Alberta Gazette, Part I — Friday, December 15, 2023

Friday, December 15, 2023

Alberta — Gazette

Alberta Gazette, Part I — Friday, December 15, 2023

Friday, December 15, 2023

Alberta — Gazette

The Alberta Gazette

Part I

Vol. 119 Edmonton, Friday, December 15, 2023 No. 23

ORDERS IN COUNCIL

O.C. 210/2023

(Municipal Government Act)

Approved and ordered:

Salma Lakhani

Lieutenant Governor. November 29, 2023

The Lieutenant Governor in Council makes the Order Annexing Land from the

City of Calgary to Rocky View County set out in the attached Appendix.

Danielle Smith, Chair.

APPENDIX

ORDER ANNEXING LAND FROM THE CITY OF CALGARY TO ROCKY

VIEW COUNTY

1 In this Order, "annexed land" means the land described in the Schedule.

2 The annexed land is separated from the City of Calgary and annexed to Rocky

View County.

Schedule

DETAILED DESCRIPTION OF THE LANDS SEPARATED FROM THE

CITY OF CALGARY AND ANNEXED TO ROCKY VIEW COUNTY

ALL THOSE PORTIONS OF THE ROAD ALLOWANCE LYING WEST OF AND

ADJACENT TO SECTIONS FOUR

(4) AND NINE (9), TOWNSHIP TWENTY-

FOUR (24), RANGE TWO (2), WEST OF THE FIFTH MERIDIAN DESCRIBED

AS FOLLOWS:

