Construction Regulations (N.S. Reg. 176/2015) (just regulations regs envfees.htm)

N.S. Reg. 176/2015

Nova Scotia — Regulations

Construction Regulations (N.S. Reg. 176/2015) (just regulations regs envfees.htm)

N.S. Reg. 176/2015

Nova Scotia — Regulations

This consolidation is unofficial and is for reference only.

For the official version of the regulations, consult the original documents on file with the Office of the Registrar of Regulations , or refer to the Royal Gazette

Part II .

Regulations are amended frequently.

Please check the list of Regulations by Act to see if there are any recent amendments to these regulations filed with our office that are not yet included in this consolidation.

Although every effort has been made to ensure the accuracy of this electronic version, the Office of the Registrar of Regulations assumes no responsibility for any discrepancies that may have resulted from reformatting.

This electronic version is copyright ©

, Province of Nova Scotia , all rights reserved. It is for your personal use and may not be copied for the purposes of resale in this or any other form.

Fees Regulations

made under clause 8A(1)(

a) of the

Environment Act

S.N.S. 1994-95, c. 1

N.S. Reg. 176/2015 (effective April 1, 2015)

amended to N.S. Reg. 85/2026 (effective March 24, 2026)

Table of Contents

Please note: this table of contents is provided for convenience of reference and does not form part of the regulations.

Click here to go to the text of the regulations .

Citation

Part 1: Environment Act

Filing fees for remediation reports

Fee for request for information from the environmental registry

Industrial air emission fees

Application fee for appeal to Minister

Part 2: Regulations Made Under the Environment Act

Activities Designation Regulations

Application fee for Division I water (water withdrawal) approval or renewal

Annual administration fee for Division I water (water withdrawal) approval

Annual approval to use fee for Division I water (water withdrawal) approval

Application fee for Division I water (non-water withdrawal) approval or renewal

Application fee for Division IV salvage yard approval or renewal

Application fees for Division V industrial approval or renewal

Environmental Assessment Regulations

Fees for undertakings requiring environmental assessments

Motive Fuel and Fuel Oil Approval Regulations

Application fee for initial motive fuel wholesaler and fuel oil wholesaler approval

Application fee for 10-year motive fuel retailer and fuel oil retailer approval

Transfer and amendment fee

Application fee for renewal of motive fuel wholesaler approval

Application fee for renewal of fuel oil wholesaler approval

On-site Sewage Disposal Systems Regulations

Fee for reviewing subdivision report

Application fee for on-site sewage installer certificate of qualification or renewal

Application fee for on-site sewage disposal system approval or renewal

Pesticide Regulations

Application fee for pesticide certificate of qualification or renewal

Application fee for pesticide approval or renewal

Petroleum Management Regulations

Annual registration fees for petroleum storage tank or system

Used Oil Regulations

Application fees for a used oil collector approval or renewal

Water and Wastewater Facilities and Public Drinking Water Supplies Regulations

Application fee for facility classification or reclassification

Examination fee for operator in training operator certification exam

Application fees for operator certification certificate or renewal

Well Construction Regulations

Application fees for well construction certificate of qualification or renewal

Citation

1 These regulations may be cited as the Fees Regulations .

Part 1: Environment Act

Filing fees for remediation reports

(1) In this Section, a “remediation report” includes any report filed with the

Department that documents a risk assessment, site management, or site

remediation of a residual contamination on a site regardless of whether or not

active site remediation was necessary.

