (d), by a specified person for a water use purpose the Lieutenant Governor in Council considers is consistent with the purposes of the reservation.

The Lieutenant Governor in Council may cancel a reservation established under subsection (1) effective on a specified date, which date must not be earlier than 30 days after the date of publication of the notice under subsection (6) (a).

The minister must publish notice of a cancellation under subsection (5), specifying the date on which the cancellation is effective,

in the Gazette, and

within 30 days after the publication under paragraph (a), in a newspaper published in the water district in which the stream or the aquifer is located, and if there is no newspaper so published then in a newspaper that circulates in that water district.

Applications for the water reserved under a reservation cancelled under subsection (5) may be accepted during the period between the date the notice of cancellation is published in the Gazette and the effective date of the cancellation, but an authorization issued in respect of the application must not be given a date of precedence that is earlier than the effective date of the cancellation.

Despite subsection (1), a licence may be issued authorizing for domestic purpose or a land improvement purpose the diversion or use of water to which a reservation established under subsection (1) applies.

Despite subsection (1), a use approval may be issued authorizing, for any water use purpose, the diversion and use of water to which a reservation established under subsection (1) applies.

Treaty first nation water reservations

If the final agreement of a treaty first nation describes a water reservation for water use purposes specified in the agreement, other than a power purpose, that British Columbia is required by the final agreement to establish in favour of the treaty first nation, the Lieutenant Governor in Council may establish that water reservation for those purposes.

A water reservation established in favour of a treaty first nation under subsection (1) is deemed to be a water reservation under

section 39 subject to the following:

the water reserved by the water reservation may only be acquired for the purposes, and in the manner, contemplated by the treaty first nation's final agreement;

section 39 (5) to (7) does not apply to that water reservation;

section 39 (8) and (9) does not apply to the water reserved by that water reservation.

Despite anything to the contrary in this Act, a water reservation established under subsection (1) for purposes authorized by the final agreement

is deemed to have been established on the date specified in the final agreement as the reference date for the priority of the water reservation, and

has priority for those purposes over water licences issued after that date in relation to the same stream, except water licences given priority by that final agreement.

Nisg̱a'a water reservation

The Lieutenant Governor in Council may, by order, establish the water reservation, described in paragraph 122 of the Lands

Chapter of the Nisg̱a'a Final Agreement, in favour of the Nisg̱a'a Nation.

The water reservation established under subsection (1) is deemed

to be a water reservation under

section 39 [water reservations] subject to the following:

the water reserved by that water reservation may only be acquired for the purposes and in the manner contemplated by paragraphs 122 to 126 of the Lands

Chapter of the Nisg̱a'a Final Agreement ;

section 39 (5) to (7) does not apply to that water reservation;

iii

section 39 (8) and (9) does not apply to the water reserved by that water reservation, and

to have been made on March 22, 1996 for the purposes of paragraph 123 of the Lands

Chapter of the Nisg̱a'a Final Agreement .

Issue of new licence

If a licence is acquired by

a regional district under

section 289 (2) [expropriation of water licences and related works] of the Local Government Act ,

an improvement district under

section 704 [power to expropriate water diversion licences and related works] of that Act, or

a municipality under

section 31 (2) [expropriation of water licences and related works] of the Community Charter ,

the comptroller may issue in place of the acquired licence a new licence having the same precedence but authorizing the diversion or use of water for any water use purpose required by the regional district, improvement district or municipality, as applicable.

Protecting Water Resources

Water Objectives

Water objectives

For the purposes of sustaining water quantity, water quality and aquatic ecosystems in and for British Columbia, the Lieutenant Governor in Council may make regulations

establishing water objectives for a watershed, stream, aquifer or other specified area or environmental feature or matter in order to sustain

water quality required for specified uses of water,

water quantity required for specified uses of water, and

iii

water quality and water quantity required to sustain aquatic ecosystems

in relation to the watershed, stream, aquifer or other area, feature or matter,

specifying factors and criteria to apply for evaluating the impacts of a land use or resource use proposal on objectives established under paragraph (a), and

respecting measures to address impacts of such proposals on the objectives.