COMMENCING AT THE POINT OF INTERSECTION OF THE SOUTHWEST

BOUNDARY OF PLAN 1911560 AND THE EAST BOUNDARY OF ROAD PLAN

8310629 IN THE NORTHWEST QUARTER OF

SECTION FOUR (4), TOWNSHIP

TWENTY-FOUR (24), RANGE TWO (2), WEST OF THE FIFTH MERIDIAN,

THENCE SOUTHERLY ALONG THE EAST BOUNDARY OF THE SAID ROAD

PLAN A DISTANCE OF EIGHT POINT SEVENTY-EIGHT

(8.78) METRES,

THENCE A SOUTHWESTERLY PROJECTION ACROSS THE NORTH-SOUTH

GOVERNMENT ROAD ALLOWANCE TO THE POINT OF INTERSECTION

WITH THE SOUTHEAST CORNER OF ROAD PLAN 1312679 AND THE WEST

BOUNDARY OF THE NORTH-SOUTH GOVERNMENT ROAD ALLOWANCE,

THENCE NORTHERLY ALONG THE WEST BOUNDARY OF THE SAID

GOVERNMENT ROAD ALLOWANCE TO THE POINT OF INTERSECTION

WITH THE NORTH BOUNDARY OF PLAN 446 AND THE SOUTHEAST

CORNER OF PLAN 7710012 IN THE SOUTHWEST QUARTER OF

SECTION

NINE (9), TOWNSHIP TWENTY-FOUR (24), RANGE TWO (2), WEST OF THE

FIFTH MERIDIAN,

THENCE A SOUTHEASTERLY PROJECTION ACROSS THE NORTH SOUTH

GOVERNMENT ROAD ALLOWANCE TO THE POINT OF INTERSECTION

WITH THE NORTH BOUNDARY OF ROAD PLAN 446 AND THE SOUTHWEST

CORNER OF PLAN 7610769,

THENCE A SOUTHERLY PROJECTION ACROSS ROAD PLAN 446 TO THE

POINT OF INTERSECTION WITH THE NORTHWEST CORNER OF PLAN

9710522,

THENCE SOUTHERLY ALONG THE WEST BOUNDARY OF THE SAID PLAN

TO THE POINT OF INTERSECTION WITH THE NORTHWEST CORNER OF

PLAN 8811394,

THENCE EASTERLY ALONG THE NORTH BOUNDARY OF THE SAID PLAN

TO THE POINT OF INTERSECTION WITH THE NORTHWEST CORNER OF

PLAN 243LG,

THENCE SOUTHERLY ALONG THE WEST BOUNDARY OF THE SAID PLAN

TO THE INTERSECTION WITH THE NORTHEAST CORNER OF ROAD PLAN

8310629,

THENCE SOUTHERLY ALONG THE EAST BOUNDARY OF THE SAID ROAD

PLAN TO THE POINT OF COMMENCEMENT IN THE NORTHWEST

QUARTER OF

SECTION FOUR (4), TOWNSHIP TWENTY-FOUR (24), RANGE

TWO (2), WEST OF THE FIFTH MERIDIAN.

O.C. 211/2023

(Municipal Government Act)

Approved and ordered:

Salma Lakhani

Lieutenant Governor. November 29, 2023

The Lieutenant Governor in Council makes the Order Annexing Land from the

County of Wetaskiwin No. 10 to the Summer Village of Poplar Bay set out in the

attached Appendix.

Danielle Smith, Chair.

APPENDIX

ORDER ANNEXING LAND FROM THE COUNTY OF WETASKIWIN NO.

10 TO THE SUMMER VILLAGE OF POPLAR BAY

1 In this Order, "annexed land" means the land described in

Schedule 1 and shown

on the sketch in

Schedule 2.

2 Effective January 1, 2024, the land described in

Schedule 1 and shown on the

sketch in

Schedule 2 is separated from the County of Wetaskiwin No. 10 and annexed

to the Summer Village of Poplar Bay.

3 Any taxes owing to the County of Wetaskiwin No. 10 at the end of December 31,

2023 in respect of the annexed land and any assessable improvements to it are

transferred to and become payable to the Summer Village of Poplar Bay together with

any lawful penalties and costs levied in respect of those taxes, and the Summer

Village of Poplar Bay on collecting those taxes, penalties and costs must pay them to

the County of Wetaskiwin No. 10.

4 For the purpose of taxation in 2025 and subsequent years, the assessor for the

Summer Village of Poplar Bay must assess the annexed land and the assessable

improvements to it.

Schedule 1

DETAILED DESCRIPTION OF THE LANDS SEPARATED FROM

THE COUNTY OF WETASKIWIN NO. 10 AND ANNEXED TO

THE SUMMER VILLAGE OF POPLAR BAY

ALL THAT PORTION OF THE NORTH HALF OF

SECTION TWENTY-EIGHT

(28), TOWNSHIP FORTY-SIX (46), RANGE ONE (1), WEST OF THE FIFTH

(5) MERIDIAN WHICH LIES SOUTHWEST OF THE SOUTHWESTERLY LIMIT OF

ROAD PLAN 6542KS EXCEPTING THEREOUT:

(

A) PLAN 5128TR SUBDIVISION

(

B) PLAN 7921318 SUBDIVISION

(

C) PLAN 9721788 SUBDIVISION

(

D) PLAN 9721790 DESCRIPTIVE

Schedule 2

SKETCH SHOWING THE GENERAL LOCATION OF THE LANDS

SEPARATED FROM THE COUNTY OF WETASKIWIN NO. 10 AND

ANNEXED TO THE SUMMER VILLAGE OF POPLAR BAY

O.C. 212/2023

(Municipal Government Act)

Approved and ordered:

Salma Lakhani

Lieutenant Governor. November 29, 2023

The Lieutenant Governor in Council makes the Order Annexing Land from Red

Deer County to the City of Red Deer set out in the attached Appendix.

Danielle Smith, Chair.

APPENDIX

ORDER ANNEXING LAND FROM RED DEER COUNTY

TO THE CITY OF RED DEER

1 In this Order, "annexed land" means the land described in

Schedule 1 and shown

on the sketch in

Schedule 2.

2 Effective January 1, 2024, the land described in

Schedule 1 and shown on the

sketch in

Schedule 2 is separated from Red Deer County and annexed to the City of

Red Deer.