(2) The types of remediation reports are as follows:

(

a) Type A – a remediation report for a domestic fuel oil spill, if the report is

either

(

i) criteria-based, or

(ii) Tier I risk assessment or remediation;

(

b) Type B – a remediation report for a domestic fuel oil spill, if the report is

either

(

i) Tier II risk assessment or remediation, or

(ii) Tier III risk assessment or remediation;

(

c) Type C – a remediation report for a non-domestic site, if the report is either:

(

i) criteria-based, or

(ii) Tier I risk assessment or remediation;

(

d) Type D – a remediation report for a non-domestic site with a single

contaminant of concern if the report, with risk-based corrective action, is

either

(

i) Tier II risk assessment or remediation, or

(ii) Tier III risk assessment or remediation

and the report has no use restrictions, no controls and no off-site impacts;

(

e) Type E – a remediation report for a non-domestic site with multiple

contaminants of concern if the report, with risk-based corrective action, is

either

(

i) Tier II risk assessment or remediation, or

(ii) Tier III risk assessment or remediation

and the report has no use restrictions, no controls and no off-site impacts;

(

f) Type F – a remediation report for a non-domestic site if the report, with risk-based corrective action, is either

(

i) Tier II risk assessment or remediation, or

(ii) Tier III risk assessment or remediation

and the report has use restrictions, controls or off-site impacts.

(3) The filing fees for a report on the remediation of contaminated sites and releases

under

Part VI and

Part VIII of the Environment Act, by the type of report identified

in subsection (2), are as set out in the following table:

Table 1

Remediation Report Filing Fees

Type of Remediation Report

Filing Fee

Type A

$149.60

Type B

$311.45

Type C

$311.45

Type D

$685.25

Type E

$1027.95

Type F

$1526.30

(4) If a remediation report does not adequately demonstrate that the requirements of

the Department are met and a new report is required by the Department, the filing

fee prescribed in subsection (3) must be re-paid in full when the report is re-filed .

(5) Confirmatory monitoring conditions may be included in a Record of Site

Compliance, Certificate of Compliance or other conditional release from site action

requirements, and if the person responsible asks the Department to be formally

released from further confirmatory monitoring obligations, the applicable fee

prescribed in subsection (3) must be paid in full to the Department.

Fee for request for information from the environmental registry

3 The fee for a request for information from the environmental registry established under

Section 10 of the Environment Act is $26.50 for each civic address submitted for a search.

Industrial air emission fees

(1) In this Section, “pollutants” means a total release to air including any one of or

combination of the following:

(

a) sulphur dioxide;

(

b) particulate matter, which includes reported annual emissions of total

particulate matter, PM 10 , or PM 2.5 , whichever is greatest;

(

c) other releases to air, as listed in subsection (2).

(2) The other releases to air referred to in clause (1)(

c) are as set out in the following

table:

Table 2

Other Releases to Air—Pollutants

• ammonia (total)

• antimony and its

compounds

• carbon monoxide

• chlorine

• chromium and its

compounds

• cobalt and its compounds

• copper and its compounds

• cresol (mixed isomers and

their salts)

• di-ethanolamine and its

salts

• hydrochloric acid

• hydrogen cyanide

• hydrogen sulphide

• manganese and its

compounds

• nickel and its compounds

• oxides of nitrogen (NO 2 )

• phosphorus (total)

• selenium and its

compounds

• sulphuric acid

• vanadium (except when in

an alloy) and its

compounds

• zinc and its compounds

• volatile organic compounds

(VOCs), including:

- 1, 2, 4-trimethylbenzene

- 7H-dibenzo(c,g)carbazole

- acetaldehyde

- benzene

- benzo(a)anthracene

- benzo(a)phenathrene

- benzo(a)pyrene

- benzo(b)flouranthene

- benzo(e)pyrene

- benzo(g,h,i)perylene

- benzo(j)flouranthene

- benzo(k)flouranthene

- biphenyl

- chloromethane

- cumene

- cyclohexane

- dibenz(a,j)acridine

- dibenzo(a,h)anthracene

- dibenzo(a,i)pyrene

- dibutyl phthalate

- dichloromethane

- ethylbenzene

- ethylene

- ethylene glycol

- flouranthene

- formaldehyde

- isopropyl alcohol

- methanol

- naphthalene

- n-hexane

- perylene

- phenanthrene

- phenol and its salts

- propylene

- pyrene

- styrene

- toluene

- trichloroethylene

- xylene (all isomers)

(3) The industrial air emission fees per year for facilities in Nova Scotia are based on the

rates set out in the following table:

Table 3

Industrial Air Emission Fees

Class

Threshold

(tonnes of pollutants/year)

Rate

(per tonne of pollutants)

≥30

$7.35/tonne

<30

no fee

Application fee for appeal to Minister

5 The application fee for a person who is aggrieved to appeal to the Minister under

Section

137 of the Environment Act is $108.95.

