British Columbia Hansard — TUESDAY, FEBRUARY 22, 2005 (37th Parliament, 6th Session) (20050222pm-Hansard-v27n15)
20050222pm-Hansard-v27n15
British Columbia — Debates (Hansard)
2005 Legislative Session: 6th Session, 37th Parliament
HANSARD
The following electronic version is for informational purposes
only.
The printed version remains the official version.
Official Report of
DEBATES OF THE LEGISLATIVE ASSEMBLY
(Hansard)
TUESDAY, FEBRUARY 22, 2005
Afternoon Sitting
Volume 27, Number 15
CONTENTS
Routine Proceedings
Page
Introductions by Members
Statements (Standing Order 25 B )
Youth in Philanthropy
S. Orr
Czorny Alzheimer Centre
D. Hayer
2010 Olympics countdown events in
Cariboo area
W. Cobb
Oral Questions
Surrey Memorial Hospital services and
termination of Fraser health authority CEO
J. Kwan
Hon. S. Bond
J. MacPhail
Surrey Memorial Hospital services and
Health estimates debate
J. Brar
Hon. S. Bond
Hon. G. Bruce
Cancer clinic in Prince George
P. Nettleton
Hon. S. Bond
Health care services in B.C.
E. Brenzinger
Hon. S. Bond
Severance payment for Fraser health
authority CEO
J. MacPhail
Hon. S. Bond
Reports from Committees
Standing Committee on Education
A Future
for Learners: The Path to Renewal of Education in British Columbia
R. Stewart
Committee of Supply
Supplementary Estimates (No. 5): Ministry of
Transportation (continued)
J. MacPhail
Hon. K. Falcon
J. Brar
Introduction and First Reading of
Bills
Supply Act, 2004-2005 (Supplementary
Estimates No. 5) (Bill 12)
Hon. C. Hansen
Second Reading of Bills
Supply Act, 2004-2005 (Supplementary
Estimates No. 5) (Bill 12)
Hon. C. Hansen
Committee of the Whole House
Supply Act, 2004-2005 (Supplementary
Estimates No. 5) (Bill 12)
Report and Third Reading of Bills
Supply Act, 2004-2005 (Supplementary
Estimates No. 5) (Bill 12)
Committee of Supply
Supplementary Estimates (No. 6): Officers of
the Legislature
Introduction and First Reading of
Bills
Supply Act, 2004-2005 (Supplementary
Estimates No. 6) (Bill 13)
Hon. C. Hansen
Second Reading of Bills
Supply Act, 2004-2005 (Supplementary
Estimates No. 6) (Bill 13)
Hon. C. Hansen
Committee of the Whole House
Supply Act, 2004-2005 (Supplementary
Estimates No. 6) (Bill 13)
Report and Third Reading of Bills
Supply Act, 2004-2005 (Supplementary
Estimates No. 6) (Bill 13)
Committee of Supply
Supplementary Estimates (No. 7):
Ministry of Community, Aboriginal and Women's Services
Hon. M. Coell
J. Kwan
B. Lekstrom
Introduction and First Reading of
Bills
Supply Act, 2004-2005 (Supplementary
Estimates No. 7) (Bill 14)
Hon. C. Hansen
Second Reading of Bills
Supply Act, 2004-2005 (Supplementary
Estimates No. 7) (Bill 14)
Hon. C. Hansen
Committee of the Whole House
Supply Act, 2004-2005 (Supplementary
Estimates No. 7) (Bill 14)
Report and Third Reading of Bills
Supply Act, 2004-2005 (Supplementary
Estimates No. 7) (Bill 14)
Committee of Supply
Supplementary Estimates (No. 8): Ministry of
Advanced Education
Hon. I. Chong
J. Kwan
Introduction and First Reading of
Bills
Supply Act, 2004-2005 (Supplementary
Estimates No. 8) (Bill 15)
Hon. C. Hansen
Second Reading of Bills
Supply Act, 2004-2005 (Supplementary
Estimates No. 8) (Bill 15)
Hon. C. Hansen
Committee of the Whole House
Supply Act, 2004-2005 (Supplementary
Estimates No. 8) (Bill 15)
Report and Third Reading of Bills
Supply Act, 2004-2005 (Supplementary
Estimates No. 8) (Bill 15)
Royal Assent to Bills
Miscellaneous Statutes Amendment Act,
2005 (Bill 3)
Attorney General Statutes Amendment
Act, 2005 (Bill 4)
[ Page 12039 ]
TUESDAY, FEBRUARY 22, 2005
The House met at 2:03 p.m.
Introductions by Members
Hon. I. Chong: Today I'm privileged to introduce some very
special and talented young guests. Before I do so, I'd like to just preface my
remarks. There's no question as to our government's and our Premier's commitment
to literacy, and this is evidenced by the literacy summit we held last November,
as well as the matching funds towards the Raise-a-Reader campaign, and mostly
recently in the throne speech, where one of the goals is to have the most
educated and literate jurisdictions on the continent.
Last November I invited all grade 6 students in my riding of Oak
Bay–Gordon Head, including home-school students, to participate in an essay
contest, the title subject of which was "B.C. is the Best Place on Earth." I am
delighted today that five essay winners joined me, along with their parents, for
lunch in the dining room and then a very brief tour of the Legislature.
I would like to introduce to this House a young lady from Willows
Elementary, Wynter Caron, and her father, Bradley Wotis. Also from Willows
Elementary is Alex Gurney, with her father, Mr. Blair Gurney. From Arbutus
Middle School, Megan Griffin, with her father, Jim Griffin, and her mother,
Susan Phillips. Also from Arbutus Middle School, Miranda Meijer, with her
mother, Gina. From Gordon Head Elementary, Jessica Round, with her father,
Adrian. Would the House please make them all very welcome.
[1405]
S. Orr: Today I would like to introduce five very special
friends that are visiting us today. First is a very, very dear friend of mine,
Vicki Kuhl, who is no stranger to this community. Vicki is a former Saanich
councillor. She is now on the Saanich police board. She is a director of the
Victoria Airport Authority and also serves as a governor for the Victoria
Foundation. With her is Paul Senez, who is the coordinator of the Victoria
Foundation Youth in Philanthropy program, and also three wonderful students who
are involved in the Youth in Philanthropy programs. Two students are Kate
Dearden and Alan Manning, and they're here from Oak Bay Secondary. The other
student, Katrina Kala, is from Lambrick Park Secondary. Actually, both of these
schools are in the member for Oak Bay–Gordon Head's riding, and I know for a
fact that she visits and is involved in these schools all the time. Would the
House make please make all my guests welcome.
Hon. M. Coell: In the House today I have some guests from
my constituency: 19 members of the Probus Club of Sidney, with Alan Lester as
their leader. Would the House please make them welcome.
B. Lekstrom: It's a privilege to rise in the House today to
introduce a guest of one of our workers, Devon Keller, from the PAB. Today we
have one of her friends visiting us from Toronto, Ontario. I understand that
this is not her first visit to beautiful British Columbia. Apparently it seems
to be growing on her. So I would like the House to welcome Joselyn Nalasco to
British Columbia and to the Legislature.
C. Clark: On my own behalf and on behalf of the member for
Chilliwack-Kent, I'd like to welcome the former Attorney General of British
Columbia, Alex Macdonald — my favourite silk-stocking socialist — to view the
proceedings from the gallery today.
R. Hawes: In the gallery today is Elsa Bokelman. Elsa is a
constituent from Maple Ridge who is here on behalf of a number of specialists
and GPs from South Africa that are…. She was here to discuss immigration issues
with the Minister of State for Immigration Services and the Minister of
Community, Aboriginal and Women's Services. Could the House make Elsa welcome.
V. Anderson: Today we have in the Legislature 90 energetic
young students from Jamieson Elementary School in Vancouver, in my riding. They
are accompanied by their teachers, Mr. Milo Wu, Ms. Flora Chen and Ms. Yvonne
Lam, and by their parents. They are here to attend question period and learn
look forward to meeting them after they have been to the Legislature, but would
the House make them welcome.
J. Bray: Joining us in the gallery today is Bernie Pauly.
Bernie is finishing her dissertation for nursing. Bernie has also been very
involved in, and on the board of, the James Bay Community Project, as well as an
active parent in South Park Family School and an all-round great community
person. I'd ask the House to please make Bernie very welcome.
Hon. P. Wong: In the gallery today we have several guests
from China: Mr. Ri Tao Ni and his assistant, Ms. Susanna Xu, and Ms. Yan Zhang.
They are coming here to look for business opportunities in British Columbia.
Would the House please make them most welcome.
P. Nettleton: I would ask that you join me in welcoming two
dear friends from Victoria. These ladies are long-time residents of Victoria —
seniors. Please join me in welcoming them today.
[1410]
Hon. P. Bell: Today I see we're joined by one of our
legislative interns, who also happens to come originally from the riding of
Prince George North, attended UNBC and graduated with a degree in political
science there. I ask that the House please make Alayna van Leeuwen welcome.
P. Nettleton: I had a birthday a few days ago, and I think
the effect of that is beginning to show. In any
[ Page 12040 ]
event, I forgot to name my dear friends from Victoria, Joy and Pauline
Culpersmith.
Mr. Speaker: Hon. members, although he is not present in
the House, I would like you to join me in wishing a happy thirtieth anniversary
to the member for Kamloops–North Thompson and his wife, Debbie.
Statements
(Standing Order 25
b) YOUTH IN PHILANTHROPY
S. Orr: There is nothing more satisfying than being able to
stand up in this chamber and talk about positive things, especially when it is
about our youth. Positive stuff that involves youth, in my opinion, is what
makes the world go around. They are our future. In fact, they are the reason I
do this job — to try and make a better future for them.
I first talked about the Youth in Philanthropy program in 2002,
when it started. This is an in-school, extracurricular program, funded by the
Victoria Foundation, which is designed to engage young people, driven by values,
in learning how to make grants to local charities.
Youth in Philanthropy started in 2002 with three high schools
involved, and it now has grown to six. The schools are Belmont, Frances Kelsey,
Lambrick Park, Oak Bay, St. Michaels and Vic High. Some of the organizations
that have benefited from this program are the Victoria Transition House, the
Land Conservancy, Kiwanis Emergency Youth Centre and PEERS, and that is just to
name a very few.
The students who participated learned about these organizations,
thus giving them a better understanding of their community. The kids in this
program really care about helping people, and they find out firsthand what it is
like to be a philanthropist and how good it feels to give.
I am very pleased this program is growing, and I would like to see
it grow across our province, allowing all kids the opportunity to know what it
is like to be a philanthropist, so that they can take that knowledge into the
future with them and know how good it feels to give.
CZORNY ALZHEIMER CENTRE
D. Hayer: In late January I was honoured to help begin
construction of Surrey's new Czorny Alzheimer Centre, a centre that will not
only care of those suffering from the most tragic of diseases, but a centre that
demonstrates the remarkable caring and contributions of a Surrey-Tynehead
family. That family is the Stewarts — relatives of our member for Maple
Ridge–Pitt Meadows. Chick and Marilyn Stewart and their family not only
contributed 8.4 acres to build this fabulous home for those suffering from
Alzheimer's disease, but they have also contributed $10 million in capital
funding to build a 36-bed facility. The generosity of the Stewarts was spurred
by Marilyn's desire to honour her father, Michael Czorny, who battled the
debilitating disease for nine years. Marilyn Stewart recalled how powerless she
felt trying to help her father deal with Alzheimer's.
She and her family are now helping many other families today and
well into the future with this exceedingly generous donation. The Czorny
Alzheimer Centre is named for Marilyn's father and mother, Michael and Nancy
Czorny. It is located on 66th Avenue and 168th Street and will house 36
Alzheimer's patients in their home-like cottage on a secure park-like ground
complete with a stream. The new centre created by the Stewarts will provide the
care needed by seniors in Surrey, while helping facilitate their independence.
[1415]
Czorny Centre, the first stand-alone facility for Alzheimer's
disease in the Fraser Valley, is scheduled to open next spring. It will benefit
our growing communities and serve as a model for the rest of the province. The
people of Surrey and all of British Columbia can be very proud of the caring and
sharing demonstrated by the Stewart family, and I ask that all members of this
House join me in applauding their munificent generosity toward aiding those
stricken by Alzheimer's disease.