3 Any taxes owing to Red Deer County at the end of December 31, 2023 in respect

of the annexed land and any assessable improvements to it are transferred to and

become payable to the City of Red Deer together with any lawful penalties and costs

levied in respect of those taxes, and the City of Red Deer, on collecting those taxes,

penalties and costs, must pay them to Red Deer County.

4 For the purpose of taxation in 2025 and subsequent years, the assessor for the City

of Red Deer must assess the annexed land and the assessable improvements to it.

5 The City of Red Deer shall pay to Red Deer County

(a) $3,900.41 on or before July 31, 2024,

(b) $3,120.33 on or before July 31, 2025,

(c) $2,340.25 on or before July 31, 2026,

(d) $1,560.17 on or before July 31, 2027, and

(e) $780.08 on or before July 31, 2028.

Schedule 1

DETAILED DESCRIPTION OF THE LANDS SEPARATED FROM

RED DEER COUNTY AND ANNEXED TO THE CITY OF RED DEER

ALL THAT PORTION OF THE SOUTH HALF OF

SECTION EIGHT (8),

TOWNSHIP THIRTY-NINE (39), RANGE TWENTY-SEVEN

(27) WEST OF THE

FOURTH

(4) MERIDIAN NOT WITHIN THE CITY OF RED DEER INCLUDING

THE NORTH-SOUTH ROAD ALLOWANCE ADJACENT TO THE EAST SIDE

OF SAID SECTION.

ALL THAT PORTION OF

SECTION FIVE (5), TOWNSHIP THIRTY-NINE (39),

RANGE TWENTY-SEVEN

(27) WEST OF THE FOURTH

(4) MERIDIAN NOT

WITHIN THE CITY OF RED DEER AND INCLUDING THAT LAND

ADJACENT TO THE SOUTH BOUNDARY OF SAID

SECTION LYING NORTH

OF THE SOUTH BOUNDARY OF PLAN 3274 JY.

ALL THAT PORTION OF

SECTION THIRTY-SIX (36), TOWNSHIP

THIRTY-EIGHT (38), RANGE TWENTY-EIGHT

(28) WEST OF THE FOURTH

(4) MERIDIAN NOT WITHIN THE CITY OF RED DEER LYING SOUTH OF

THE SOUTH BOUNDARY OF PLAN 3274 JY.

ALL THAT PORTION OF

SECTION THIRTY-ONE (31), TOWNSHIP

THIRTY-EIGHT (38), RANGE TWENTY-SEVEN

(27) WEST OF THE FOURTH

(4) MERIDIAN NOT WITHIN THE CITY OF RED DEER

COMMENCING AT THE INTERSECTION OF THE EASTERN BOUNDARY OF

PLAN 082 9964 AND THE SOUTHERN BOUNDARY OF PLAN 3274 JY;

THENCE NORTH ALONG THE PRODUCTION OF A LINE FROM SAID

INTERSECTION TO THE SOUTH BOUNDARY OF LOT 2, BLOCK 4,

PLAN 6222 KS; THENCE EASTERLY ALONG THE SOUTH BOUNDARIES OF

LOT 2, BLOCK 4, PLAN 6222 KS, LOT 4, BLOCK 4, PLAN 192 1033, AND

PLAN 992 0009 TO THE SOUTHEASTERN BOUNDARY OF PLAN 992 0009 TO

THE INTERSECTION OF THE SOUTHEASTERN BOUNDARY OF

PLAN 992 0009 AND LOT 1B, BLOCK 4, PLAN 912 3387; THENCE, ALONG

THE SOUTHEASTERLY BOUNDARY OF LOT 1B, BLOCK 4, PLAN 912 3387

TO ITS INTERSECTION WITH THE SOUTHERN BOUNDARY OF LOT 24,

BLOCK 3, PLAN 867 MC; THENCE EASTERLY ALONG THE SOUTHERN

BOUNDARY OF LOT 24, BLOCK 3, PLAN 867 MC TO THE WESTERN

BOUNDARY OF THE NORTH-SOUTH ROAD ALLOWANCE ADJACENT TO

THE WEST BOUNDARY OF

SECTION FIVE (5), TOWNSHIP THIRTY-NINE

(39), RANGE TWENTY-SEVEN

(27) WEST OF THE FOURTH

(4) MERIDIAN;