Part 2: Regulations Made Under the Environment Act

Activities Designation Regulations

Application fee for Division I water (water withdrawal) approval or renewal

(1) Except as provided in subsection (2), the application fee for an initial water

withdrawal approval or for a renewal of the approval for each term as required under

clause 5(1)(

a) of Division I of the Activities Designation Regulations is $331.75.

(2) The application fee in subsection (1) does not apply to agriculture, aquaculture or

recreational water withdrawal activities.

Annual administration fee for Division I water (water withdrawal) approval

7 The administration fee per year for a water withdrawal approval holder, under clause

5(1)(

a) of Division I of the Activities Designation Regulations , by category of use of water

withdrawal approval is as follows:

(

a) Category I – for hydroelectric use ......................................................... $663.45

(

b) Category II – for domestic, industrial, bottled water, or public drinking water

supply use ............................................................................................. $265.40

Annual approval to use fee for Division I water (water withdrawal) approval

(1) In addition to the administrative fee in

Section 7, subject to the minimum annual

approval to use fee set out in subsection (2), and except as provided in subsections

(3) and (4), the approval to use fee per year for a water withdrawal approval holder,

under clause 5(1)(

a) of Division I of the Activities Designation Regulations is as

follows:

(

a) for municipal, recreational, industrial or domestic purposes, the approval to use

fee is the total of all amounts calculated as follows:

(

i) for each 1 000 000 L per day up to 2 000 000 L ........................... $145.95

(ii) plus for each additional 1 000 000 L per day over

2 000 000 L and up to 9 000 000 L .............................................. $152.50

(iii) plus for each additional 1 000 000 L per day over

9 000 000 L and up to 27 000 000 L ............................................ $165.90

(iv) plus for each additional 1 000 000 L per day over

27 000 000 L and up to 90 000 000 L .......................................... $172.45

(

v) plus for each additional 1 000 000 L per day over

90 000 000 L ............................................................................... $179.10

(

b) for a fish farming or a fish hatchery operation use, the approval to use fee is

20% of the amount determined under clause (a);

(

c) for hydroelectric power generation use, the approval to use fee is calculated at

the rate of $2.10 per horsepower of rated hydraulic capacity.

(2) Except as provided in subsections (3) and (4), the minimum approval to use fee per

year for a water withdrawal approval is $66.15.

(3) The holder of a water withdrawal approval authorizing the use of water for

agriculture, conservation, or beautification purposes is exempt from the approval to

use fee.

(4) To retain a water withdrawal approval if the approval holder temporarily suspends

their use of water for more than 90 days, the approval to use fee per year may be

reduced to the greater of

(a) 10% of the amount calculated under subsection (1); and

(b) $265.40.

(5) The fee reduction provided for in subsection (4) does not apply to a water

withdrawal approval that authorizes water withdrawal for use only during one season

of the year.

Application fee for Division I water (non-water withdrawal) approval or renewal

(1) The activities requiring a Division I water (non-water withdrawal) approval and

included in the categories referred to in subsections (2) and (3) are as set out in the

following table:

Table 4

Categories of Non-Water Withdrawal Activities

Category I activities :

construction or

maintenance of a culvert

construction or

maintenance of a wharf

placement of a rock or

other erosion protection

material in a surface

watercourse

construction or

maintenance of a bridge if

(

i) a portion of the

structure of the bridge

is in a watercourse, or

(ii) the use of equipment

in the watercourse or 3

m from the edge of the

watercourse is

required

construction or

maintenance of a weir,

fishway or other in-stream

structure

installation or

maintenance of fishing

equipment, a fish-way, a

counting fence, a fish

habitat improvement

structure, an aquaculture

cage or any similar

structure in a watercourse

Category II activities:

Any other alteration of a surface watercourse or the flow of the water in a surface

watercourse requiring a Division I water (non-water withdrawal) approval which is

not listed as activity under another category.