2010 OLYMPICS COUNTDOWN EVENTS
IN CARIBOO AREA
W. Cobb: "Let the Countdown Begin" was the headline in the
100 Mile Free Press as they got ready to show the Olympic spirit by
celebrating the five-year countdown to the 2010 games.
Mayor Barnett is the local committee chair in 100 Mile. She raised
the Spirit of B.C. flag at the South Cariboo visitor information centre to bring
awareness to the games. Joining the mayor were Bev and Jeff Kendy, who are
co-chairs of the 2006 B.C. Northern Winter Games to be held in 100 Mile at that
time.
In Williams Lake they co-ordinated the flag-raising ceremony with
a winter carnival, which they hoped to be the first annual. The carnival — even
though we had a little shortage of snow — was a huge success and brought many
families into the downtown courthouse square for the festivities. The carnival
was sponsored by the business improvement area association and of course tied in
the Olympic theme for the first event.
Earlier this week, John Furlong, head of the Olympic bid
committee, spoke at the chamber of commerce lunch and also spoke to about 550
students on the opportunities available leading up to the games. I was available
to drop the commemorative puck at the minor hockey tournament, and they also
received a Spirit of B.C. banner.
In Cache Creek the ceremony was held at the elementary school. The
students marched out one by one and took their place around the flagpole. Mayor
Ranta read the proclamation, and a drum ceremony was performed by the Bonaparte
band elders. The flag-raising ceremony in Ashcroft was performed by the cadets,
[ Page 12041 ]
with Legion members on hand for the event at the landmark fire hall and Mayor
Anderson reading the proclamation.
The countdown to 2010 has indeed begun.
Mr. Speaker: That concludes members' statements.
Oral Questions
SURREY MEMORIAL HOSPITAL SERVICES
AND TERMINATION OF
FRASER HEALTH AUTHORITY CEO
J. Kwan: In 2002 Kathy Kinloch, an executive director with
the Fraser health authority, said the emergency ward at Surrey Memorial was
stretched, and it needed a capital expansion. In December the Cochrane report
put forward recommendations for changes to emergency care. Last month Fraser
health authority CEO Bob Smith sent a memo to staff raising alarm bells about
overcrowded emergency rooms. But the government has done nothing.
Why is the Premier making Bob Smith the fall guy today, when the
situation at the Fraser health authority has been a mess since the B.C. Liberals
reorganized health care into chaos?
Hon. S. Bond: We absolutely agree that there are growth
pressures in the Fraser health authority and, in particular, facing Surrey
Memorial Hospital. But as we've pointed out numerous times, demographics are not
new to anyone. As we move forward, we are today making sure that we are going to
move forward rapidly and aggressively to address the pressures that face Surrey
Memorial Hospital.
Mr. Speaker: The member for Vancouver–Mount Pleasant has a
supplementary question.
J. Kwan: The government knew as far back as 2002 that there
were growing pressures in the emergency ward. The fact is that B.C. Liberals are
the ones to blame for the crisis at the Fraser health authority.
The government can try to blame Bob Smith and make him the fall
guy three months before an election, but the buck stops with this Premier and
this government. If Bob Smith really wants to be blamed, can the Premier explain
today why the Minister of Health — actually as recently as yesterday — defended
the Fraser health authority on the handling of the emergency care in this House?
The Minister of Health defended the Fraser health authority's actions as
recently as yesterday.
Hon. S. Bond: We've made it clear that there is work to be
done in the Fraser health authority. Let's look at the track record of what this
government has actually managed to accomplish in the period of time we've been
in Victoria.
[1420]
We are actually going to see the delivery of a new hospital in
Abbotsford, which people knew about for how many years — a decade? — prior to
this. We have seen a response by the Fraser health authority to deal with the
short-term pressures, but we expect more.
Interjections.
Mr. Speaker: Order, please.
The member for Vancouver–Mount Pleasant has a further
supplementary.
J. Kwan: Certainly, the people of Surrey expected more from
this government and this Minister of Health. Bob Smith was paid $320,000 a year.
This government spent more than $50,000 just to move him out here from Halifax
to take the job. Here's what the former Minister of Health, now the Minister of
Finance, had to say about Smith's on-the-job performance: "I believe he has done
a first-class job as the CEO of a multibillion-dollar organization." Again, to
the Premier: how can British Columbians have any faith in a government that gave
Mr. Smith glowing reviews but then fired him at the first sign of political
trouble less than three months before the election?
Hon. S. Bond: Health authorities are large and complex, and
there comes a point in time where it is perhaps necessary to have a change in
leadership. In fact, that was certainly evident in 2001 in Victoria — wasn't it?
We're actually going to see a new direction in the Fraser health
authority, because we believe the people of the Fraser health authority deserve
the best quality health care they can access.
J. MacPhail: Government's motto is "Shoot first and then
find out what's wrong later." Here's what the former Minister of Health had to
say about complex organizations: "He is worth every dime of that salary we are
paying to provide leadership for an extremely complex organization." That's what
the former Minister of Health had to say about Bob Smith.
Well, what's happening at Surrey Memorial under this government's
leadership? The average wait time for Surrey Memorial in the emergency room is
six to eight hours. The emergency room today is 42 percent above capacity.
Surgical wait times are exploding since this government took over.
Again to the Minister of Health: after three years of giving Bob
Smith their full support up to and including yesterday, despite ongoing chaos in
emergency rooms, what changed last night to warrant his firing this morning?
Hon. S. Bond: Let's talk about the accomplishments of this
government in terms of health care. We have record health care spending in the
province of…
Interjection.
Mr. Speaker: Order, please.
[ Page 12042 ]
Hon. S. Bond: …British Columbia. In fact, across the province
we've added almost 70,000…
Interjection.
Mr. Speaker: Let us hear the answer, please.
Hon. S. Bond: …new procedures across the spectrum in terms
of people's ability to access hips — new hips — and knees and angioplasties.
This is a government that has an aggressive plan for reform…
Interjection.
Mr. Speaker: Order, please.
Hon. S. Bond: …and we are going to continue to move
aggressively toward improving health care in this province.
Mr. Speaker: The Leader of the Opposition has a
supplementary question.
J. MacPhail: Let me remind the Minister of Health and the
Premier that on top of Bob Smith's salary, this government paid his predecessor,
Pat Zanon, $700,000 in severance to make room….
Interjections.
Mr. Speaker: Hon. members, let us hear the questions and
the answers.
J. MacPhail: I'm fine with this. It shows how little they
understand the problem they've created, Mr. Speaker. It shows just how little
they understand what they've done to patients.
They paid Pat Zanon $700,000 in severance to clear the way for Bob
Smith because they thought Bob Smith could be trusted to do their dirty work.
You see, Mr. Speaker, they don't get it.
Again to the Minister of Health: what did she learn between
yesterday's question period, when she defended the Fraser health authority, and
this morning that finally convinced her that their hand-picked candidate that
cost the taxpayers hundreds of thousands of dollars had to be sacrificed to
cover her political hide?
[1425]
Hon. S. Bond: Let's talk about the mess we had to clean up
when we got to Victoria. Severance is a perfectly good example of that. In fact,
we now have the most rigorous standards in the country in terms of termination
expectations. I'm always surprised….
Interjections.
Mr. Speaker: Order, please. Order, please, hon. members.
Hon. S. Bond: I'm always surprised…
Interjections.
Mr. Speaker: Order, please. If we're going to continue with
question period, let's have some order in the House, or we'll stop it right
here.
Hon. S. Bond: …that a former Minister of Health would
actually be able to stand up and continue to point fingers across the floor of
this House, when there was not one single FTE in the previous government that
was responsible for planning in health care.
SURREY MEMORIAL HOSPITAL SERVICES
AND HEALTH ESTIMATES DEBATE
J. Brar: Since becoming an MLA, I have heard nothing but
horror stories about patient care at Surrey Memorial Hospital. With a large and
growing population, the Surrey Memorial Hospital is not equipped to take care of
patients properly and provide quality care to the patients in Surrey.
Can the Minister of Health tell us how much it's going to cost to
expand the emergency room and how much it's going to cost to build the necessary
long-term care beds to take the pressure off acute care beds?
Hon. S. Bond: First of all, while there are always
challenging circumstances that occur in the health care system, the men and
women that serve every day in the health care profession are extraordinary. The
vast majority of experiences that people have in the British Columbia public
health care system are exceptional. A great deal of work has been done in terms
of looking at the need to expand Surrey Memorial Hospital. That work is being
done. We expect to see that expedited as soon as possible.
Mr. Speaker: The Member for Surrey–Panorama Ridge
has a supplementary question.
J. Brar: The minister says they didn't know how much money
it was going to cost but says there are plans and all that kind of stuff. I have
been hearing that since the by-election. When the by-election took place, all
those kinds of plans…. I don't know where those plans are, and where the money
is, I don't know. But can she tell us how much it will cost or point to
dedicated funding in the budget?
There's one simple reason why so many of my constituents did not
vote in favour of this government in the by-election. They simply don't trust
this government.
Will the Minister of Finance…
Interjections.
Mr. Speaker: Please, hon. members.
J. Brar: …commit today that he will allow this House to
examine the health estimates in detail so we can find out ourselves whether
these promises are real?
[ Page 12043 ]
She is talking about plans. Show me the money. Where is the money?
Hon. G. Bruce: The work of the House…. The government has
business to undertake. We will be undertaking that business here. We're all
here. We're doing supplemental estimates now around the clock as we sit here.
We've been going at it. You've had minutes and hours on all of the supplemental
estimates as we're here. The people's business of this province will be done in
this House. And when it's finished, we will go to the polls, and once again
British Columbians will elect good government in the province of British
Columbia by returning this side of the House to government.
CANCER CLINIC IN PRINCE GEORGE
P. Nettleton: Rumour has it that the cancer clinic has been
approved for Prince George. If that is the case, has the Minister of Health
Services been instructed to hold back on the announcement closer to the writ
being dropped in order to achieve maximum voter impact?
[1430]
Hon. S. Bond: The member should be well aware of the
process that we're undergoing in terms of the cancer strategy. Currently the
northern health authority plus the provincial health services authority are
doing a study on how we can improve cancer care across northern British
Columbia. I've made it clear that that report has not yet been received. We
expect to receive it within the next couple of weeks.
HEALTH CARE SERVICES IN B.C.
E. Brenzinger: As the health care system slowly erodes due
to operational cutbacks and poor planning on the asset side, it means that this
government has not anticipated growth and, hence, has not built hospitals to
serve regions where the population is increasing. British Columbians are
witnessing an unacceptable rate of misdiagnosis, infection, unclean facilities
and unnecessary deaths.
What threshold needs to be reached before the Minister of Health
recognizes that there is a health care crisis and that Surrey Memorial Hospital
is the second-busiest emergency ward in the country and needs to be given the
funding to operate properly?
Hon. S. Bond: In the budget recently brought down, we'll
see that the health care budget was increased by $1.5 billion. By the end of
next year, in fact, the Fraser health authority will have received an additional
$200 million.
SEVERANCE PAYMENT FOR
FRASER HEALTH AUTHORITY CEO
J. MacPhail: The Minister of Health wants to blame
everybody else except her Premier and herself for the absolute failure of Surrey
Memorial Hospital to deliver quality patient care. This morning she fired Bob
Smith and blamed him for all of the problems.
If Bob Smith is the problem at Surrey Memorial Hospital, why are
this Premier and this government paying him $300,000 in severance pay?
Hon. S. Bond: We've already made it perfectly clear. We
have the most rigorous standards in terms of severance in the country, and we
will adhere to the expectations that are laid down in legislation.
[End of question period.]
Interjections.
Mr. Speaker: Order, please.
Interjections.
Mr. Speaker: Order, please, hon. members. Order, please.
Would the members please take their arguments outside the House. The member for
Coquitlam-Maillardville has the floor.
Reports from Committees
R. Stewart: I have the honour to present the report of the
Select Standing Committee on Education for the fifth session of the
thirty-seventh parliament entitled A Future for Learners: The Path to Renewal
of Education in British Columbia.
I move the report be taken as read and received.
Motion approved.
R. Stewart: I ask leave of the House to permit the moving
of a motion to adopt the report.
Leave granted.