THENCE SOUTH ALONG THE WESTERN BOUNDARY OF THE

NORTH-SOUTH ROAD ALLOWANCE ADJACENT TO THE WEST OF THE

SOUTHWEST QUARTER OF

SECTION FIVE (5), TOWNSHIP THIRTY-NINE

(39), RANGE TWENTY-SEVEN

(27) WEST OF THE FOURTH

(4) MERIDIAN

AND ITS PROJECTION SOUTH TO THE SOUTH BOUNDARY OF

PLAN 3274 JY; THENCE WESTERLY ALONG THE SOUTH BOUNDARY OF

PLAN 3274 JY TO ITS INTERSECTION WITH PLAN 082 9964, BEING THE

POINT OF COMMENCEMENT.

Schedule 2

SKETCH SHOWING THE GENERAL LOCATION OF THE AREAS

SEPARATED FROM RED DEER COUNTY AND ANNEXED TO

THE CITY OF RED DEER

O.C. 213/2023

(Municipal Government Act)

Approved and ordered:

Salma Lakhani

Lieutenant Governor. November 29, 2023

The Lieutenant Governor in Council makes the Order Annexing Land from

The Municipal District of Willow Creek No. 26 to the Town of Claresholm set out in

the attached Appendix.

Danielle Smith, Chair.

APPENDIX

ORDER ANNEXING LAND FROM THE MUNICIPAL DISTRICT OF

WILLOW CREEK NO. 26 TO THE TOWN OF CLARESHOLM

1 In this Order,

(a) "annexed land" means the land described in

Schedule 1 and shown on the

sketch in

Schedule 2;

(b) "Town of Claresholm Land Use Bylaw" means the Town of Claresholm

Land Use Bylaw No. 1525 in effect as of September 5, 2023.

2 Effective January 1, 2024, the land described in

Schedule 1 and shown on the

sketch in

Schedule 2 is separated from The Municipal District of Willow Creek No.

26 and annexed to the Town of Claresholm.

3 Any taxes owing to The Municipal District of Willow Creek No. 26 at the end of

December 31, 2023 in respect of the annexed land and any assessable improvements

to it are transferred to and become payable to the Town of Claresholm together with

any lawful penalties and costs levied in respect of those taxes, and the Town of

Claresholm, on collecting those taxes, penalties and costs, must pay them to The

Municipal District of Willow Creek No. 26.

4 For the purpose of taxation in 2024 and in each subsequent year, up to and

including 2038, the annexed land and the assessable improvements to it

(

a) must be assessed by the Town of Claresholm on the same basis as if they

had remained in The Municipal District of Willow Creek No. 26, and

(

b) must be taxed by the Town of Claresholm in respect of each assessment

class that applies to the annexed land and the assessable improvements to it

using the tax rate established by The Municipal District of Willow Creek

No. 26.

5(1) Where in 2024 or any subsequent taxation year, up to and including 2038, a

portion of the annexed land

(

a) becomes a new parcel of land created at the request or on behalf of the

landowner

(

i) as a result of subdivision,

(ii) as a result of separation of title by registered plan of subdivision, or

(iii) by instrument or any other method,

(

b) is redesignated, at the request of or on behalf of the landowner, under the

Town of Claresholm Land Use Bylaw to another designation, or

(

c) is connected, at the request of or on the behalf of the landowner, to water or

sanitary sewer services provided by the Town of Claresholm,

section 4 ceases to apply at the end of that taxation year in respect of that portion of

the annexed land and the assessable improvements to it.