(2) Except as provided in subsection (3), the application fees for an initial water

approval or for a renewal of the approval for each term as required under Division I

of the Activities Designation Regulations , other than for a water withdrawal approval

under clause 5(1)(a), by category of water (non-water withdrawal) approval are as

follows:

(

a) Category I ............................................................................................. $124.60

(

b) Category II ............................................................................................ $311.45

(3) The application fee set out in subsection (2) does not apply to an application by the

Department of Transportation and Infrastructure Renewal.

Application fee for Division IV salvage yard approval or renewal

10 The application fee for an initial salvage yard approval or a renewal of the approval for ten

years under Division IV of the Activities Designation Regulations is $330.05.

Application fees for Division V industrial approval or renewal

(1) The activities requiring an industrial approval as listed in the “Parts” under the

Division V-Industrial Approvals provisions of the Activities Designation Regulations

and included in the categories referred to in subsection (2) are as set out in the

following table:

Table 5

Categories of Activities Requiring Industrial Approval

Category I activities:

Part 1: Chemical plants

• chemical manufacturing

• fertilizer manufacturing

• explosives manufacturing

• pesticide manufacturing

• petrochemical manufacturing

• coke or carbon manufacturing

• pharmaceutical manufacturing

Part 2: Construction

•cement plant

Part 3: Food or fish

and animal by-product

•fish meal plant

Part 4: Metal

• iron and steel mill

Part 5: Mineral

•mineral processing

plant

Part 6: Oil and gas

•oil refinery

•natural gas processing

plant

Part 7: Wood product plants

• pulp manufacturing

• pulp and paper

manufacturing

• wood treatment

Part 8: Primary

manufacturing plants

•textile manufacturing

•tire manufacturing

Part 9: Power plants

•power plant

Part 11: Biotechnology

• biotechnology products

manufacturing plant

Part 12: Miscellaneous

•industrial incinerator

•industrial landfill

Category II activities:

An activity designated in the Division V industrial approvals under the Activities

Designation Regulations that is not listed as an activity under another category.

Category III activities:

Part 1: Chemical

• fertilizer storage facility

• industrial cleaners

manufacturing facility

Part 2: Construction

•asphalt paving plant

•stationary ready mix

concrete plant

•pit

•topsoil removal

operation

Part 3: Food or fish

and animal by-products

•inland fish processing

plant

•fish silage operation

Part 5: Minerals

• bulk sample site

• bulk solids handling loadout

facility

Part 6: Oil and gas

•brine storage pond

•used oil collection

facility with storage

capacity of less than

50 000 L (otherwise

under category II)

Part 12: Miscellaneous

• crematorium

• cemetery

Category IV activities:

Part 3: Food or fish and animal by-products

dairy or dairy products plant that processes less than 250 000 L of milk per year

(2) The application fee for an initial industrial approval or for a renewal of the approval

for each term as required under Division V of the Activities Designation Regulations

is as follows:

(

a) Category I ........................................................................................... $8625.15

(

b) Category II .......................................................................................... $3317.35

(

c) Category III ......................................................................................... $1326.95

(d)Category IV .......................................................................................... $484.00

Environmental Assessment Regulations

Fees for undertakings requiring environmental assessments

(1) The undertakings requiring environmental assessments and included in the categories

referred to in subsection (2), are as set out in the following table:

Table 6

Categories of Undertakings Requiring Environmental Assessment

Category I undertakings :

An undertaking designated as a “class II undertaking” as listed in

Schedule “A” to the

Environmental Assessment Regulations .

Category II undertakings :

An undertaking designated as a “class I undertaking” as listed in

Schedule “A” to the

Environmental Assessment Regulations except if the undertaking is set out as a

Category III undertaking.