R. Stewart: I move that the report be adopted, and in
moving adoption, I wish to make the following comments.
The Select Standing Committee on Education was mandated to assess
the progress made to date in implementing the recommendations contained in the
committee's 2002 report. The preparation of this 2002 report was, in fact, the
first time in almost a quarter-century that the Select Standing Committee on
Education had asked the people of B.C. for their opinions on our education
system. The results of our review of that report concluded that increased school
board autonomy, a simplified funding formula and a new comprehensive
accountability framework had provided British Columbia students with world-class
learning opportunities.
[1435]
I appreciate this opportunity to move the adoption of the
committee's report, and I would like to thank the organizations who took the
time to provide us with
[ Page 12044 ]
their thoughts. I would also like to extend my sincere appreciation to all
members of the committee for their input and dedication throughout this
important process.
Motion approved.
Orders of the Day
Hon. G. Bruce: I call Committee of Supply.
Committee of Supply
The House in Committee of Supply; J. Weisbeck in the chair.
The committee met at 2:39 p.m.
SUPPLEMENTARY ESTIMATES:
MINISTRY OF TRANSPORTATION
(continued)
On vote 37(S): ministry operations, $550,000,000 (continued) .
J. MacPhail: Just before we broke for the noonhour, I was
asking questions about the Sea to Sky Highway and the fact that the government
now has to account on taxpayer debt for the portion of money that was supposed
to be paid by the private sector.
[1440]
I would like to ask the minister about the logic behind the
accounting principle that when a commitment to a capital lease is made, it is
defined as a public liability. Could he explain that accounting principle,
please?
Hon. K. Falcon: The member knows that we as a government,
as part of our openness and transparency, are the only government — that I'm
aware of — in North America that is now following generally accepted accounting
principles, otherwise known as GAAP.
In terms of the logic which belies the accounting profession and
the auditor general's possible requirement that the financing portion of the
private sector partner's contribution be considered a capital lease…. I can't
begin to totally understand the arcane nature of accounting policy and the
requirements thereto, but I can say this to the member: we will, as always, be
fully compliant and GAAP-compliant. That is why, through an abundance of
caution, we are ensuring that as part of going forward, we will include that
portion of the private sector financing as part of the total government debt, in
anticipation of a pending ruling by the auditor general.
J. MacPhail: This is why it is such a mockery to not debate
the estimates of this new budget. This minister can't answer the question, and
we're not going to get any access to the Minister of Finance. The answer he just
gave is ridiculous — absolutely ridiculous.
Once again the citizens of British Columbia are being harmed by
the secretiveness and the scaredy-catness of this government. They're going to
run away without answering any of these questions.
My information is this. When a contribution is determined to be a
capital lease, it means that the person who will be doing the leasing is taking
no risk and that the only risk is to the taxpayer. That's why the debt
associated with that capital lease has to be assigned to the taxpayer. It has
got nothing to do with GAAP — nothing. We faced this in the 1990s; we faced it
in the 1980s.
Perhaps the minister could tell us: what is the risk factor that
the private sector is now not taking and that leads to the auditor general's
conclusion that this is a capital lease?
Hon. K. Falcon: There is no change at all in the risk
profile. The only difference is that as the owner of the asset the government of
British Columbia…. That is primarily why the accounting rules require that the
capital lease be included: because we will be the owner once the work is
completed. That is why this drives that accounting issue.
[1445]
J. MacPhail: Well, Mr. Chair, it's ridiculous for me to
pursue this line of questioning with this minister, because he doesn't know what
he's talking about. He simply doesn't know what he's talking about, and frankly,
it's embarrassing for us to continue this discussion.
What we do know is that since this government made the
announcement that they were going to have this wonderful public-private
partnership on the Sea to Sky Highway, it has all fallen apart. There ain't
nothin' left of it. The government has to assume all of the risk, and that's why
they're being charged the full accounting for the debt. That's why this is, and
that's the difference from what happened last announcement.
I don't know why they don't just admit it. It's a publicly owned
highway. It's public money that's covering off this highway. At best, the
private operator is getting a good advantage to make a profit at the taxpayers'
expense, which is, of course, typical of this government. It's absolutely
typical of this government, under the guise of public-private partnerships, to
have them all fall apart except for the portion where the private operator gets
to make a profit at taxpayer expense. That's the nub of this issue, plain and
simple, and it's right there in the budget plan.
It is unfortunate that the abuse of this House doesn't allow for
that to come out, except for with the opposition. If we could actually debate
the estimates, perhaps the Finance minister would be able to explain all of
this. But oh, no. We're not going to get to do that. No. We're going to have
people stand up, like the member for West Vancouver–Capilano, who stood up and
said, "Blah, blah, blah. Can you tell me why you're so wonderful, government?"
instead of asking hard-nosed questions about the Sea to Sky Highway and how his
constituents
[ Page 12045 ]
are being raked over the coals because of that. The minister of highways
can't even explain what a capital lease is — can't even explain it. It's
embarrassing.
Under the gateway project, what's changed with this supplemental
estimate?
Hon. K. Falcon: Prior to answering that, I want to touch on
something the member said. I can't let that go by, because she is trying to
impugn the benefit of P3s. As a government that single-handedly set the standard
for public tax dollars being wasted on megaprojects that went disastrously
wrong, it is amazing to me that she can stand there and critique a process
called P3s — public-private partnerships — whereby you do have risk transfer,
where the taxpayer doesn't have to take it all on the chin when something may go
wrong.
It's funny that she mentions Sea to Sky, because on the Sea to Sky
we had a great example of that when the Rutherford Creek Bridge collapsed.
Instead of the taxpayer being on the hook for that, the private proponent was
responsible for replacing that, at their cost, when something went wrong — not
us as the taxpayers.
The other thing I will say about Sea to Sky is that I really want
to take a moment to recognize the incredible work of the contractors and their
employees who have been doing the work there. It is ahead of schedule. It is
under budget. They have been doing exceptional work in very challenging
circumstances, and I have heard this positive feedback from mayors up and down
that corridor. I have heard this feedback from travellers along that corridor.
It truly is a great success, and try as that member might, she will not be able
to impugn the fact that it will be a great asset for British Columbia.
[1450]
Speaking of the gateway program — something I'm very excited about
— the key difference here is that we've added $200 million. Those dollars will
be utilized for planning purposes; for environmental assessment work; and for
some partnering with the federal government on some potential capital aspects of
that, which we're currently negotiating. So there are very, very many strong
benefits coming forward as a result of the gateway program.
J. MacPhail: I didn't find out what changed except for $200
million. Where is the money being allocated?
Hon. K. Falcon: Actually, I just said that, so I'll say it
again for the member because she may not have heard that part. The dollars will
be allocated in a whole range of areas. They're going to be allocated towards….
It could include everything from property acquisition. It will certainly include
substantial planning work. It will include a very substantial public
consultation process, which has already begun. It will include some potential
capital initiatives that would be undertaken.
There is a whole range of issues that will be…. Some will be
dependant on what level of federal government involvement we have. More
importantly, what this recognizes very clearly, I believe, is this government's
very strong commitment to moving forward with the gateway program.
J. MacPhail: Perhaps I could have just a few more
specifics. Could he name a capital project that's going to benefit from this
$200 million? For instance, the twinning of the Port Mann Bridge and the
expanding of Highway 1, which is a gateway project, cost $1.05 billion. The
minister tried to announce that during the recent Surrey–Panorama Ridge
by-election. He spent a real whack of money there. How much is going toward the
twinning of the Port Mann Bridge and the expansion of Highway 1 in '05-06?
Hon. K. Falcon: We are in the midst of negotiating with our
partners on this. There are negotiations that take place with local governments
and with the federal governments. I expect we will have more to say in the
coming months about that, but at this point I'm not prepared to talk about that
just because we haven't concluded those negotiations. Upon conclusion of those
negotiations, we will, of course, be talking about that in the coming months.
J. Brar: On the Port Mann Bridge, you know, there's a
history there. I saw, during the by-election, that this was the number one issue
for the Liberal government. Yes, I understand that they have to negotiate the
project with the federal government, but what are you going to negotiate? Do you
have a plan? How much is it going to cost? Do you know about that? We want to
know how much it is going to cost and what your plan is on this.
Hon. K. Falcon: Certainly, as I have said many times
before, we're in the midst of determining the scope of that project. We have,
for example, wanted to include improvements to all the interchanges along the
No. 1 highway to ensure that we work with municipalities so that traffic flows
in and off the freeway will be improved. That is ongoing.
We've always said that the total cost, when you include the
interchange work, is likely in the $1.4 billion range, but again, that scope is
something we're in the midst of establishing. This is all part of our plan of
moving forward with the gateway program. It is a very important part of that.
We also happen to believe that there will be strong federal
interests in the gateway program, because of the enormous impact it will have on
the economy of British Columbia and on the ability to move not just people but
goods throughout the lower mainland gateways. The South Fraser perimeter road,
the twinning of the Port Mann Bridge, the widening of No. 1 and the improvement
of the interchanges and, of course, the North Fraser perimeter road are all
critical parts of that gateway program.
J. Brar: What I want to know is: is there any money — even
a single dollar — allocated for the construction of the Port Mann Bridge?
[ Page 12046 ]
Hon. K. Falcon: As I mentioned to the member, we're in the
midst of negotiations right now. I will be saying in the coming months where
some of those dollars will be going, so I would ask the member to stay tuned.
[1455]
J. Brar: I have difficulty understanding that when you are
going to negotiate, particularly…. We have this bridge and we need to twin it.
The minister, at this point in time, doesn't know how much it's going to cost.
What I'm asking is: what is the cost of twinning the bridge? Do you have any
money allocated in the current budget for the construction of the bridge from
your side? Leave aside the federal government.
Hon. K. Falcon: The bridge portion at this point is
estimated to be about $800 million of the $1.4 billion. As you can see from the
substantial financial commitment just over the next three years alone — almost
$300 million towards the gateway program…. Again, I will have more to say on
what, if any, of the capital portions of that will be in the coming months once
we conclude some negotiations that are underway.
J. Brar: The minister is saying that the money we have
allocated is about $300 million at this point in time for the whole gateway
project. Out of that, can the minister tell how much money is going to be
allocated for the Port Mann Bridge?
Hon. K. Falcon: As I've said, no, I can't, because we're in
the midst of negotiations right now. We'll have more to come in the coming
months. Once we conclude those negotiations, we'll have a better sense of what
portions we are able to move forward on immediately. Stay tuned, because in the
coming months you'll know that.
J. Brar: The total cost for the Port Mann Bridge is $800
million, as per the minister's estimates. So the total money allocated by the
government at this point in time, $300 million…. Is the minister expecting only
$5 million more for the gateway project from the federal government?
Hon. K. Falcon: We're in discussions with the federal
government and have been for some time. I'll be very candid. I am seeking every
possible penny I can out of the federal government for this project. The reason
I'm doing that is because I actually think there is a strong Canadian interest
here. Canada benefits when British Columbia benefits from making up for the
historical lack of infrastructure investment that the previous government did
not make in lower mainland infrastructure.
This is very, very important for Canada. I expect that the federal
government will recognize its importance to Canada, and I expect to get every
possible dollar I can out of federal government contributions to a project that
will have enormous pan-Canadian benefit.
[1500]
J. Brar: I'm trying to understand the numbers here. The
total cost for the gateway project, as projected by the minister, is $1.5
billion, if I'm correct. The money committed by the government for the next
three years, up to year 2008, is $300 million. My question is: if the government
does not get the remaining almost 80 percent of the money from the federal
government, is this government committed to elevate the funding from this
government? If that's the case, what is that? How much is that?
Hon. K. Falcon: We will cross that bridge when we come to
it. What I can tell the member is that I think it is very important to recognize
that these dollars are a very substantial commitment to moving this project
forward as aggressively as we can. I do happen to think — I'm always hopeful and
optimistic — that we can bring some federal dollars to the table.
I think the federal government will recognize — with, hopefully,
even the encouragement of the member opposite, who is from Surrey and knows how
challenging it is for residents of Surrey just to access Highway 1, whether it's
from 152nd, 160th or 176th — what a problem that is for the residents that
member serves. I hope that member will be joining me in writing and pushing the
federal government to contribute to this very important project.