(2) Where, in any taxation year, the total area of the annexed land to which

section 4

applies falls below 3.45 hectares (8.75 acres),

section 4 ceases to apply at the end of

that taxation year in respect of that portion of the annexed land and the assessable

improvements to it.

6 After

section 4 ceases to apply to a portion of the annexed land in a taxation year,

that portion of the annexed land and the assessable improvements to it must be

assessed and taxed for the purposes of property taxes in the same manner that other

property of the same assessment class in the Town of Claresholm is assessed and

taxed.

7 The Town of Claresholm shall pay The Municipal District of Willow Creek No. 26

the sum of $6,726.62 on or before July 1, 2024.

Schedule 1

DETAILED DESCRIPTION OF THE LANDS SEPARATED FROM

THE MUNICIPAL DISTRICT OF WILLOW CREEK NO. 26 AND ANNEXED

TO THE TOWN OF CLARESHOLM

ALL THAT PORTION OF THE EAST HALF OF

SECTION TWENTY-SEVEN

(27), TOWNSHIP TWELVE (12), RANGE TWENTY-SEVEN (27), WEST OF THE

FOURTH

(4) MERIDIAN NOT WITHIN THE TOWN OF CLARESHOLM.

ALL THAT PORTION OF THE NORTHEAST QUARTER OF

SECTION

TWENTY-TWO (22), TOWNSHIP TWELVE (12), RANGE TWENTY-SEVEN

(27), WEST OF THE FOURTH

(4) MERIDIAN NOT WITHIN THE TOWN OF

CLARESHOLM EXCLUDING ALL THAT LAND LYING SOUTH OF THE

NORTH BOUNDARY OF RW 423 FB.

Schedule 2

SKETCH SHOWING THE GENERAL LOCATION OF THE AREAS

SEPARATED FROM THE MUNICIPAL DISTRICT OF WILLOW CREEK

NO. 26 AND ANNEXED TO THE TOWN OF CLARESHOLM

GOVERNMENT NOTICES

Energy and Minerals

Production Allocation Unit Agreement

(Mines and Minerals Act)

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Countess Basal Quartz Agreement No. 8" and that the Unit became effective on

August 1, 2022.

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Countess Basal Quartz Agreement No. 9" and that the Unit became effective on

August 1, 2022.

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Countess Glauconitic Agreement No. 17" and that the Unit became effective on

July 1, 2022.

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Elmworth Montney Agreement No. 17" and that the Unit became effective on

January 1, 2022.

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Elmworth Montney Agreement No. 18" and that the Unit became effective on

January 1, 2022.

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Ferguson Bakken Agreement No. 8" and that the Unit became effective on September

1, 2022.

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Ferguson Bakken Agreement No. 9" and that the Unit became effective on October 1,

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Killam Lloydminster Agreement No. 2" and that the Unit became effective on

December 1, 2022.

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Lacombe Duvernay Agreement No. 1" and that the Unit became effective on July 1,

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Lacombe Duvernay Agreement No. 2" and that the Unit became effective on July 1,

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Lacombe Duvernay Agreement No. 3" and that the Unit became effective on July 1,

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Lloydminster Sparky Agreement No. 7" and that the Unit became effective on

September 1, 2022.

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement - Lone

Pine Creek Wabamun Agreement No. 2" and that the Unit became effective on

December 1, 2022.

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Norris Glauconitic Agreement" and that the Unit became effective on July 1, 2022.

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Provost Cummings Agreement No. 15" and that the Unit became effective on October

1, 2022.

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Provost Rex Agreement No. 5" and that the Unit became effective on July 1, 2022.

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Provost Rex Agreement No. 6" and that the Unit became effective on July 1, 2022.