Category III undertakings :

A facility for manufacturing wood products that are pressure-treated with chemical

products designated as a “class I undertaking” under

Section 2 of Part A: Industrial

facilities of the Class I Undertakings as listed in

Schedule A to the Environmental

Assessment Regulations .

An undertaking designated as a “class I undertaking” under Part E: Waste Management

of the Class I Undertakings as listed in

Schedule A to the Environmental Assessment

Regulations .

An undertaking designated as a “class I undertaking” under Part F: Other of the Class I

Undertakings as listed in

Schedule A to the Environmental Assessment Regulations .

(2) The fees for a undertaking requiring an assessments under the Environmental

Assessment Regulations are as follows:

(

a) Category I undertaking registration ................................................... $17 250.40

(

b) Category II undertaking registration ................................................. $11 146.40

(

c) Category III undertaking registration ................................................... $6369.35

(

d) approval transfer ................................................................................... $662.85

(

e) focus report ......................................................................................... $6634.75

(

f) environmental assessment report ...................................................... $17 250.40

(

g) additional information request .............................................. 1/2 registration fee

(3) The approval transfer fee set out in clause (2)(

d) applies if an approval is transferred

from one proponent to another.

(4) The fees set out in clauses (2)(e), (

f) and (

g) apply only to Category II and III

undertakings and only if the Minister decides that the report or information is

required.

(5) In addition to the fees set out in subsection (2), a proponent is responsible for

(

a) all costs associated with an environmental assessment review panel review and

hearing; and

(

b) all costs associated with a joint federal-Provincial environmental assessment

panel.

Motive Fuel and Fuel Oil Approval Regulations

Application fee for initial motive fuel wholesaler and fuel oil wholesaler approval

13 The application fee for an initial motive fuel wholesaler and fuel oil wholesaler approval

for 1 year under the Motive Fuel and Fuel Oil Approval Regulations is as follows:

(

a) motive fuel wholesaler ........................................................................ $1993.50

(

b) fuel oil wholesaler ................................................................................ $132.65

Application fee for 10-year motive fuel retailer and fuel oil retailer approval

13A The application fee for a 10-year motive fuel retailer and fuel oil retailer approval under

the Motive Fuel and Fuel Oil Approval Regulations is as follows:

(

a) motive fuel retailer ................................................................................ $436.00

(

b) fuel oil retailer ...................................................................................... $436.00

Transfer and amendment fee

14 The fee for a transfer of or an amendment to any approval under the Motive Fuel and Fuel

Oil Approval Regulations is $132.65.

Application fee for renewal of motive fuel wholesaler approval

(1) Subject to the minimum application fee set out in subsection (2), the application fee

for a renewal of a motive fuel wholesaler approval per year under the Motive Fuel

and Fuel Oil Approval Regulations is calculated based on the total motive fuel

volume sold at the rate per litre of $0.00045.

(2) The minimum fee for applying to renew a motive fuel wholesaler approval per year

is $1993.50.

16 [repealed]

Application fee for renewal of fuel oil wholesaler approval

(1) The application fee for the renewal of a fuel oil wholesaler approval per year is as

follows:

(

a) if the volume is less than 50 000 L .......................................................... $13.30

(

b) if the volume is greater than 50 000 L, subject to the minimum fee set out in

subsection (2), the application fee for the renewal of a fuel oil wholesaler

approval per year under the Motive Fuel and Fuel Oil Regulations is calculated

based on the total fuel oil volume sold at the rate per litre of $0.000130.

(2) The minimum application fee for applying to renew a fuel oil wholesaler approval

per year for a volume greater than 50 000 L is $132.65.