A regulation under this

section may

require that a water objective be considered by a public officer making a specified decision under a specified enactment, if the decision is in relation to the watershed, stream, aquifer or other area or environmental feature or matter for which the water objective was prescribed, and

Despite any other enactment, a regulation under subsection (2) may provide that a specified water objective applies despite or subject to objectives, standards, requirements or plans established in relation to environmental matters under the specified enactment or another specified enactment.

A regulation under this

section may require that

a regional district consider specified water objectives when developing, amending or adopting a regional growth strategy under

Part 13 [Regional Growth Strategies] of the Local Government Act ,

a municipality consider specified water objectives when developing, amending or adopting an official community plan under

Part 14 [Planning and Land Use Management] of the Local Government Act or

Part XXVII [Planning and Development] of the Vancouver Charter ,

a local trust committee consider specified water objectives when developing, amending or adopting an official community plan under

section 29 [land use and subdivision regulation] of the Islands Trust Act , and

a prescribed person or entity consider specified water objectives when developing, amending or enacting plans or undertaking planning processes under prescribed enactments.

Stream Protection

Definitions

For the purposes of this Division:

bank-to-bank dam means

a structure that is capable of impounding or storing water and that spans a stream from bank to bank, or

structures that together are capable of impounding or storing water and that span a stream

from one bank to a natural or other feature or structure in the stream, and

from the feature or structure to the other bank of the stream or, if applicable, between features or structures and to the other bank of the stream;

construction of a bank-to-bank dam includes the alteration of an existing structure so that it becomes a bank-to-bank dam but does not include the alteration of an existing bank-to-bank dam;

protected river means a river set out in the Schedule.

No new dams on protected rivers

A person must not construct a bank-to-bank dam anywhere on a protected river.

The comptroller or a water manager must not issue or amend an authorization, change approval or permit to authorize the construction of a bank-to-bank dam anywhere on a protected river.

An authorization, change approval or permit issued or an amendment made contrary to subsection (2) has no effect.

This

section applies despite any other enactment.

This

section does not apply to a dam authorized by a licence, permit or approval issued under the Water Act before March 15, 1997.

Prohibition on introducing foreign matter into stream

Unless authorized under this or another enactment or excepted under subsection (2), a person must not

introduce debris, refuse, carcasses, human or animal waste, pesticides, fertilizers, contaminants or another matter or substance into a stream, a stream channel or an area adjacent to a stream, or

cause or allow debris, refuse, carcasses, human or animal waste, pesticides, fertilizers, contaminants or another matter or substance to be introduced into a stream, a stream channel or an area adjacent to a stream

in such a quantity or in such a manner as to cause a significant adverse impact to

the stream or stream channel,

the existing uses of the water from the stream,

the property of riparian owners on the stream,

an aquifer that is hydraulically connected to the stream or the existing uses of the water from that aquifer, or

the aquatic ecosystem of the stream.

Subsection (1) does not apply in relation to

a forest practice to which

section 46 [protection of the environment] of the Forest and Range Practices Act applies, or

a prescribed activity, practice or substance.

In a prosecution under

section 106 (4) (n) [general offences] , it is not necessary to prove that the human or animal waste, pesticide, fertilizer, contaminant or other matter or substance, if diluted or its concentration reduced subsequent to the introduction into the stream, continued to cause or to be likely to cause a significant adverse impact on the quality of water in the stream or in an aquifer that is hydraulically connected to the stream or the uses made of the water from the stream or aquifer that is hydraulically connected to the stream.

Remediation orders in relation to foreign matter in stream

An engineer may order a person who contravenes

section 46 (1) [prohibition on introducing foreign matter into stream] to

stop the introduction of debris, refuse, carcasses, human or animal waste, pesticides, fertilizers, contaminants or other matter or substance into the stream, the stream channel or an area adjacent to the stream,

remove the debris, refuse, carcasses, human or animal waste, pesticides, fertilizers, contaminants or other matter or substance from the stream, the stream channel, the area adjacent to the stream or an aquifer that is hydraulically connected to the stream and to which the matter or substance has migrated, and

take measures, in accordance with the direction of the engineer, to remediate or mitigate the effects of the introduction.