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Provost Sparky Agreement No. 20" and that the Unit became effective on February 1,

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Provost Sparky Agreement No. 21" and that the Unit became effective on February 1,

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Provost Viking Agreement No. 39" and that the Unit became effective on July 1,

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Provost Viking Agreement No. 40" and that the Unit became effective on December

1, 2021.

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Provost Viking Agreement No. 41" and that the Unit became effective on February 1,

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Provost Viking Agreement No. 42" and that the Unit became effective on February 1,

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Provost Viking Agreement No. 43" and that the Unit became effective on February 1,

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Provost Viking Agreement No. 44" and that the Unit became effective on March 1,

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Provost Viking Agreement No. 47" and that the Unit became effective on October 1,

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Twining Duvernay Agreement No. 23" and that the Unit became effective on August

1, 2022.

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Twining Duvernay Agreement No. 24" and that the Unit became effective on August

1, 2022.

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Verger Ellerslie Agreement" and that the Unit became effective on August 1, 2022.

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Verger Ellerslie Agreement No. 2" and that the Unit became effective on August 1,

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Viking-Kinsella Sparky Agreement No. 7" and that the Unit became effective on

August 1, 2022.

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Wayne-Rosedale Lower Mannville Agreement" and that the Unit became effective on

January 1, 2022.

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Wembley Montney Agreement No. 62" and that the Unit became effective on

October 1, 2021.

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Wembley Montney Agreement No. 63" and that the Unit became effective on

October 1, 2021.

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Wembley Montney Agreement No. 67" and that the Unit became effective on

September 1, 2021.

Notice is hereby given, pursuant to

section 102 of the Mines and Minerals Act, that

the Minister of Energy and Minerals on behalf of the Crown has executed

counterparts of the agreement entitled "Production Allocation Unit Agreement -

Wembley Montney Agreement No. 71" and that the Unit became effective on

September 1, 2021.

Infrastructure

Sale or Disposition of Land

(Government Organization Act)

Name of Purchaser: The Board of Governors of Northwestern Polytechnic

Consideration: $1.00

Land Description:

Parcel 1:

Meridian 6 Range 6 Township 71

Section 27 Quarter North East

Containing 65.2 hectares (161 acres) more or less

Excepting thereout:

A) Plan 8292ET - Road - 9.16 hectares (22.64 acres) more or less - Reservoir Site

B) Plan 2187JY - Road - 0.943 hectares (2.33 acres) more or less

C) Plan 2021277 - Subdivision - 19.771 hectares (48.86 acres) more or less

D) Plan 2021280 - Subdivision - 2.460 hectares (6.08 acres) more or less

Excepting thereout all mines and minerals

-and-

Parcel 2:

Plan 2021277; Block 1; Lot 2

Excepting thereout all mines and minerals

Area: 0.823 hectares (2.03 acres) more or less

-and-

Parcel 3:

Plan 2021277; Block 2; Lot 1

Excepting thereout all mines and minerals

Area: 2.787 hectares (6.89 acres) more or less

Public Safety and Emergency Services

Cancellation of Qualified Technician Appointment

(Intox EC/IR II)

Royal Canadian Mounted Police, Traffic Services "K" Division

Autet, Cody Brian

(Date of Cancellation November 24, 2023)

Designation of Qualified Technician Appointment

(Intox EC/IR II)

DND Military Police

Yeung, Andy Lam Chun

(Date of Designation November 3, 2023)

Edmonton Police Service

Charif, Oliver

Feely, Benjamin Alexander

Hudson, Lisa Marie

Jefferis, Alanna Jayne

Kharoud, Simarpreet Singh

Miller, Noah Everett

Simon, Mia Jane

Widner, Jean Sebastien

(Date of Designation November 10, 2023)

Autet, Cody Brian

(Date of Designation November 24, 2023)

Royal Canadian Mounted Police, Traffic Services "K" Division

Barnett, Matthew Roger

Chaput, Bradley Michael

Herbert, Aoife Carys

Larcher, Andre

McFarlane, Brett Robert

Poirier, Gabriel

Poirier, Victor-Emmanuel Sylvain Joseph

Prokusheva, Anna

Ralh, Ashish Kumar

Vroom, Marielle Brigitte

Weir, Benjamin Francis Hugh

(Date of Designation November 3, 2023)