J. Brar: I understand the need for the Port Mann Bridge,
and I have said that from the very first day. The question I have is…. I'm not
going to stand up here and support something which is not viable, which is not
workable. My question again is: do we have a workable, fully developed business
plan which you are going to present to the federal government and which has all
the estimated budgets of every project?
Hon. K. Falcon: I think it might be helpful for the member
to know that on a project of this size and this scale, whenever we approach the
federal government, it's with numbers that are of what I call an order of
magnitude. The reason is that until you go through the public consultation and
the consultative process with all of the respective municipalities…. Some of
that can change, and that will impact costs. What you do is establish an order
of magnitude so that people have a sense, especially the federal government, as
to how much we're talking about in terms of the magnitude of the project.
The other thing I would say to the member — and I think it is very
important — is that this 200 million in additional dollars that has now been
contributed towards the gateway program is just the beginning of an ongoing
process. What I would say to the member is to not get himself overly concerned
about the construction-cost funding portion, because of course, you know we have
to go through the environmental assessment work and the public consultation
work. This will allow us to accelerate that work and get through it. The outer
years that you don't see here will be where you will
[ Page 12047 ]
need the very substantial capital dollars for the actual construction itself.
J. Brar: This government has been talking a lot in the past
and even today about how we should run the government as a business. I
understand that. But any business, even if it's a very small business, has to
start with a full-blown business plan which includes everything from market
analysis, consultation done and all the projections in the budget to information
from their partners. I don't understand, at this point in time, if you don't
have a business plan to start with, on what basis you are going to negotiate
with the federal government.
Can you tell me whether you have a business plan or are in the
process of developing a business plan where you have full and complete
information after doing the necessary work to get the business plan completed?
[1505]
Hon. K. Falcon: The member likes to keep talking about
business plans, so I would refer him to a couple of things. One is that the
federal government, Transport Canada, did a study which showed that congestion
actually costs the lower mainland economy — wait for this — $1.5 billion
annually. That is the lost economic cost to the economy of the lower mainland
because we have traffic gridlock and there has not been historical investment
made by the previous government in the transportation infrastructure.
The Port Mann Bridge, in particular, was built in 1963. That was
40 years ago. The population of the GVRD 40 years ago was about 800,000 people.
Today it's three times that number, and there still has been no new investment.
The final thing I would say to the member is that yes, we do have
a business plan. That business plan will be part of the public consultation
process and will be shared, because we are in the midst of, as I've said to the
member….
Interjection.
Hon. K. Falcon: I keep hearing heckling from the member for
Vancouver-Hastings, who was the leader in a government that did absolutely
nothing for lower mainland infrastructure at all for the decade that she was in
power.
Interjection.
Hon. K. Falcon: "HOV lanes" is apparently this member's
answer to what she did to solve the transportation gridlock crisis in the lower
mainland. Unfortunately for the member, the HOV lanes didn't solve the $1.5
billion worth of congestion challenges we face in the lower mainland.
Interjection.
The Chair: Order, please.
Hon. K. Falcon: We are actually moving forward. The member,
along with the public, will be able to peruse the business plan that will be
shared with all the public during the consultation process. Part of these funds
will go towards making sure it happens.
J. Brar: Well, finally. This is the first time I've heard
that there is a business plan; I don't know at what stage, though. I would like
to know: is the business plan complete at this stage? If not, on what day will
it be completed, and can I get a copy of that?
Hon. K. Falcon: The business plan will go out to the public
through the public consultation process, which will take place in the fall. The
business plan will incorporate the public consultation that we hear, and any
final refinements will be made to the business plan as a result of that public
consultation.
J. MacPhail: So we've got no business plan, no public
consultation. We have a failed announcement that didn't work during the Surrey
by-election. We've got this government having done absolutely nothing along this
corridor in its four years, and all of a sudden we learn that they're expecting
the federal government to pay 80 percent of the project.
Could the minister tell me where, in the history of Canadian
federal-provincial relations, the federal government has ever paid 80 percent of
an infrastructure project?
Hon. K. Falcon: Well, I have to say that I never cease to
be amazed by the unbelievable things that come out of that member's mouth.
Apparently an over $300 million commitment this year and three years out isn't a
commitment and apparently isn't doing anything. That member had a decade to do
something and did nothing. A band-aid solution was one thing they did on the
Port Mann Bridge, and that's all it was. We are actually engaged in the most
massive infrastructure program that the lower mainland has ever seen.
Now, this member talks about 80 percent federal dollars. You know,
the member is just frankly, as usual, wrong. We go to the federal government and
ask them to be partners in projects like this, and as the member knows, there is
a substantial amount of work that has to take place before you ever actually
start the major construction process. What we are doing is demonstrating this
province's commitment to moving that forward by undertaking these expenditures.
We will be building that bridge. We will provide a twinned Port Mann and a
widened Highway 1, and it will be an enormous benefit for British Columbians in
the lower mainland not just today, but well into the future.
[1510]
J. MacPhail: I guess the proof is in the pudding. Here we
are, days away from the end of this government's first term, and they've done
nothing. Here we are, days away from this government's term, and they've
committed $300 million on a $1.5 billion pro-
[ Page 12048 ]
ject. They have no business plan — none, zero. They've done no public
consultation, they've done no environmental assessment, and people are supposed
to say: "Oh gee, that's a good record." Well, their record stinks, and we know
that. They'll be judged on that record come May 17.
The reason why I say, "Has there ever been a federal government
that's committed 80 percent to an infrastructure project?" is because that's
what the minister said. He said: "The project costs $1.5 billion. We've
committed $300 million. We have no plan. We've got nothing to negotiate with the
federal government, and we're expecting the federal government to come up with
the dollars." That was the answer to the question.
We in the opposition can only assume that they're expecting the
government to come up with $1.2 billion. Oh wait, there's another possibility.
Let's see. Maybe in the year '09…. Let me see. How many years away will that be,
and how many of those people will even exist on the other side? Maybe in '09 the
government…. Well, I should say the Liberals. The Liberals might say: "Well, if
we're elected to government, we'll commit more money."
Again, this government — and particularly this minister — have
such poor business acumen that they think…. Well, actually, it's been tested. It
was tested in the by-election. This minister stood up and made the big promise
about the Port Mann Bridge. I don't think anyone believed him.
Wait. Does his mother live in the riding? No, his mother doesn't
live in the riding. So maybe nobody believed him, and that's why he did so
poorly as the political lead in that by-election. His commitments are so false,
they're like cotton candy. They're backed up by absolutely nothing, and we see
that from the questioning.
When are the negotiations going to begin with the federal
government? Do they start after the business plan has been done next fall?
Hon. K. Falcon: Actually, the member just doesn't quite
understand that the fullness of my political genius strategy will be fully
exemplified on May 17, when we will again revert to seizing the opportunity of
winning that chair back.
I will say this to the member. She's wrong again. I have to say
it's getting a little tiresome having to say that all the time. It must be
difficult being proven wrong so many times. She's wrong that we haven't started
consultation, because actually, we have. In fact, consultation is underway as we
speak. She's wrong when she says we haven't consulted. Actually, we have
consulted with all of the councils up and down the corridor. She's wrong when
she says we haven't done environmental assessment work, because we've actually
done extensive environmental assessment work. It's not completed yet. We still
have more to do, but it's well underway. Again, I find myself in this position
of having to point out that the member is wrong, wrong, wrong.
As far as the government commitment, let me just say this. Unlike
a previous government that — as one of their members used to say, "We used to
make announcements we had no concept of ever fulfilling…. Unlike a government
that used to make announcements that had no dollars to fulfil…. For example, the
$125 million mental health plan comes to mind. Not one dollar was put aside for
that. Unlike that kind of a sorry, tragic….
Interjection.
Hon. K. Falcon: Sorry, I hear a voice. I do believe the
voice is the member for Vancouver–Mount Pleasantness or whatever. That member
should know that she was actually a leader in creating that tragic decade of
broken promises and broken dreams.
What we have done instead is actually put into place over $334
million from this year and going forward for the next three years to actually
open up British Columbia. We are builders again in British Columbia. We are
creating opportunity. We're not going to be like the naysayers on the opposite
side, who can find a thousand reasons why you should never do anything. We're
doing it. We're building. British Columbia is growing again, and that's why
we're going to be re-elected so massively on May 17, 2005.
[1515]
The Chair: The member for Surrey–Panorama Ridge on vote
37(S). Let's get back to the debate.
J. Brar: The minister has said that they're working on the
business plan. My question is pretty simple. What specific steps are they going
to take to build the complete business plan? Can you tell us?
Hon. K. Falcon: There'll be several stages that we will go
through. We will finalize our consultation with the cities that are involved in
the corridor. We will complete our engineering and environmental work that is
underway. As I talked about scope of project, I talked about the fact that we've
already begun the environmental assessment work. That work will be completed. We
will continue negotiations with the federal government, because obviously we
think that they should be an important player in this, and we're hopeful they
will be. Then we will go out in the fall to the public for consultation on the
entire project, including the business plan that we put in front of them.
J. Brar: The benefit-cost analysis is a very important part
of developing a business plan. Can the minister tell: has the gateway program
done any benefit-cost study of the Port Mann Bridge and Highway 1 expansion?
Hon. K. Falcon: Our preliminary benefit-cost ratio for the
entire project is 3.3. The portion for the Port Mann was actually substantially
higher. I haven't got the exact number, but it was in excess of 4.
[ Page 12049 ]
J. Brar: There is a consultant report that Vaughn Palmer has
reported on, but it's not published anywhere on the gateway program website. Can
you tell me what that consultant report is?
[1520]
Hon. K. Falcon: Member, I'll need more information on that.
I'm not familiar with the consultant report that Mr. Palmer has commented on.
J. Brar: Can the minister tell me the scope of public
consultation? Where will that take place, and what community will be part of it?
What municipalities will be part of it?
Hon. K. Falcon: We're already consulting with
municipalities about this issue. We're actually in the process of designing the
public consultation process. What I can tell the member is that public
consultation is something I think…. Frankly, I'm very proud of how our ministry
handles that. We've done a substantial amount of work throughout the province,
whether it's Kicking Horse Canyon or Sea to Sky Highway or whatever the case may
be.
I can tell you that it will include features you see in all of our
public consultation processes. It includes open houses, it includes meetings
with stakeholders, and it will include community meetings. It also includes
pretty substantial website feedback criteria, where we allow people to enter
onto the website and provide feedback from there. It's a very open process that
allows maximum opportunity for the public to have their input.
J. Brar: Mr. Chair, you know, this is a very huge capital
project we have. I think we must have a lot of things very clear in our mind at
this point in time. The stakeholders — who are they? Can you tell me the list of
those people, who they are?
Hon. K. Falcon: This is not a comprehensive list but will
be sort of typical of the kind of stakeholders that typically have input in
these kinds of things. It includes the Trucking Association. It includes the
railway operators. It includes the ports. It includes the B.C. Automobile
Association, various user groups, members of the general public, etc.
J. Brar: Does this list also include…? You mentioned the
word "municipalities." I understand there are a number of municipalities that
are going to be interested in this project and also maybe a number of
communities which will benefit or be impacted by this project. Does the
government have any list of different municipalities you are going to consult?
Hon. K. Falcon: As I mentioned, those consultations with
the municipalities are already underway. They are key players in this whole
process, because we want to ensure that we work cooperatively with them to
ensure that traffic flow is moving to the benefit of, frankly, all the players.
I think the easiest way to explain to the member in terms of which
municipalities…. It's virtually all of them, except those on the north shore of
the Burrard, and Richmond. Excepting those ones, virtually everyone else is
involved in that consultation discussion.
[1525]
J. Brar: The consultant report…. I have more specific
information on that. This is from the Vancouver Sun . It's June 26, '04.
The headline is: "Ten years, $6 billion in roads and bridges." In this
article
Vaughn Palmer reports, on the second page: "The consultant report released last
month forecasts annual revenues starting in the $40 million range at the time of
completion in 2007, rising to $50 million by 2010." Does the government know
about that consultant report at all?
Hon. K. Falcon: Based on the numbers I'm hearing, I think
the member is referring to the Fraser River crossing, otherwise known as the
Golden Ears project. That sounds very suspiciously to me like the numbers,
exactly, for that Fraser River crossing.