If the engineer considers that the effects of an introduction described in subsection (1) (

a) cannot be remediated, or cannot be fully remediated, at the location of the introduction, that engineer may order the person referred to in subsection (1) to take compensatory mitigation measures, in place of or supplemental to other remediation measures, on a different part of the stream into which the introduction was made.

The comptroller or a water manager may authorize the government or another person to take the actions necessary to comply with an order under subsection (1), and the person who contravened

section 46 (1) is liable to the government or that other person, as applicable, for the costs of complying with the order if any of the following apply:

the person who is subject to an order under subsection (1) fails to comply with the order within the time specified in the order;

the person who contravened

section 46 (1) cannot be identified or located after reasonable effort;

the comptroller or the water manager considers that failure to remediate or mitigate the introduction immediately may result in harm or damage to anything referred to in

section 46 (1) (

c) to (g).

Any expense reasonably incurred by a person in the exercise of authority provided under subsection (3), unless the person is acting on behalf of the government, may be recovered from the person to whom the order was directed as money paid for, and at the request of, that person.

If work is carried out under subsection (3) by or on behalf of the government, the costs to the government are a debt due to the government by the person to whom the order was directed and may be recovered in accordance with

section 98 [recovery of amounts owing for work performed] .

This

section does not limit the authority under

section 91 [power of comptroller to authorize actions] or 93 [powers of engineers and officers] .

Wells and Groundwater Protection

Definitions

For the purposes of this Division:

person responsible , with respect to constructing a well, installing a well pump, conducting a flow test or decommissioning a well, means,

if the activity is supervised by a professional, that professional,

if paragraph (

a) does not apply and the activity is supervised or performed by a well driller or well pump installer who is qualified to supervise or perform that activity, that well driller or well pump installer,

if neither paragraph (

a) nor (

b) applies, a person who performs the activity in the ordinary course of that person's business, and

if none of paragraphs (a), (

b) or (

c) applies, the person on whose behalf the activity is performed;

professional means a registrant as defined in

section 5 of

Schedule 1 to the Professional Governance Act ;

qualified , in respect of an activity in relation to a well or well pump,

for a well driller, means a well driller who has the qualifications prescribed as required to perform or supervise the activity in relation to the well or well pump, and

for a well pump installer, means a well pump installer who has the qualifications prescribed as required to perform or supervise the activity in relation to the well or well pump;

well includes any casing, screen, drive shoe, packer, riser pipe, cap, valve, grout, liner and seal relating to a well;

well driller means a person who has the prescribed qualifications;

well pump installer means a person who has the prescribed qualifications.

For the purposes of this Division, a person's actions are directly supervised by another person if that other person is responsible for the control and conduct of the person's actions.

Restrictions on constructing or decommissioning wells and related activities

Subject to

section 50, this

section applies to a person who

constructs a well,

decommissions a well,

deactivates a well, or

disinfects a well.

A person referred to in subsection (1) must

comply with the applicable regulations,

in the case of an activity referred to in subsection (1) (a), (

b) or (c), either

be a well driller who is qualified in respect of the activity in relation to the well, or

act under the direct supervision of

a person described in subparagraph (i), or

a professional who has competency in the field of hydrogeology or geotechnical engineering, and

in the case of an activity referred to in subsection (1) (d), be a person described in paragraph (

b) or a well pump installer described in

section 50 (2) (b) (i), or act under the direct supervision of a person described in

section 50 (2) (b) (ii).