On-site Sewage Disposal Systems Regulations

Fee for reviewing subdivision report

18 The fees for reviewing a subdivision report are as follows:

(

a) for a subdivision with fewer than 3 lots .............................................. no charge

(

b) for a subdivision with at least 3 lots and no more than 10 lots ............... $232.35

(

c) for a subdivision with more than 10 lots ................................................ $630.45

Application fee for on-site sewage installer certificate of qualification or renewal

19 The application fee for an initial on-site sewage installer certificate of qualification or for a

renewal of the certificate of qualification per year as required under the On-site Sewage

Disposal Regulations is $166.05.

Application fee for on-site sewage disposal system approval or renewal

20 The application fee for an initial on-site sewage disposal system approval, for installation

within in a specified term, or for a renewal of the approval as required under the On-site

Sewage Disposal Systems Regulations is $66.35.

Pesticide Regulations

Application fee for pesticide certificate of qualification or renewal

(1) Subject to the reduced fee for applications for additional certificates of qualification

provided for in subsection (2), the application fee for an initial certificate of

qualification or a renewal of the certificate of qualification for five years and by class

of certificate of qualification as established under the Pesticide Regulations are as

follows:

(

a) Class I – Vendor ..................................................................................... $66.35

(

b) Class II – Structural ................................................................................ $66.35

(

c) Class III (A) – Forestry ........................................................................... $66.35

(

d) Class III (B) – Greenhouse ...................................................................... $66.35

(

e) Class III (C) – Industrial Vegetation ........................................................ $66.35

(

f) Class III (D) – Landscape ....................................................................... $66.35

(

g) Class IV – Mosquito and Biting Fly ........................................................ $66.35

(

h) Class V – Aquatic Vegetation ................................................................. $66.35

(

i) Class VI – Fumigation ............................................................................ $66.35

(

j) Class VII – Aerial ................................................................................... $66.35

(

k) Class VIII – Agricultural ......................................................................... $66.35

(

l) Class X – Special ................................................................................... $66.35

(2) If a person applies for more than one class of pesticide certificate of qualification or

renewal, the fee is $66.35 for the first application plus $13.30 for each additional

class applied for.

(3) The application fee for an initial certificate of qualification or a renewal of the

certificate of qualification for a one year period for a Class IX – Business Operator

under the Pesticide Regulations is $33.00.

Application fee for pesticide approval or renewal

22 The application fees for an initial pesticide approval or a renewal of the approval as

required under Division II of the Activities Designation Regulations and the Pesticide

Regulations are as follows:

(

a) a pesticide (non-forestry) approval for an area up to 20 ha ..................... $132.65

plus add for each additional ha over 20 ha ................................................ $5.30

(

b) a pesticide (forestry) approval for an area up to 6 ha ............................... $66.35

plus add for each additional ha over 6 ha .................................................. $5.30

Petroleum Management Regulations

Annual registration fees for petroleum storage tank or system

(1) Subject to the fee reduction provided for in subsection (2), the registration fees per

year for a petroleum storage tank or a petroleum storage tank system that is either

(

a) an underground tank with a nominal capacity of 2000 L or greater;

(

b) an above-ground tank s with a nominal capacity of 4000 L or greater,

are as follows:

• at a bulk plant ....................................................................................... $132.65

• at a motive fuel outlet ........................................................................... $132.65

• at an industrial facility ........................................................................... $132.65

• at a commercial facility ......................................................................... $132.65

• at a marina ............................................................................................ $132.65

• at a government facility .......................................................................... $66.35

(2) The registration fee per year for a petroleum storage tank or petroleum storage tank

system is reduced by 50% if the person registering the tank or system voluntarily

obtains and provides proof of insurance coverage for a leak or release from the tank

or system which is acceptable to the Department.

Used Oil Regulations

Application fees for a used oil collector approval or renewal

(1) Subject to the minimum application fee set out in subsection (2), the application fees

for an initial used oil collector approval or for a renewal of the approval as required

under the Used Oil Regulations are as follows:

(

a) for facility with storage capacity of less than 50 000 L .......................... $132.65

(

b) for facility with storage capacity of greater than 50 000 L ................ $0.00265/L

(2) The minimum application fee for a used oil collector approval or renewal is $132.65.