Safety Codes Council

Agency Accreditation

(Safety Codes Act)

Pursuant to

Section 30 of the Safety Codes Act it is hereby ordered that

City of Edmonton, Office of the City Manager Dept. Fire Rescue Services/Fire

Prevention and Education, Accreditation No. A000235, Order No. 725

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Fire

Consisting of all parts of the National Fire Code - 2019 Alberta Edition, and Fire

Investigation (cause and circumstance) as amended from time to time.

Accredited Date: February 26, 1996 Issued Date: November 23, 2023.

Pursuant to

Section 30 of the Safety Codes Act it is hereby ordered that

Dynamysk Automation, Accreditation No. A000841, Order No. 2865

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Building

Consisting of all parts of the National Building Code - 2019 Alberta Edition, and the

National Energy Code of Canada for Buildings 2017 as amended from time to time.

Accredited Date: November 16, 2012 Issued Date: November 22, 2023.

_______________

Pursuant to

Section 30 of the Safety Codes Act it is hereby ordered that

Dynamysk Automation, Accreditation No. A000841, Order No. 2711

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Electrical

Consisting of all parts of the CSA C22.1-21 Canadian Electrical Code (25th Edition)

and Alberta Electrical Utility Code (6th Edition, 2022) as amended from time to time.

Accredited Date: August 28, 2009 Issued Date: November 22, 2023.

_______________

Pursuant to

Section 30 of the Safety Codes Act it is hereby ordered that

Dynamysk Automation, Accreditation No. A000841, Order No. 2866

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Gas

Consisting of all parts of the CSA-B149.1:20 Natural gas and propane installation

code, CSA-B149.2:20 Propane storage and handling code, CSA-B108.1:21

Compressed natural gas refuelling stations installation code, and CSA-B108.2:21

Liquefied natural gas refuelling stations installation code.

Excluding the CSA-B109:17 Natural gas for vehicles installation code, CSA-

B149.3:20 Code for the field approval of fuel related components on appliances and

equipment, and CSA B149.5:20 Installation code for propane fuel systems and

containers on motor vehicles.

Accredited Date: November 16, 2012 Issued Date: November 22, 2023.

Pursuant to

Section 30 of the Safety Codes Act it is hereby ordered that

Dynamysk Automation, Accreditation No. A000841, Order No. 2867

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Plumbing

Consisting of all parts of the National Plumbing Code of Canada 2020, and Alberta

Private Sewage Systems Standard of Practice 2021 as amended from time to time.

Accredited Date: November 16, 2012 Issued Date: November 22, 2023.

Corporate Accreditation

(Safety Codes Act)

Pursuant to

Section 28 of the Safety Codes Act it is hereby ordered that

Nutrien, Accreditation No. C000142, Order No. 443

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations on industrial and related facility properties owned by or under their

care and control for the discipline of Electrical

Consisting of all parts of the CSA C22.1-21 Canadian Electrical Code (25th Edition)

and Alberta Electrical Utility Code (6th Edition, 2022) as amended from time to time.

Accredited Date: December 10, 1995 Issued Date: November 21, 2023.

Joint Municipal Accreditation

(Safety Codes Act)

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

City of Camrose, Camrose County, Village of Bawlf, Village of Bittern Lake,

Village of Edberg, Village of Hay Lakes, Village of Rosalind, Accreditation No.

J000111, Order No. 0484

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Building

Consisting of all parts of the National Building Code - 2019 Alberta Edition, and the

National Energy Code of Canada for Buildings 2017 as amended from time to time.

Accredited Date: December 14, 1995 Issued Date: November 23, 2023.