Unless provided otherwise by a regulation under

section 83 [plan regulations — restrictions on groundwater activities] or 137 [minister's regulations restricting groundwater activities] , subsection (2) (

b) or (

c) of this

section does not apply in respect of the following:

a person

excavating a well to a depth of not more than 15 m, or

performing an activity referred to in subsection (1) with respect to an excavated well that has a depth of not more than 15 m;

a person deactivating or disinfecting a well owned by the person;

a person constructing or decommissioning a geotechnical well, if the activity of constructing or decommissioning the well is not likely to penetrate an aquifer;

a person installing, replacing or repairing, on a well owned by the person,

a flow meter, or

a well cap, well cover, valve or vent that is part of the wellhead and accessible at the surface of the ground;

a prescribed

person,

well,

iii

activity in relation to a prescribed work, or

activity.

A person who, in performing an activity referred to in subsection (3) (

c) or prescribed under subsection (3) (e), penetrates an aquifer must stop performing that activity until the person has complied with subsection (2) (

b) and must take the steps recommended by the person described in that subsection.

Restrictions respecting well pumps and flow tests

This

section applies to a person who

installs, maintains, repairs, removes or tests a well pump or a wellhead,

conducts a flow test of a well, or

disinfects a well pump.

A person referred to in subsection (1) must

comply with the applicable regulations, and

either

be a well pump installer or well driller who is qualified in respect of the activity in relation to the well, or

act under the direct supervision of

a person described in subparagraph (i), or

a professional who has competency in the field of hydrogeology or geotechnical engineering.

Despite subsection (2) (b) (

i) and (ii) (A), if the regulations require that an activity described in subsection (1) be performed or directly supervised only by a professional who has competency in the field of hydrogeology or geotechnical engineering, that activity must be performed or directly supervised by a professional who is so qualified.

Unless provided otherwise by a regulation under

section 83 [plan regulations — restrictions on groundwater activities] or 137 [minister's regulations restricting groundwater activities] , subsections (2) (

b) and (3) do not apply in respect of the following:

a person installing a well pump in a monitoring well, a geotechnical well or a closed-loop geoexchange well;

a person disinfecting a well pump owned by the person;

a prescribed

person,

well or well pump,

iii

activity in relation to a prescribed work, or

activity.

Proof of qualifications and insurance

On the direction of

the comptroller,

a water manager,

an engineer,

an officer, or

a drinking water officer,

a person who is performing or directly supervising an activity that under this Act must be performed or directly supervised by a professional with specified competencies, or by a well driller or well pump installer who is qualified in respect of the activity in relation to the well, must immediately provide proof that the person is qualified to perform or supervise the activity and, if the person is required under subsection (2) to carry insurance, proof of that insurance.

If the regulations require that a professional or a well driller carry not less than the prescribed amount of liability insurance in the event of liability arising from the performance or supervision of activities under this Act, the professional or well driller, as applicable, must carry that amount.

When asked to do so, a professional, a well driller or a well pump installer must provide to any person who engages the professional, well driller or well pump installer to perform or supervise activities under this Act

proof of insurance, if insurance is required under the regulations, and

proof of qualifications.

Controlling artesian flow during construction

For the purposes of this

section and

section 53, artesian flow of a well is under control when

the artesian flow

is clear of sediment,

is entirely conveyed through the well's production casing to the wellhead, if the well has a production casing,

iii

may be mechanically stopped for an indefinite period in a manner that prevents leakage onto the surface of the ground or into another aquifer penetrated by the well, and

does not pose a threat to property, public safety or the environment, or

if the artesian flow cannot be controlled in accordance with paragraph (a), the well is decommissioned

in accordance with the regulations,

by a person authorized under

section 49 [restrictions on constructing or decommissioning wells] , and

iii

in a manner that allows no artesian flow at the surface of the ground or leakage into another aquifer penetrated by the well.

If a well driller or a professional encounters artesian conditions while constructing a well or supervising the construction of a well, the well driller or professional must ensure, as soon as practicable, that

any artesian flow is stopped or brought under control, or

if the artesian well is likely to flow periodically, steps are taken to ensure that that artesian flow will be stopped or controlled during those periods.

A person, other than a well driller or a professional, who, while constructing a well, encounters

flowing artesian conditions, or

artesian conditions that indicate the artesian well is likely to flow periodically,

must notify the well owner of the encounter and the person and the well owner must ensure that a well driller who is qualified in respect of the activity or a professional is engaged, and that well driller or professional must comply with subsection (2) in relation to the artesian flow.