J. Brar: We will come back to this one with more clarity
later on.
I know the minister has been talking about tolling the bridge. Are
these net benefits that the minister is talking about greater or fewer under the
toll scenario? I know the minister has been talking about tolling the bridge at
some point in time. Under a benefit analysis, are these net benefits greater or
fewer under the toll scenario?
Hon. K. Falcon: We have provided the cost-benefit ratios.
Those are ratios that do not include tolling. Should tolling be contemplated as
something that would move forward, we would obviously undertake those and
determine what those benefit-cost ratios would be.
J. MacPhail: I've been listening, and I wanted to explore
some of this issue about what the benefits and costs are. The minister is
talking about ratios. I actually want to talk about net benefit and costs. Does
the minister have any net-benefit-and-cost analysis?
[1530]
Hon. K. Falcon: When you have a benefit-cost rate of 3.3,
that coincides with a net benefit of more than $6 billion.
J. MacPhail: What discount rate was used for future costs
and benefits?
Hon. K. Falcon: Eight percent.
J. MacPhail: Over what period of time?
Hon. K. Falcon: Twenty-five years.
[ Page 12050 ]
J. MacPhail: I heard the minister say that that's for the
Fraser River crossing. But does that study also include the Port Mann Bridge?
Perhaps he could tell us the range of the benefit-cost study. I have some other
questions on that.
Hon. K. Falcon: That rate of 3.3 includes the whole gateway
program. It does not include the Fraser River crossing. I imagine GVTA probably
did its own assessment on the Fraser River crossing.
J. MacPhail: Sorry, I may have missed this. This study is
public? The minister is making this study to which he is referring public?
Hon. K. Falcon: No, this is part of the draft business plan
that will be coming out in the fall as part of the consultation process, once
we've completed our discussions with the cities and determined the other issues
that I mentioned to the member for Surrey–Panorama Ridge.
J. MacPhail: Well, I assume this study will be made public.
Can the minister tell us what the title is of the study on which he's just been
answering questions, so that we will know to make sure that it's made public?
Hon. K. Falcon: It's a working paper. I don't believe it
has an official title. But I can tell that member that in the fall it will be
fully released, and the member will be able to share it and enjoy it along with
the rest of the public.
J. MacPhail: Well, we'll see whether we'll be enjoying it
or not. I'm not quite sure why this study isn't released now. It doesn't give
any disadvantage to anyone who may bid on the project, including the federal
government — no disadvantage whatsoever. I assume the study is for the project
and not the proponents. So no, I don't in any way trust the government to do the
right thing and release this at all.
What costs around environmental impact does the study take into
account?
Hon. K. Falcon: They do include environmental impacts.
J. MacPhail: Yes. Which ones?
Hon. K. Falcon: I don't have those numbers with me, but
again, they will be released in the fall as part of the public consultative
process.
J. MacPhail: What did he expect we were going to talk about
under the $200 million? Oh, thank you. You committed 20 percent of ferry money
to a project that you haven't got any business plan for — no business plan.
We're trying to figure out what other studies you've done.
Does the study take into account lost transit revenue or impacts
on highway safety?
Hon. K. Falcon: Yes.
J. MacPhail: Why can the minister tell me that, but he
can't tell me what the environmental impacts are? Are greenhouse gas emissions
taken into account?
Hon. K. Falcon: I don't have all of that information with
me. As I said to the member, it will all come out in the fall. You will see
everything, and you can fill your heart with all the information that will be
there. There's lots of it.
[1535]
J. MacPhail: Well, that's completely insulting to the
voters — completely insulting. But actually, I guess we could use that quote in
an election ad showing that this government doesn't have any substance behind
its promise — nothing. Given their record of broken promises, the voters will
go: "Uh-huh, you're right. Let's be scared. Let's be very, very afraid."
What traffic pattern modelling did the government use? Was it from
the regional transportation plan or their own?
Hon. K. Falcon: We jointly developed a traffic modelling
program with TransLink, and that's the model we're using.
J. MacPhail: Does TransLink have this study to which the
minister refers?
Hon. K. Falcon: As I've said to the member before, this is
all still preliminary work that is underway. We'll continue to work on this. Of
course, once that work is completed, we will share all that work with all the
stakeholders, including TransLink.
J. MacPhail: Whenever the minister gets into a corner, all
of a sudden it turns out to be just preliminary work. He can answer some
questions but not others — all sounds pretty iffy to me. Why? Because it is
iffy. The money ain't there; the study ain't there. The partners aren't there;
the public isn't there. No one's there except the Minister of Transportation
trying to buy votes. That's the only reason we're having this discussion at all,
because he's trying to buy votes.
The minister said that the benefit-cost study was for the entire
gateway program. Well, is there any specific cost-benefit study done for the
Port Mann Bridge or the Highway 1 project? It seems to me that in order to do a
cost-benefit study, you have to do it on the individual parts. I don't think
this government is going to be able to get enough money from the other partners
to do even one part of this project, let alone all three.
Hon. K. Falcon: I already answered this question for the
member for Surrey–Panorama Ridge. The member for Vancouver-Hastings wasn't here
when I answered that, but as I indicated, we did also do a separate rate for the
Port Mann Bridge portion of it. I
[ Page 12051 ]
didn't have the exact number, but I knew it was well over 4.
J. MacPhail: Mr. Chair, just for the benefit of a seasoned
member, he was just unparliamentary — number one.
Number two, it's his job to answer questions no matter who they
come from. He's not supposed to discuss who is not in the chamber, Mr. Chair.
God forbid that be done for his government — I'll tell you that.
Number three, he did not…. I asked this question before, and he
said the study was done for the entire gateway project. It's got nothing to do
with what previous question was asked. He said the study was done for the entire
gateway project, not the Fraser River crossing.
J. Brar: There are numerous neighbourhood groups —
including the livable region coalition and the recently merged Langley
conservation network, Surrey environmental partners — who are opposed to this
project.
My question to the minister is: has the minister done any
consultation with those groups, or is there any plan to do that consultation?
[1540]
Hon. K. Falcon: As I've mentioned repeatedly, there will be
full public consultation in the fall. All those groups will have every
opportunity to avail themselves of the numerous and many consultative events —
whether they're open houses, community meetings, the website or what have you.
J. MacPhail: How far geographically will the consultations
go? The four exits from Highway 1 flow into the constituency of
Vancouver-Hastings. What consultation is going to be done in the riding of
Vancouver-Hastings? Specifics, please.
Hon. K. Falcon: I've already indicated that we're still in
the midst of designing that consultative process in consultation with the
municipalities. As I've already said before and I'll say again, all of the
municipalities are involved except Richmond and the North Shore.
J. MacPhail: Well, let me see — the fall. Could we have a
date of when it's going to be started — the consultation, this grand project?
Oh, I know. Well, then let me ask for this commitment. Will the minister commit
to revealing all of the work that hasn't been done in preparation for this as he
rolls out his election goodies?
The minister didn't want to answer that question. That would be
called truth in advertising, and I know that's anathema to the Liberal
government.
I'll tell you something, Mr. Chair. If this minister raises the
phrase "Port Mann Bridge" once, he will have to be held accountable for all of
the work that he hasn't done in Surrey, in Burnaby, in Vancouver, in the North
Shore, where he hasn't…. It's not even on the radar screen amongst the public or
the city councils, including TransLink and GVRD, that he's done any outreach
whatsoever on the planning of the Port Mann Bridge and Highway 1.
He's shaking his head. Well, stand up and tell us, because that's
all we've been asking. He's saying: "No, no. That's not true." Well, that's all
we've been asking. Tell us what the outreach has been. Let me know right now
what discussions he's had with the city of Vancouver about the effect of this
gateway project on Vancouver-Hastings.
Hon. K. Falcon: Well, I'm forced to once again say the
member is wrong. We actually have engaged in consultation with all of the
councils. We have engaged in consultation with the GVTA. We have engaged in
consultation with the GVRD and the GVTA board, and we will continue to do that
as we go forward with a public consultative process, which begins in the fall.
I don't have the level of detail that the member wants for the
specific riding of Vancouver-Hastings, because we're in the process of working
with the staff at the municipalities to get that information. Then we will come
forward with the full and complete public consultative process.
J. Brar: Do we have…? In a business plan, we usually have….
A good business plan should include some sort of time line on different issues.
Does this government have time lines about when the consultation process is
going to start, when it's going to finish and when the government actually plans
to start — any projection of dates — the actual construction of the bridge?
[1545]
Hon. K. Falcon: I appreciate the member raising the issue
of business plans, because business plans are very important before a government
undertakes major capital projects. As the member well knows, there was no
business plan for the fast ferries. That was one of the reasons why the
taxpayers found themselves in such a horrific situation, where almost half a
billion dollars of taxpayer money was wasted. That should give the member real
encouragement.
We are still, as I mentioned to the member, designing the process
and working with the municipalities. That consultative process will start in the
fall. Typically, a consultative process on a project like this will last
probably…. Six to eight months is the likely time frame we're talking about. As
a result of that public consultative process, we will be able to finalize a lot
of those kinds of issues into the business plan that the member talks about.
J. Brar: Is there any tentative date you have in the
supposed business plan for when the construction of the bridge is likely to
start?
Hon. K. Falcon: Actually, the fact of the matter is that
you can't. You can't until you've nailed down the environmental assessment work,
because believe it or
[ Page 12052 ]
not, you actually have to know what impacts are going to be created. You
can't until you've completed the engineering, the scope of engineering work
required. The public consultative process is a big part of that because you're
going to hear from the….
Interjection.
Hon. K. Falcon: Is there an echo in here? No.
Interjection.
The Chair: Order, please, member. Member, just listen,
please.
Hon. K. Falcon: If the member for Vancouver-Hastings would
actually listen, she might learn a thing or two here. As I indicated, there will
be a full consultative process, and the public will have an opportunity….
Interjection.
Hon. K. Falcon: Yes, of course they do, member. They will
be able to have their say.
Interjection.
The Chair: Member, please. You'll have an opportunity to
ask questions. Just listen now, please.
Hon. K. Falcon: As a result of the contributions of the
public, we can then nail down all the elements of the business plan when we have
completed the public consultative process, when we have completed the scope of
engineering work and when we have completed the environmental assessment work.
That's actually how you build a business plan that makes sense.
Interjection.
Hon. K. Falcon: Well, I'm apparently being lectured by the
member opposite on how to do a business plan. I can't help but remind that this
member was the one who actually had no business plan for fast ferries. In fact,
when the board dared to suggest this might not be a good use of taxpayer
dollars, you fired them, and you put a new board in place made up of people who
didn't have a clue how to undertake a major business project.
It's a little bit difficult for me to hear this member lecture me
on business plans. I'm sorry; it's a challenge for me. But I can assure the
member that our business plan will include all of the information that needs to
be there. It will be fully shared with the public. The public will have full
input on that. That is actually how you move forward on a major project and
protect the public purse.
J. MacPhail: Well, the one infrastructure project that I
was responsible for, the millennium line, came in under budget and on time.
In fact, what this government has just said is that they have no
construction date. They have no construction date in mind. What they're going to
do is go to the public, I guess, and say: "Hey, when would you like the project
started?" It's like a hippie kind of thing. "Hey, man, any idea when you'd
actually like to reach nirvana?" Then you work back from there.
Maybe there would be an epiphany among some certain public groups
where they would say: "You know, I just love it when Capricorn comes together
with Aries, and I think that would be a good day to start construction." Then
others may say: "We don't want you to start construction at all, and it makes
sense for us to have that input, because you don't have any plan anyway — no
construction date."
This government has no business plan, no public consultation
planned, no construction date planned, no budget. This project is a fake — an
absolute fake. Can the minister name any other business plan that…? Well,
actually, no. That's an unfair question, because this government hasn't built
anything. That's an unfair question.
[1550]
Okay, let's look at the RAV project, then. There are construction
dates for the RAV project. Was that wrong? The public consultation is ongoing on
that. They've got construction dates in there. Are they wrong to do that?
Hon. K. Falcon: No, they're not wrong at all. That project
is obviously much more well-advanced. I couldn't help but note that the member
mentioned how she was responsible for the millennium line. Boy, that triggered
some fond memories, like how they overrode the environmental assessment process
and overrode local governments so they could ram it through without the
appropriate environmental assessment work.