Water and Wastewater Facilities and Public Drinking Water Supplies Regulations

Application fee for facility classification or reclassification

25 The application fee for a water and wastewater facility classification or re-classification as

required under the Water and Wastewater Facilities and Public Drinking Water Supplies

Regulations is $132.65.

Examination fee for operator in training operator certification exam

26 The examination fee for the writing of the exam for an operator in training operator

certification under the Water and Wastewater Facilities and Public Drinking Water

Supplies Regulations is $27.25.

Application fees for operator certification certificate or renewal

27 The application fees for an initial operator certification certificate or a renewal of the

operator certification certificate for four years as required under the Water and Wastewater

Facilities and Public Drinking Water Supplies Regulations for all types are as follows:

(

a) initial operator certification certificate ................................................... $100.00

(

b) renewal of operator certification certificate .............................................. $61.15

Well Construction Regulations

Application fees for well construction certificate of qualification or renewal

28 The application fees for an initial well driller, well digger and pump installer certificate of

qualification or for a renewal of the certificate of qualification per year as required under

the Well Construction Regulations are as follows:

(

a) for a well driller using 1 machine .......................................................... $350.00

plus add for each additional machine to be used .................................... $145.75

(

b) for a well digger using 1 machine ......................................................... $116.65

plus add for each additional machine to be used ...................................... $33.00

(

c) for a Class I well pump installer ............................................................ $116.65

(

d) for a Class II well pump installer ............................................................ $58.30

Legislative History

Reference Tables

Fees Regulations

N.S. Reg.

176/2015

Environment Act

Note: The

information in these tables does not form part of the regulations and is

compiled by the Office of the Registrar of Regulations for reference only.

Source Law

The current consolidation of the Fees Regulations made under the Environment Act includes all of the following regulations:

N.S.

Regulation

In force

date*

How in force

Royal Gazette

Part II Issue

176/2015

Apr 1, 2015

date specified

Apr 8, 2015

69/2016

Apr 12, 2016

date specified

Apr 29, 2016

85/2026

Mar 24, 2026

date specified

Apr 3, 2026

The following regulations are not yet in force and are

not included in the current consolidation:

N.S.

Regulation

In force

date*

How in force

Royal Gazette

Part II Issue

*See subsection 3(6) of the Regulations Act for

rules about in force dates of regulations.

Amendments by Provision

ad. = added

am. = amended

fc. = fee change

ra. = reassigned

rep. = repealed

rs . = repealed and substituted

Provision affected

How affected

11(1), Table 5, Category IV ............

ad. 69/2016

11(2)(d) ............................................

ad. 69/2016

13 .....................................................

rs . 85/2026

13A ..................................................

ad. 85/2026

16 .....................................................

rep. 85/2026

17 .....................................................

rs . 85/2026

Note that changes to headings are not

included in the above table.

Editorial Notes and Corrections:

Note

Effective

date

The reference in s. 9(3) to the Department of

Transportation and Infrastructure Renewal should be read as a reference to

the Department of Transportation and Active Transit in accordance with O.I.C.

2021-56 under the Public Service Act ,

R.S.N.S. 1989, c. 376.

Feb 23, 2021

The reference in s. 9(3) to the Department of

Transportation and Infrastructure Renewal should be read as a reference to

the Department of Public Works in accordance with O.I.C. 2021-209 under the Public Service Act , R.S.N.S. 1989, c.

Aug 31, 2021

Repealed and Superseded:

N.S.

Regulation

Title

In force

date

Repealed

date

Note: Only

regulations that are specifically repealed and replaced appear in this

table. It may not reflect the entire

history of regulations on this subject matter.

Document details

CollectionNova Scotia — Regulations
CitationN.S. Reg. 176/2015
Date2015-01-01
Typeregulation
Volume / chapterjust regulations regs envfees.htm
Languageen
Formathtm
SourcePROVINCIAL
Identifier4e753b90308f06bb25d9f81875872a2e6ae3c047

Source file is stored in the law ingest library (htm).