A well driller or professional who encounters or takes steps to stop or control artesian flow must notify the well owner and the land owner of the encounter and the steps taken.

If the well driller or professional described in subsection (2) or engaged under subsection (3) fails to comply with subsection (2), the well owner must ensure that a well driller who is qualified in respect of the activity or a professional complies with subsection (2).

If the comptroller or a water manager is satisfied, based on the report of a professional, that because of exceptional circumstances it is not practicable to bring artesian flow under control in accordance with subsection (1) (

a) or (

b) but the artesian flow can be managed in another manner without posing a threat to property, public safety or the environment, the artesian flow may be brought under control in accordance with the directions of the decision maker.

A person responsible for stopping or controlling artesian flow under this

section must comply with any applicable regulations and any directions of an engineer in relation to stopping or controlling the flow.

Controlling flowing artesian well

The owner of a flowing artesian well must engage a well driller who is qualified in respect of the activity or a professional and ensure that the well driller or professional, as applicable, stops the flow of that well or brings the flow of that well under control.

If the owner of a flowing artesian well fails to comply with subsection (1) and the owner of the land on which the well is located does not know who owns the well, the owner of that land must comply with subsection (1).

Section 52 (6) and (7) apply for the purposes of this section.

Well caps or well covers

The following persons must secure a well cap or well cover on a well in accordance with the regulations:

a person who drills a well or alters a well;

a person who owns a well that does not have a well cap or well cover secured on the well.

If a well owner does not comply with subsection (1) (

b) and the owner of the land on which the well is located does not know who owns the well, the owner of that land must comply with subsection (1) (b).

A person must not remove the well cap or well cover from a well except for the purpose of

inspecting, developing, disinfecting, maintaining, repairing or altering the well or inspecting, maintaining, repairing, replacing or altering works associated with the well,

installing, re-installing, removing or testing a well pump,

testing the flow of the well,

measuring the water level in the well,

taking a water sample from the well, or

undertaking similar activities that require temporary removal of the well cap or well cover.

A person who temporarily removes a well cap or well cover as authorized under subsection (3) must replace the cap or cover in accordance with the regulations as soon as practicable after completing the work for which that cap or cover was removed.

A person must not destroy, injure or tamper with a well cap or well cover.

Well identification

In this section, "owner" and "water supply system" have the same meaning as in

section 1 [definitions] of the Drinking Water Protection Act .

The following persons must attach an identification plate to a well or wellhead in accordance with the regulations:

a person responsible for drilling a well or altering a well that does not have an identification plate attached;

unless a plate is attached under paragraph (a), the owner of a water supply system.

Subsection (2) does not apply in respect of a monitoring well, a geotechnical well, a closed-loop geoexchange well or a well made for the purpose of groundwater remediation.

A person who is required to attach an identification plate under this

section must submit a report in accordance with the regulations to

the comptroller, and

a water manager, an engineer or an officer, if directed to do so by that official.

A person who decommissions a well must remove and destroy the identification plate referred to in subsection (2).

Decommissioning or deactivating well

For the purposes of this section, a well is considered to be in service if

the well is used regularly or on a periodic basis, or

the well is kept active as a backup water supply.

Despite subsection (1), a well is considered to be not in service

if the well is not used for the prescribed period, or

in prescribed circumstances.

If a well is, in accordance with subsection (2), not in service, the well owner must ensure that the well is deactivated or decommissioned as soon as practicable in accordance with the regulations and by a person authorized under

section 49 [restrictions on constructing or decommissioning wells and related activities] of this Act.

If a deactivated well is not in service for the prescribed period, the well owner must ensure that the well is decommissioned as soon as practicable in accordance with the regulations and by a person authorized under

section 49 of this Act.

Despite the period prescribed for the purposes of subsection (4), if the comptroller or a water manager is satisfied that a well is being properly maintained as a deactivated well for later use, the decision maker may extend that prescribed period.