You know what? We're not going to do that the way you did that,
member for Vancouver-Hastings, because it was appalling — what you did. In fact,
I would encourage the member and her new member for Surrey–Panorama Ridge to
read some of the headlines from back in the nineties when you overrode the
environmental assessment process — made a mockery of what was supposed to be
there to protect the environment.
That is the record of that member, and that's not how we're going
to do it. That's why I'm proud. When this member says we have no commitment,
I'll tell you, I think most British Columbians would say $330 million is a
pretty significant commitment. I think most British Columbians would say: "We
are proud of a government that actually is going to undertake the full
environmental assessment impact and not shortchange it the way that member and
her government did."
We will not run roughshod over public consultation. We will not
run roughshod over environmental assessment impact. We are going to do it right.
It will be a business plan that will stand up to scrutiny. Frankly, it will be a
stark contrast to the absolute legacy of mismanagement and roughshod overriding
that the
[ Page 12053 ]
member's hopelessly incompetent government undertook during their decade of
dismal economic performance in British Columbia.
J. Brar: I keep hearing different scenarios of this whole
project. The consultation will start sometime in the future; the negotiation
with the federal government will start sometime soon, and so on. I think the
minister, by now, would understand that the government works from year to year
in different budgets.
What I don't understand at this point in time is how the minister
is going to present his case to the federal government in asking for the
partnership — for money — without indicating any date, any budget year to the
federal government. Can you explain that?
Hon. K. Falcon: Actually, the federal government were the
ones that came up with the study that demonstrated there's a $1.5 billion annual
cost to our economy as a result of congestion and gridlock. The federal
government, perhaps more than almost anybody, is keenly aware of the huge
challenges that gridlock and congestion cause. That's why we are working with
the federal government, together as partners, to help solve this problem and
move forward in British Columbia so that we can have a transportation network
that actually works for British Columbians.
J. Brar: The GVRD argues that the Port Mann Bridge does not
support the livable region strategic plan, which is the region's
long-term plan. What is the government doing to ensure that their concerns are
addressed?
[H. Long in the chair.]
[1555]
Hon. K. Falcon: We've already started that dialogue. We've
met with the board of the GVRD. I'll remind the member that the liveable region
plan has not been updated in over ten years. I was speaking to the chair of the
GVRD, and the chair was telling me that they are actually beginning the process
of updating that liveable region plan so it reflects the reality that's out
there. I encouraged them to do that. Of course we will continue, through the
public consultative process, to ensure that they have every opportunity. We will
work with them as they work through a new liveable region plan that will be
updated to reflect the reality of growth and what's happening.
J. Brar: If in this case the GVRD does not come to the
table, will the government push through with this project and override the
interests of the GVRD, even if it resolved to oppose the project?
Hon. K. Falcon: Our intent is to work with the GVRD. I
believe we will be able to fashion a working relationship. We may not agree on
every issue, but I do think we all agree that congestion is a major problem, and
it needs to be dealt with. I look forward to having a constructive relationship
with the GVRD. I actually have a very good working relationship with the chair
of the GVRD, who supports the gateway program. I think that working with other
members of the GVRD, we can fashion a consensus and move forward in a positive
way for all British Columbia.
J. MacPhail: Here's what the Minister of Transportation
said on September 8 of last year about congestion: "You cannot build your way
out of congestion completely."
I searched all sorts of transportation plans to try to find, in
North America, where adding capacity has reduced congestion at all. There's not
one transportation study or analysis that shows where adding capacity has
reduced congestion — not one single one. So maybe the minister could show me or
tell me where I should look. Clearly, my research is faulty. What jurisdiction
in North America has he looked at where adding vehicle capacity has reduced
congestion?
Hon. K. Falcon: I'm not surprised the member will take that
position. In fact, it's exactly why there was no investment in transportation
infrastructure throughout the province. One thing that this government and our
Premier recognize is that there is a direct correlation between the economic
prospects of British Columbia and its transportation network.
The fact of the matter is that we know that when we talk about
economic corridors…. I did say that — and I always say that, I should add to the
folks in this House — you cannot build your way out of congestion. I accept that
as a given, but I also accept that Highway 1 and that corridor is the most
congested corridor in the entire province. It's a congested corridor because it
was built 40 years ago when we had a third of the population that we have today.
The other thing I would say to the member is that we also
recognize that this is just one piece of our bigger transportation plan to deal
with the challenges we face. That's why we are part of a $1.7 billion rapid
transit project for the Richmond-Airport-Vancouver line. That's why we are
contributing $170 million towards the northeast sector public transit. That's
why we continue to fully fund a transportation plan with B.C. Transit, and
that's why this gateway program is so critical.
Remember, at the end of the day we have to move goods in British
Columbia too. Not all of those goods go by rail and air. Some of them go by
truck. We also have to make sure that we recognize that the tens of thousands of
truckers and the businesses that rely on getting their goods to market must have
a network that they can get through. That's why this is one piece of a big
transportation vision and a plan for British Columbia — a plan that we set out
and introduced late in 2002 for British Columbia called Opening up B.C. I'm very
proud of that plan and the leadership our Premier had in fostering and putting
together the plan, and also the leadership that the former Minister of
Transportation had in setting out that plan.
[ Page 12054 ]
[1600]
J. MacPhail: Let me just take this a little bit more
slowly, then, for the minister. It's congestion that causes the economic
malaise. That's why I looked for studies that would demonstrate that adding
capacity, the way this government is doing, reduces congestion let alone
eliminates it — that adding vehicle capacity, reducing congestion, would solve
the economic dilemmas faced by the trucking industry. So I searched for studies
all throughout North America, and I couldn't find any that proved anything
except the opposite point: adding vehicle capacity does nothing for congestion.
It does absolutely nothing for it. That's why I asked the minister for his
study. That's all. It's just a basic, factual question. What studies does he
have to show that congestion will be reduced by the gateway project? What
comparators elsewhere has he examined?
Hon. K. Falcon: What I will say to the member is that the
member needs to look at the successful economies in the world today, and to look
at…. For us to be successful, an economy like that of British Columbia, a small
trading province competing around the world, needs to have a comprehensive
transportation plan that includes investment in public transit and appropriate
investment in infrastructure.
The member should know that the northeast sector of our oil and
gas is exploding in growth. One of the primary reasons is that they came to us
and said: "We need to be investing in transportation, roads and infrastructure."
As a result of those kinds of investments, we now see drilling happening not
just in the winter season but year-round.
That's what the Sierra-Yoyo-Desan P3 was about: an award-winning
private partnership, a $40 million road built up in the northeast sector, which
is now helping to continue the huge, explosive growth in economic activity in
the northeast sector. This member has challenges understanding that, and I get
that. This member philosophically opposes making these kinds of investments, but
I can tell him you that as part of an overarching transportation plan, these
investments are very important.
The one and a half billion dollars that congestion costs the lower
mainland each and every year is a cost on the economy that affects every small
business person in the lower mainland. It affects every part of this province
because even in northern and rural British Columbia, when they're shipping their
goods by truck to get to market, and when they're sitting in that congestion for
three or four hours a day, it actually impacts their ability to be competitive.
That's why we're making these investments, and that's the economic
plan we have for British Columbia: to get ourselves into a position where
British Columbia is a world-competitive economy. That's exactly what we're
doing.
J. MacPhail: I take it from that, with the minister
shifting ground from the gateway project up to the northeast corner of the
province, that he has no studies. He has none — absolutely no studies to show or
demonstrate that what he is going to do will have any impact on congestion
whatsoever.
The studies I looked at, just for his information, are from the
cities of Phoenix, Houston, Los Angeles, Seattle, Montreal and Toronto. Those
are the studies I looked at. The minister can't even name one study to prove his
point that adding capacity actually reduces congestion. I have all those studies
that show adding capacity has zero effect and sometimes a negative impact on
congestion, and the minister doesn't even have one study.
Let me ask this, then: what is the effect on ridership on the
Richmond-Airport-Vancouver rapid transit line when the gateway project is fully
implemented?
Hon. K. Falcon: The answer is it will have virtually no
significant impact at all on ridership. In reflecting on what the member says, I
can only assume that the member feels the way she does because their economic
plan, or at least the result of their economic plan, was actually to slow down
the economy of British Columbia to such an extent that perhaps infrastructure
wasn't needed.
I suppose it is kind of like their small business plan. Their
small business plan is to take large businesses and, through regressive
regulatory and tax policy, reduce them to small businesses. Sadly, in many cases
they just fled the province for a greater opportunity elsewhere.
[1605]
That appears to be the plan that the member has, but I'll say
this. I've said it before, and I'll say it again: that's part of the great
choice that British Columbians will have in front of them. We are builders in
this province again. We're not afraid to be builders. We're not afraid to ensure
that we have a comprehensive transportation vision that includes some of the
most massive investment in public transit we've seen in the history of this
province, that includes certainly the most massive investment in road and
rehabilitation infrastructure improvement we've seen in this province. We want
to ensure that British Columbia is going to be not just competitive but the most
competitive economy in the country. We are going to lead the nation in economic
growth and opportunities for the people of British Columbia.
J. MacPhail: I know that flourish of rhetoric probably
impressed the Minister of Transportation, but unfortunately, it's all smoke and
mirrors. This government actually hasn't invested one single cent yet in any of
these projects we're talking about — not one cent. That's why he can't answer
any questions. That's why he can't tell us when the construction date is going
to be.
I would just remind him that each and every year through the 1990s
a half billion dollars was invested in roads and bridges and transit — every
year. This government has done nothing. Now they're going to make an election
promise — a latter-day election promise —
[ Page 12055 ]
saying: "Oh, trust us. If you vote for us again, we promise to invest
something."
The government doesn't have any study whatsoever to show that
adding vehicle capacity reduces congestion — none. But he just said that he can
absolutely, factually tell me there will be no effect on ridership of the
Richmond-Airport-Vancouver line with the building of the gateway project. How
does he know that? Can he tell me what study he's done?
Hon. K. Falcon: Our preliminary analysis suggested there is
virtually no impact. We're talking about two very different corridors, and
therefore it's demonstrating in our preliminary work that there is virtually no
impact whatsoever.
J. MacPhail: Is it the entire gateway project that the
minister is talking about — upon which those analyses have been done? The
minister is nodding yes. Perhaps he could describe the analyses then, please.
When the minister stands up and says there's virtually no linkage whatsoever
between the rapid transit line, SkyTrain and this gateway project…. Perhaps he
could just tell me.
Hon. K. Falcon: The preliminary and initial runs of the
traffic model don't indicate any impact. Now, the member knows these are very
complex and complicated technical models that we go through. But, as I say, the
preliminary information is that there is virtually no impact.
J. MacPhail: Does that include the South Fraser perimeter
road as well in the impact study?
Hon. K. Falcon: Yes.
J. MacPhail: I would love to see that study, then. I'd just
love to see it. Could I have a copy of it, please? Sorry, Mr. Chair. I'll let
the minister answer on the record.
Hon. K. Falcon: As I've indicated on at least half a dozen
occasions, the member will have full access to that in the fall when the public
consultation process begins.
[1610]
J. MacPhail: What's the problem with releasing it now? I
don't understand that. The minister just went on record saying he has a study,
and it shows that there will be absolutely no impact. I'm just very curious as
to how that could be. I'm skeptical. I'm sure a whole bunch of people in the
GVRD would be skeptical as well. Let me ask this: does the GVRD have that study?
Hon. K. Falcon: The member keeps referring to it as a
study. I've said again that this involves preliminary work on initial runs of a
traffic model. As I said, in the fall when we begin the public consultative
process, we will share that with all the stakeholders and all members of the
public including that member.
J. MacPhail: I guess, then, that it's not a study. They
looked at some traffic patterns, and the minister concludes that there is no
issue. Hoo, boy, that's really comforting. I think the minister is just making
it up as he goes along. And the public is supposed to have confidence in him or
his government?
Let's find out what other studies the government's done on this.
Claims to be the big enviro-guru; says the former government, on the millennium
line, overrode environmental assessment. That's simply not true. He knows that.
It's the greenest project, the cleanest project under budget, done in record
time. It turns out that the municipalities, after consultation, welcomed the
project, as did the public. Of course, they were actually involved, unlike this
government, where you have to take the minister's word.