If the owner of the land on which the well is located does not know who owns the well, the owner of the land must comply with subsections (3) and (4).

Well reports

Subject to the regulations, a person responsible for

constructing a well,

installing a well pump,

conducting a flow test of a well, or

decommissioning a well

must maintain a daily log containing the prescribed information and must complete a report in accordance with the regulations.

The person referred to in subsection (1) must retain and produce at the direction of an officer, an engineer or a drinking water officer the log and report required under subsection (1).

A person who is required under subsection (1) to complete a report must submit a copy of the report in accordance with the regulations to

the well owner,

in prescribed circumstances, for prescribed wells or if artesian flow is encountered in constructing the well, the comptroller, and

if directed to do so by the comptroller, a water manager, an engineer, an officer or a drinking water officer, that official.

Despite

section 117 (4) [delivery and publication of documents and information] , the comptroller must publish reports received under subsection (3) (

b) and may publish reports received under subsection (3) (c), whether or not a report includes personal information.

Well operation

A person must operate a well in accordance with the regulations and any directions of an engineer in respect of the well.

A person must not operate a well in a manner that causes or is likely to cause

the intrusion of saline groundwater, sea water or contaminated water into

the aquifer from which that well diverts water,

another aquifer, or

iii

a stream that is hydraulically connected to an aquifer referred to in subparagraph (

i) or (ii), and

a significant adverse impact on

the quality of water in

the aquifer from which a well diverts water,

another aquifer, or

a stream that is hydraulically connected to an aquifer referred to in clause (

A) or (B), or

the existing uses made of the water diverted from

a well that diverts water from the aquifer,

a well that diverts water from another aquifer, or

a stream that is hydraulically connected to an aquifer referred to in clause (

A) or (B).

Subsection (2) does not apply

to a well made for the purpose of groundwater remediation, or

with respect to a prescribed activity in relation to a prescribed class of well.

In a prosecution under

section 106 (5) (i) [general offences] , it is not necessary to prove that the saline groundwater, sea water or contaminated water, as applicable, if diluted subsequent to the intrusion, continued to cause or to be likely to cause a significant adverse impact on, as applicable,

the quality of water in

the aquifer from which the well diverts water,

another aquifer, or

iii

a stream that is hydraulically connected to an aquifer referred to in subparagraph (

i) or (ii), or

the existing uses made of the water

from any well that diverts water from the aquifer,

from any well that diverts water from another aquifer, or

iii

diverted from a stream that is hydraulically connected to an aquifer referred to in subparagraph (

i) or (ii).

Prohibition on introducing foreign matter into well

A person must not introduce, allow to be introduced or cause to be introduced any of the following into a well:

refuse;

carcasses;

human or animal waste;

pesticides or fertilizers;

material from construction or demolition;

a prescribed matter or substance;

another contaminant, clay, silt, rock or a similar material, or another matter or substance, in such amounts or in such a manner as to cause or to be likely to cause a significant adverse impact on

the quality of water in

the well,

another well that diverts water from the same aquifer,

another aquifer, or

a stream that is hydraulically connected to an aquifer referred to in clause (

B) or (C), or

the existing uses made of the water from

the well,

another well that diverts water from the same aquifer,

another aquifer, or

a stream that is hydraulically connected to an aquifer referred to in clause (

B) or (C).

Subsection (1) does not apply with respect to

a well owner in the proper operation, disinfection, maintenance, repair, deactivating or decommissioning of a well in accordance with the regulations,

a well made for the purpose of groundwater remediation,

activities authorized or required under an enactment,

a prescribed contaminant, matter or substance.

In a prosecution under

section 106 (5) (k) [general offences] , it is not necessary to prove that the contaminant, matter or substance, if diluted or its concentration is reduced subsequent to the introduction into the well, continued to cause or to be likely to cause a significant adverse impact on, as applicable,

the quality of water in

the well,

another well that diverts water from the same aquifer,

iii

another aquifer, or

a stream that is hydraulically connected to an aquifer referred to in subparagraph (ii) or (iii), or

the existing uses made of the water from

the well,

another well that diverts water from the same aquifer,

iii

another aquifer, or

a stream that is hydraulically connected to an aquifer referred to in subparagraph (ii) or (iii).