His word has been challenged. His word has been challenged,
actually, in the hallway — about the truthfulness of the things that he has said
in here. And then he's had to apologize. Now, that was about matters of criminal
activity. You're right. That was about criminal activity raids on the
Legislature. That's true.
The Chair: Member, will we please stick to the vote? I
don't think it's necessary to go through the characters of people.
Interjection.
J. MacPhail: Thank you, Mr. Chair, I certainly will.
But it certainly isn't out of line at all, just for the minister's
benefit. I'm just actually reiterating the facts that are on the record in
Hansard . I do see that they're troublesome. The facts are troubling to the
Minister of Transportation, and I can understand why.
The government argues that building the bridge will reduce our
greenhouse gas emissions. I asked the minister about that. He had no evidence of
that whatsoever. He didn't even know whether that was part of his study when I
asked him about that a few moments ago. But if you go to their climate change
policy, they actually claim that the building of this bridge is part of their
climate change policy. Whoa. There's a leap. It's not even a leap of faith.
Increasing highway capacity will actually encourage more cars into
the system, fewer transit trips — despite what the minister alleges, and for
which he has no evidence whatsoever — fewer walking trips, fewer trips that
actually encourage anything other than the use of the car.
My question is this: what evidence does the government have that
tells us that we're actually going to reduce greenhouse gas emissions through
going ahead with the gateway program? That's what their website says.
Hon. K. Falcon: First of all, let me preface my comment by
reminding the member that again she's
[ Page 12056 ]
wrong. I have lost count of how many times she's been wrong. That member
actually rammed through the millennium project over her own environmental
assessment policies of her government of the day — a shameful display of
government arrogance and brutality on the people who were concerned about those
issues.
What I will say regarding greenhouse gas emissions….What the
member should know is that actually having traffic idling 16 hours a day in
traffic isn't really good for the environment. That might be news to the member,
but it actually is not helpful to have cars sitting there three and four hours a
day, each way, trying to get through a traffic corridor. That's bad for the
environment.
[1615]
Part of the great thing about the twinning of the Port Mann Bridge
is that we now have additional options to consider — options like, for example,
public transit corridors, bicycle paths, new HOV lanes, the consideration of
dedicated commercial lanes — ways that we can continue, through demand
management models, to actually improve the environmental impact while at the
same time freeing up the most congested corridor in the province. That's exactly
what we're going to do.
J. MacPhail: Is that part of the business plan — each and
every one of those?
Hon. K. Falcon: Yes. Again, it is part of the preliminary
business plan that we're working on. It will go to public consultation in the
fall to ensure we get full input, because we may get some more good ideas out of
the public consultation process. But yes, that is part of it.
J. MacPhail: Boy, it seems that everything we ask is part
of the business plan. It seems to be pretty fully shaped. Why is the government
hiding it?
The minister doesn't want to answer. Interesting. No wonder this
government wants to shut down this Legislature: they actually don't want to
answer the questions. So we're supposed to trust the government that all of
these greenhouse gas–reducing ideas are included.
When I asked the minister just moments ago whether he could even
tell me whether that was part of the study, he didn't know. Reducing greenhouse
gas emissions. He said: "Oh, I have no idea." He says: "I don't know. I'll get
you that information." Now it turns out that, oh, they're a model of it. Let me
see who they trust — British Columbians.
Well, let me ask this to the minister: what study has he done to
show that congestion will be reduced and that cars will idle less? What exact
studies has he done?
Hon. K. Falcon: Again, as I have said to the member many
times, these are the preliminary results we have, based on the information that
we've done to date. We continue to work on that and gather that information.
During the public consultative process in the fall we will fully and completely
work through that information as we get more input from stakeholders and members
of the public.
J. MacPhail: I don't think the public is going to do a
study on reducing congestion. The government presents to the public their
studies on how this is going to reduce congestion.
My gosh. This is pretty basic stuff: what studies will the
government present to the public to show that their gateway project reduces
congestion, and what will that study demonstrate?
Hon. K. Falcon: That will be included in the information we
bring forward in the fall and share with the public for public input.
J. MacPhail: Is the study being done right now? Who's doing
it? How much is it costing?
Hon. K. Falcon: The work is part of the work being
undertaken by the dedicated project team we have on the gateway project. They
will continue to do that work, as they will continue all the other preliminary
work that is underway in terms of environmental assessment work, engineering
scope, etc. Once we enter into the public consultative process in the fall, all
that work will be shared with all members of the public and all stakeholders.
J. MacPhail: I need more specifics than that. Surely, the
study has already been set up, because a congestion study has to be done over a
period of time — on a monthly basis; also on a daily basis and an hourly basis.
Who's doing the congestion study? Over what period of time? When
will it be completed? And how much does it cost? The gateway project team can
tell me that.
[1620]
Hon. K. Falcon: I've answered this multiple times. I'll try
one more time. This is part of the work that the project team is undertaking.
The project team is undertaking a whole range of work associated with this
project. They will have all of that information available as the consultative
process begins in the fall. All the stakeholders, including that interested
member, will have every opportunity to have input once the information is shared
in the fall.
J. MacPhail: Maybe the minister could tell me the terms of
reference for the congestion study that the gateway project is undertaking.
Hon. K. Falcon: As part of the business plan, all of these
areas get fully explored. In the fall in the public consultation phase of this
project, all of the information will be shared with interested stakeholders,
members of the public and, of course, the member opposite.
[ Page 12057 ]
J. MacPhail: Well, maybe I could then take it one step back.
Are there terms of reference for a congestion study? I won't even ask the
minister to reveal what they are. Are there terms of reference?
Hon. K. Falcon: There are terms of reference for all
technical studies that we undertake in respect to the project.
J. MacPhail: Could the minister name the technical studies,
please?
Hon. K. Falcon: They're on a whole range of issues. I don't
have them at my fingertips, but they're on a whole range of issues the project
team is undertaking that will, again, be made fully available in the fall public
consultative process.
J. MacPhail: I can hardly wait. Everybody's going to be
real busy.
Tell me how big the gateway project team is that is doing all of
these studies the minister keeps referring to. How many people are dedicated to
this?
Hon. K. Falcon: The core team is about 24 individuals. They
in turn, of course, will engage and utilize consultants.
J. MacPhail: It's ridiculous to suggest that a team of 24
can do all of these studies. The minister knows that, and the staff knows that.
No wonder the public is cynical about these pre-election and election
announcements that this minister makes. He's got nothing to back it up.
Will the congestion study include the level of greenhouse gas
emissions and the effect of the project on greenhouse gas emissions?
Hon. K. Falcon: Part of the analysis will include that.
Again, that will be part of the information that comes forward in the public
consultative process.
J. MacPhail: What is the link between the congestion study
and the study on determination of the level of the greenhouse gas emissions? Is
this a model that the government itself is making up starting from scratch, or
are they models that they've examined and that they'll be replicating?
[1625]
Hon. K. Falcon: Those are technical details that I'm not
aware of and I don't have at my fingertips, but I can assure the member that
that is part of what the project team is undertaking. The project team, of
course, once they conclude and gather all that information, will share that with
the public during the public consultative process in the fall, which all
stakeholders, the public and the member opposite will have an opportunity to be
part of.
J. MacPhail: Well, I guess all the government members just
want to say "aye, aye" to a $200 million expenditure and that it's ridiculous
that the opposition would ask for this technical information, because the
minister doesn't have it with him.
Yesterday the Minister of Forests didn't have his information with
him. I still haven't received it. Today the Minister of Transportation says:
"Trust us. Give us the money. We don't have any of the studies. You can't have
access to them. They're not done; they're not public. I can't give you the terms
of reference. I don't have any studies elsewhere to show that what we're doing
is the right thing to do."
Here's what every other study showed. Every other study showed
that when you add capacity, congestion is either the same or worse, and
greenhouse gas emissions go up. I've named the studies where that's
demonstrated.
This government seems to think that although the minister can
provide me no evidence whatsoever, all of their studies — which we have no
details on — will prove exactly the opposite. He can't name the terms of
reference. He can't name the range of studies. He can't name the time line. He
can't tell me who's doing them, and he can't tell me what the budget is for
them. But, oh, we're supposed to trust this government that their studies will
show what no other jurisdiction has ever achieved.
Well, I'd like to say gee, if you believe that, I've got a bridge
for you to buy. But unfortunately, in this case it's true. British Columbians
are going to have to buy a bridge, to the tune of $800 million. This government
can't…. I should say, actually, that this minister can't demonstrate one single,
solid, factual basis upon which we should invest in that bridge — not one. He's
got no construction time line. He's going to leave it up to the people to decide
the construction time line. He has no plan for consultation. That'll roll out.
He's got no budget. He's got no technical studies. This is the equivalent of
asking people to buy a pig in a poke. It is shameful that these Liberal MLAs sit
here and allow this to happen.
Vote 37(
S) approved.
Hon. K. Falcon: I move that the committee rise and report
resolution.
Motion approved.
The committee rose at 4:28 p.m.
The House resumed; Mr. Speaker in the chair.
[1630]
Committee of Supply reported resolution.
Mr. Speaker: When shall the report be considered?
Hon. K. Falcon: Forthwith. I move that the report of
resolution from the Committee of Supply on February 22, 2005, be now received,
taken as read and agreed to.
[ Page 12058 ]
Motion approved.
Hon. K. Falcon: I move that there be granted from and out
of the consolidated revenue fund the sum of $550 million. This sum is in
addition to that authorized to be paid under
section 1 of the Supply Act,
2004-2005, and is granted by Her Majesty towards defraying the charges and
expenses of the public service of the province for the fiscal year ending March
31, 2005.
Motion approved.
Introduction and
First Reading of Bills
SUPPLY ACT, 2004-2005
(SUPPLEMENTARY ESTIMATES No. 5)
Hon. C. Hansen presented a message from His Honour the
Administrator: a bill intituled Supply Act, 2004-2005 (Supplementary Estimates
No. 5).
Hon. C. Hansen: I move that the bill be introduced and read
a first time now.
Motion approved.
Hon. C. Hansen: The use of supplementary estimates is
consistent with the spirit of the Budget Transparency and Accountability Act.
This supply bill is introduced to provide supply for the operations of programs
for the 2004-05 fiscal year, as outlined in the supplementary estimates (No. 5)
tabled earlier. The bill will provide the additional funds required to defray
the charges and expenses of the public service of the province for the fiscal
year ending March 31, 2005. In accordance with established practice, the
government seeks to move this bill through all stages this day.
Mr. Speaker: Hon. members, in keeping with the practice of
this House, the bill will be permitted to advance through all stages in one
sitting.
Bill 12 introduced, read a first time and ordered to proceed to
second reading forthwith.
Second Reading of Bills
SUPPLY ACT, 2004-2005
(SUPPLEMENTARY ESTIMATES No. 5)
Hon. C. Hansen: I move that Bill 12 be now read a second
time.
Motion approved.
Hon. C. Hansen: I move the bill be now referred to a
Committee of the Whole House for consideration forthwith.
Bill 12, Supply Act, 2004-2005 (Supplementary Estimates No.
5), read a second time and referred to a Committee of the Whole House for
consideration forthwith.
Committee of the Whole House
SUPPLY ACT, 2004-2005
(SUPPLEMENTARY ESTIMATES No. 5)
The House in Committee of the Whole on Bill 12; H. Long in the
chair.
The committee met at 4:35 p.m.
Sections 1 and 2 approved.
Schedule approved.
Preamble approved.
Title approved.
Hon. C. Hansen: I move that the committee rise and report
the bill complete without amendment.
Motion approved.
The committee rose at 4:35 p.m.
The House resumed; Mr. Speaker in the chair.
Report and
Third Reading of Bills
Bill 12, Supply Act, 2004-2005 (Supplementary Estimates No. 5),
reported complete without amendment, read a third time and passed.
Supplementary Estimates
Hon. C. Hansen presented a message from His Honour the
Administrator: supplementary estimates (No. 6) for the fiscal year ending March
31, 2005.
Hon. C. Hansen moved that the said message and the estimates
accompanying the same be referred to Committee of Supply.
Motion approved.
Committee of Supply
The House in Committee of Supply; H. Long in the chair.