Remediation orders in relation to foreign matter in well

An engineer may order a person who contravenes

section 58 (2) or 59 (1)

to stop the introduction of,

to remove, or

to take measures, as directed by the engineer, to remediate or mitigate the effects of the introduction of

any thing, contaminant, matter or substance introduced into a well contrary to

section 58 (2) or 59 (1).

If the engineer considers that the effects of an introduction described in subsection (1) cannot be remediated, or cannot be fully remediated, at the location of the introduction, that engineer may order the person referred to in subsection (1) to take compensatory mitigation measures, in place of or supplemental to other remediation measures, on a different part of the aquifer into which the introduction was made.

If the engineer cannot ascertain who contravened

section 58 (2) or 59 (1), as applicable, the engineer may make an order under subsection (1) or (2) against the well owner.

If the engineer cannot ascertain who contravened

section 58 (2) or 59 (1), as applicable, or who owns the well, the engineer may make an order under subsection (1) or (2) against the owner of the land on which the well is located.

The comptroller or a water manager may authorize the government or another person to take the actions necessary to comply with an order under subsection (1), and the person to whom the order was directed is liable for the costs to the government or that other person, as applicable, of complying with the order if

a person who is subject to an order under subsection (1), (2), (3) or (4) fails to comply with that order, and

the comptroller or the water manager considers that the failure may result in harm or damage to water in the aquifer, in another aquifer or in a stream that is hydraulically connect to either aquifer.

Any expense reasonably incurred by the other person, unless that person is acting on behalf of the government, in the exercise of authority provided under subsection (5), may be recovered from the person liable as money paid for, and at the request of, that person.

If work is carried out under subsection (5) by or on behalf of the government, the costs to the government are a debt due to the government by the person liable and may be recovered in accordance with

section 98 [recovery of amounts owing for work performed] .

This

section does not limit the authority under

section 91 [power of comptroller to authorize actions] or 93 [powers of engineers and officers] .

Wells on Crown land

Sections 53 [controlling flowing artesian well] , 54 [well caps or well covers] , 56 [decommissioning or deactivating well] and 59 [prohibition on introducing foreign matter into well] do not apply to the government as the owner of land on which a well is located unless

the well was drilled by or on behalf of the government, or

the well was purchased by the government.

If, on or after November 1, 2004, a person

has a right to use or occupy Crown land on which a well is constructed or located, and

fails to comply with

section 53, 54, 56 or 59,

the government may enforce the applicable provision against the person as if that person were the owner of the land on which the well is located, despite any subsequent termination of the right to use or occupy the land.

Drilling authorizations

If a regulation under

section 83 [plan regulations — restrictions on groundwater activities] or 137 [minister's regulations restricting groundwater activities] of this Act or under

section 36 [implementing a plan: restrictions on groundwater activities] of the Drinking Water Protection Act requires that a person hold a drilling authorization in order to

drill a well,

alter a well,

install a well pump, or

conduct a flow test,

the person must not engage in the restricted activity without holding a drilling authorization issued in accordance with this section.

In considering an application for a drilling authorization, the decision maker must consider, as applicable,

the water sustainability plan in respect of which the regulation is made under

section 83,

the purpose identified in the minister's regulation under

section 137, or

the drinking water protection plan the regulations implement.

The decision maker must not issue a drilling authorization unless

the applicant is the owner of the land on which the well and any works related to the well are or will be located,

the land on which the well and any works related to the well are or will be located is Crown land, or

if neither paragraph (

a) nor (

b) applies, the applicant submits the prescribed evidence of the consent of the owner of the applicable land.

this Act and the regulations,

orders of the comptroller, a water manager or an engineer, or

any other enactment.

If a regulation under

section 83 of this Act or under

section 36 of the Drinking Water Protection Act prohibits an activity referred to in subsection (1) of this section, an application for a drilling authorization authorizing the activity in the area to which the prohibition applies may not be considered.