The committee met at 4:39 p.m.
SUPPLEMENTARY ESTIMATES:
OFFICERS OF THE LEGISLATURE
Vote 4-D(S): Elections B.C., $545,000 — approved.
[ Page 12059 ]
[1640]
Hon. C. Hansen: I move that we rise, report resolution and
ask leave to sit again.
Motion approved.
The committee rose at 4:41 p.m.
The House resumed; Mr. Speaker in the chair.
Committee of Supply reported resolution.
Mr. Speaker: When shall it be considered as read?
Hon. C. Hansen: Forthwith. I move the report of resolution
from the Committee of Supply on February 22, 2005, be now received, taken as
read and agreed to.
Motion approved.
Hon. C. Hansen: I move that there be granted from and out
of the consolidated revenue fund the sum of $545,000. This sum is in addition to
that authorized to be paid under
section 2 of the Supply Act, 2004-2005, and is
granted by Her Majesty to defray the capital expenditures requirements of the
province for the fiscal year ending March 31, 2005.
Motion approved.
Hon. C. Hansen: I call Committee of Supply for the
consideration of vote 5(
S) regarding the information and privacy commissioner.
Committee of Supply
The House in Committee of Supply; H. Long in the chair.
The committee met at 4:44 p.m.
SUPPLEMENTARY ESTIMATES:
OFFICERS OF THE LEGISLATURE
Vote 5(S): information and privacy commissioner, $115,000 —
approved.
Hon. C. Hansen: I move that the committee rise and report
resolution.
Motion approved.
The committee rose at 4:45 p.m.
The House resumed; Mr. Speaker in the chair.
Committee of Supply reported resolution.
Mr. Speaker: When shall the report be considered?
Hon. C. Hansen: Forthwith. I move that the report of
resolution from the Committee of Supply on February 22, 2005, be now received,
taken as read and agreed to.
Motion approved.
Hon. C. Hansen: I move that there be granted from and out
of the consolidated revenue fund the sum of $115,000. This sum is in addition to
that authorized to be paid under
section 1 of the Supply Act, 2004-2005, and is
granted by Her Majesty to defray the charges and expenses of the public service
of the province for the fiscal year ending March 31, 2005.
Motion approved.
Hon. C. Hansen: I call Committee of Supply to consider vote
6(
S) regarding the budget for the ombudsman's office.
Committee of Supply
The House in Committee of Supply; H. Long in the chair.
The committee met at 4:47 p.m.
SUPPLEMENTARY ESTIMATES:
OFFICERS OF THE LEGISLATURE
Vote 6(S): ombudsman, $20,000 — approved.
Hon. C. Hansen: I move that we rise and report resolution.
Motion approved.
The committee rose at 4:48 p.m.
The House resumed; Mr. Speaker in the chair.
Committee of Supply reported resolution.
Mr. Speaker: When shall the report be considered?
Hon. C. Hansen: Forthwith. I move that the report of
resolution from the Committee of Supply on February 22, 2005, be now received,
taken as read and agreed to.
Motion approved.
Hon. C. Hansen: I move that there be granted from and out
of the consolidated revenue fund the sum of $20,000. This sum is in addition to
that authorized to be paid under
section 1 of the Supply Act, 2004-2005, and is
granted by Her Majesty to defray the charges and expenses of the public service
of the province for the fiscal year ending March 31, 2005.
Motion approved.
[ Page 12060 ]
Hon. C. Hansen: I call Committee of Supply to consider vote
7(
S) regarding the budget for the police complaint commissioner.
Committee of Supply
The House in Committee of Supply; H. Long in the chair.
The committee met at 4:49 p.m.
SUPPLEMENTARY ESTIMATES:
OFFICERS OF THE LEGISLATURE
Vote 7(S): police complaint commissioner, $105,000 — approved.
Hon. C. Hansen: I move that the committee rise and report
resolution.
Motion approved.
The committee rose at 4:50 p.m.
The House resumed; Mr. Speaker in the chair.
Committee of Supply reported resolution.
Mr. Speaker: When shall the report be considered?
Hon. C. Hansen: Forthwith. I move that the report of
resolution from the Committee of Supply on February 22, 2005, be now received,
taken as read and agreed to.
Motion approved.
Hon. C. Hansen: I move that there be granted from and out
of the consolidated revenue fund the sum of $105,000. This sum is in addition to
that authorized to be paid under
section 1 of the Supply Act, 2004-2005, and is
granted to Her Majesty towards defraying the charges and expenses of the public
service of the province for the fiscal year ending March 31, 2005.
Motion approved.
Introduction and
First Reading of Bills
SUPPLY ACT, 2004-2005
(SUPPLEMENTARY ESTIMATES No. 6)
Hon. C. Hansen presented a message from His Honour the
Administrator: a bill intituled Supply Act, 2004-2005 (Supplementary Estimates
No. 6).
Hon. C. Hansen: I move that the bill be introduced and read
a first time now.
Motion approved.
Hon. C. Hansen: Mr. Speaker, the use of supplementary
estimates is consistent with the spirit of the Budget Transparency and
Accountability Act. This supply bill is introduced to provide supply for the
operations of government programs for the 2004-05 fiscal year, as outlined in
the supplementary estimates (No. 6) tabled earlier. The bill will provide the
additional funds required to defray the charges and expenses of the public
service of the province for the fiscal year ending March 31, 2005. In accordance
with established practice, the government seeks to move this bill through all
stages this day.
Mr. Speaker: We'll pause for a moment while we distribute
the bill.
Hon. members, in keeping with the practice of this House, the bill
will be permitted to advance through all stages in one sitting.
Bill 13 introduced, read a first time and ordered to proceed to
second reading forthwith.
Second Reading of Bills
SUPPLY ACT, 2004-2005
(SUPPLEMENTARY ESTIMATES No. 6)
Hon. C. Hansen: I move that Bill 13 be now read a second
time.
Motion approved.
Hon. C. Hansen: I move that the bill be now referred to a
Committee of the Whole House for consideration forthwith.
Bill 13, Supply Act, 2004-2005 (Supplementary Estimates No. 6),
read a second time and referred to a Committee of the Whole House for
consideration forthwith.
Committee of the Whole House
SUPPLY ACT, 2004-2005
(SUPPLEMENTARY ESTIMATES No. 6)
The House in Committee of the Whole on Bill 13; H. Long in the
chair.
The committee met at 4:55 p.m.
Sections 1 to 3 inclusive approved.
Schedules 1 and 2 approved.
Preamble approved.
Title approved.
Hon. C. Hansen: I move that the committee rise and report
the bill complete without amendment.
[ Page 12061 ]
Motion approved.
The committee rose at 4:56 p.m.
The House resumed; Mr. Speaker in the chair.
Report and
Third Reading of Bills
Bill 13, Supply Act, 2004-2005 (Supplementary Estimates No. 6),
reported complete without amendment, read a third time and passed.
Supplementary Estimates
Hon. C. Hansen presented a message from His Honour the
Administrator: supplementary estimates (No. 7) for the fiscal year ending March
31, 2005.
Hon. C. Hansen moved that the said message and the estimates
accompanying the same be referred to Committee of Supply.
Motion approved.
Committee of Supply
The House in Committee of Supply; H. Long in the chair.
The committee met at 5 p.m.
SUPPLEMENTARY ESTIMATES:
MINISTRY OF COMMUNITY, ABORIGINAL
AND WOMEN'S SERVICES
On vote 17(S): ministry operations, $40,000,000.
Hon. M. Coell: Mr. Speaker, if I can just take a moment to
outline why I'm requesting this. In February the province started negotiations
with the Peace River regional district and its member municipalities to renew
the MOU on oil and gas revenue allocation. The oil and gas sector is spread
widely over the rural territory, and these local governments do not have
adequate industrial tax base support. As a result, historical infrastructure
deficits have arisen in some municipalities in the Peace River and Northern
Rockies regional districts.
These deficits are principally in the formerly rural subdivisions
that were originally developed with low service standards in specific areas
around Fort St. John. The $40 million will address these deficits. Under the
proposed MOU the Peace River regional district will continue to compensate in
lieu of access to the rural tax base.
It is proposed that an unconditional grant in lieu of taxes for
the region also be increased by $8 million. That was $12 million in the previous
year and will go to $20 million effective April 1, 2005. The $20 million, when
added to the existing municipal infrastructure tax proceeds in the Peace River
district, brings the total annual proceeds from industry in the region to about
$29 million in total. The $40 million is a one-time cash payment to open and
close, I guess, the new MOU. I think it's very good news for the northeast, and
they'll put that money to good use for infrastructure throughout the area.
I might add that the Fair Share agreement dates back to 1989, when
the provincial government and the Peace River regional district reached an
agreement where the province would transfer $12 million per year until the
fiscal year 2007-08. There was a reopener clause in that MOU, and that could be
triggered after five years. That had begun.
In April 2004 the provincial government provided a one-time
payment of $6 million to the communities in the PRRD in recognition that two
years would pass before the mid-term negotiations could be expected to conclude.
I'm very pleased that the negotiations have been successful. I look forward to
questions from members in the Legislature.
J. Kwan: The government had put out a press release on
budget day announcing this spending. Why did the government wait until budget
day of 2005 to announce this 2004 spending?
Hon. M. Coell: The negotiations had just reached a point
where we could do that, and it seemed an appropriate time.
J. Kwan: So it has nothing really to do with the
pre-election goodies that the government wants to announce three months in
advance of the election.
Maybe the minister could tell me where the $40 million came from
with the existing budget. Is it unspent dollars within the ministry, or is it
new money that came from contingency? Where did the moneys come from for this
2004 line item?
Hon. M. Coell: It's beyond the budget. It would be coming
from new growth in the economy and new funds into this ministry.
J. Kwan: We understand that the northeast communities have
been lobbying for $80 million as opposed to $40 million. Is another $40 million
built into the 2005 budget?
Hon. M. Coell: No. This is the offer that was made, and the
$40 million is what we hope would be the only payment.
[1705]
J. Kwan: This is locked in for how many years? Is there
another reopener in terms of potential negotiations for the MOU in the future?
Hon. M. Coell: There is a proposed escalator in the yearly
budget, but the MOU hasn't been finalized yet, so I can't say whether there will
be a reopener at some point in the future.
[ Page 12062 ]
J. Kwan: The February 15 news release states, "Allocation of
the $40 million will be determined by discussion with the local governments in
the region and the province. Negotiations continue toward finalizing a new
memorandum of understanding before the end of the month," which the minister
just acknowledged that he has not yet completed. Who is doing the negotiations
at the moment?
Hon. M. Coell: Mr. Vince Collins, on behalf of the
government, is the negotiator.
J. Kwan: What will the total amount be now — the total
investment dollars in the northeast part of British Columbia for the last fiscal
year — with this additional $40 million?
Hon. M. Coell: The total would be the $12 million that was
in the budget and allocated, plus this $40 million one-time funding.
J. Kwan: This is one-time money, so with the negotiations
that are coming — or that will be finalized — it is not anticipated that there
will be any more additional dollars. This is not ongoing over a period of time?
Hon. M. Coell: The total dollars would be the one-time
funding of $40 million, and then we've added or offered $8 million on top of the
$12 million for $20 million a year consistently after that. There would be an
escalator cost added to that $20 million, as well, over the years to come.
J. Kwan: The February 15 release also refers to the annual
funding of $20 million. Is that spending in the 2005 budget then — that $20
million?
Hon. M. Coell: That will be in the 2005-06 budget, the $20
million.
J. Kwan: Does this have anything to do with the $135
million northern trust initiative that was announced several times last year?
Hon. M. Coell: No, they are not directly related.
J. Kwan: Is there any relationship with this year's budget
that includes $366 million invested in the northern forestry and the energy and
mining area? Does this have anything to do with that budget item, or is that
completely separate also?
[J. Weisbeck in the chair]
Hon. M. Coell: Yes, it's separate as well. This is really
to do with the Fair Share agreement that dates back to 1998 and had the reopener
clause in it. I think what the communities in the northeast were hoping for is
that when it got to this stage, when they reopened, there would be a lump sum
payment and then an increase in the yearly funding to cover infrastructure. It's
really a stand-alone amount of money dating back to the Fair Share agreement.
J. Kwan: Yes, I remember the Fair Share ag