Water analyses for new or altered wells

If a well is drilled or prescribed alterations are made to a well, the person responsible for a prescribed activity in relation to the well, or another person in prescribed circumstances, must, in accordance with the regulations,

take or cause to be taken a sample of the groundwater in the well, and

cause the sample to be analyzed.

If the groundwater in a well is to be used for domestic purposes as defined in

section 1 [definitions] of the Drinking Water Protection Act , the sampling and the analyses of the groundwater required by regulations referred to in subsection (1) of this

section must also comply with the requirements under that Act.

A person who is required by regulations under subsection (1) to have groundwater samples analyzed must submit a copy of the results of the analyses, in the prescribed time and manner, to

the comptroller,

the well owner, and

if directed to do so by a water manager, an engineer, an officer or a drinking water officer, that official.

Subject to

section 117 (4) [delivery and publication of documents and information] , the comptroller must publish results received by the comptroller under subsection (3).

Water Sustainability Plans

Definitions

For the purposes of this Division:

local authority means

the council of a municipality,

the board of a regional district,

a local trust committee,

an improvement district or greater board, or

a body prescribed by regulation as a local authority for the purposes of a particular water sustainability plan;

plan regulation means a regulation under

section 76 [plan regulations — effect on statutory decisions] ,

section 77 [plan regulations — effect on approval by approving officer] ,

section 78 [plan regulations — restriction or prohibition on use of land or resources] ,

section 79 [plan regulations — reduction of water rights] ,

section 80 [plan regulations — directions regarding works or operations] ,

section 81 [plan regulations — relationship with other planning processes] ,

section 82 [plan regulations — dedicated agricultural water] , and

section 83 [plan regulations — restrictions on groundwater activities] ;

responsible person , in respect of a proposed water sustainability plan, means the person designated by the minister under

section 66 (2) (a) [order establishing plan development process] as the person responsible for preparing the proposed plan;

significant change means a change in relation to a licence or a drilling authorization, whether the change is voluntary or involuntary, that is recommended by a proposed water sustainability plan and that, if implemented, would,

in the case of a licence,

significantly reduce the quantity of water that the licensee is authorized to divert under the licence,

result in significantly different works than the works authorized under the licence,

iii

restrict the water use purposes for which water may be used under the licence, or

cancel the licence, and

in the case of a drilling authorization, cancel the drilling authorization.

Order designating area for planning process

The minister, on request or on the minister's own initiative, by order, may designate an area for the purpose of the development of a water sustainability plan

if the minister considers that a plan for the area will assist in

preventing or addressing

conflicts between water users,

conflicts between the needs of water users and environmental flow needs,

risks to water quality, or

risks to aquatic ecosystem health, or

identifying restoration measures in relation to a damaged aquatic ecosystem, or

in other prescribed circumstances.

A request to the minister referred to in subsection (1) must

be made in the prescribed manner, if any, and

include the prescribed information, if any.

An order under subsection (1) must include the reasons for which the order is made.

Section 124 (4) (d) [general regulation-making powers] applies to an area designation under subsection (1) of this section.

Order establishing plan development process

The minister, by order, may establish the process by which a proposed water sustainability plan for a plan area is to be developed.

Without limiting subsection (1), an order under that subsection may do one or more of the following:

designate the government or another person as the person responsible for preparing the proposed plan;

if the government is the responsible person,

establish the terms of reference for the plan, and

establish one or more technical advisory committees in relation to development of the plan;

if a person other than the government is the responsible person,

authorize the responsible person to prepare the terms of reference for the plan, subject to approval by the minister, and

require the responsible person to establish one or more technical advisory committees in relation to development of the plan;

subject to subsection (3), do one or more of the following:

provide whether remuner

Document details

CollectionBritish Columbia — Consolidated Statutes
Citationstatreg 14015
Typestatute
Volume / chapterstatreg 14015
Languageen
Formatxml
SourcePROVINCIAL
Identifier147ad7584a74afdb64feb6f6e43fee715b947250