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

City of Camrose, Camrose County, Village of Bawlf, Village of Bittern Lake,

Village of Edberg, Village of Hay Lakes, Village of Rosalind, Accreditation No.

J000111, Order No. 0483

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Electrical

Consisting of all parts of the CSA C22.1-21 Canadian Electrical Code (25th Edition)

as amended from time to time.

Accredited Date: December 14, 1995 Issued Date: November 23, 2023.

______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

City of Camrose, Camrose County, Village of Bawlf, Village of Bittern Lake,

Village of Edberg, Village of Hay Lakes, Village of Rosalind, Accreditation No.

J000111, Order No. 0481

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Gas

Consisting of all parts of the CSA-B149.1:20 Natural gas and propane installation

code, CSA-B149.2:20 Propane storage and handling code, CSA-B108.1:21

Compressed natural gas refuelling stations installation code, and CSA-B108.2:21

Liquefied natural gas refuelling stations installation code.

Excluding the CSA-B109:17 Natural gas for vehicles installation code, CSA-

B149.3:20 Code for the field approval of fuel related components on appliances and

equipment, and CSA B149.5:20 Installation code for propane fuel systems and

containers on motor vehicles.

Accredited Date: December 14, 1995 Issued Date: November 23, 2023.

_______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

City of Camrose, Camrose County, Village of Bawlf, Village of Bittern Lake,

Village of Edberg, Village of Hay Lakes, Village of Rosalind, Accreditation No.

J000111, Order No. 0480

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Plumbing

Consisting of all parts of the National Plumbing Code of Canada 2020, and Alberta

Private Sewage Systems Standard of Practice 2021 as amended from time to time.

Accredited Date: December 14, 1995 Issued Date: November 23, 2023.

Municipal Accreditation

(Safety Codes Act)

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

City of Red Deer, Accreditation No. M000101, Order No. 104

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Building

Consisting of all parts of the National Building Code - 2019 Alberta Edition, and the

National Energy Code of Canada for Buildings 2017 as amended from time to time.

Accredited Date: December 7, 1994 Issued Date: November 24, 2023.

_______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

City of Red Deer, Accreditation No. M000101, Order No. 179

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Electrical

Consisting of all parts of the CSA C22.1-21 Canadian Electrical Code (25th Edition)

as amended from time to time.

Accredited Date: June 26, 1995 Issued Date: November 24, 2023.

______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

City of Red Deer, Accreditation No. M000101, Order No. 103

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Fire

Consisting of all parts of the National Fire Code - 2019 Alberta Edition, and Fire

Investigation (cause and circumstance) as amended from time to time.

Accredited Date: December 7, 1994 Issued Date: November 24, 2023.

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

City of Red Deer, Accreditation No. M000101, Order No. 101

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Gas

Consisting of all parts of the CSA-B149.1:20 Natural gas and propane installation

code, CSA-B149.2:20 Propane storage and handling code, CSA-B108.1:21

Compressed natural gas refuelling stations installation code, and CSA-B108.2:21

Liquefied natural gas refuelling stations installation code.

Excluding the CSA-B109:17 Natural gas for vehicles installation code, CSA-

B149.3:20 Code for the field approval of fuel related components on appliances and

equipment, and CSA B149.5:20 Installation code for propane fuel systems and

containers on motor vehicles.

Accredited Date: December 7, 1994 Issued Date: November 24, 2023.

_______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

City of Red Deer, Accreditation No. M000101, Order No. 102

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Plumbing

Consisting of all parts of the National Plumbing Code of Canada 2020, and Alberta

Private Sewage Systems Standard of Practice 2021 as amended from time to time.

Accredited Date: December 7, 1994 Issued Date: November 24, 2023.

_______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Village of Paradise Valley, Accreditation No. M000103, Order No. 1252

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Building

Consisting of all parts of the National Building Code - 2019 Alberta Edition, and the

National Energy Code of Canada for Buildings 2017 as amended from time to time.

Accredited Date: August 22, 2000 Issued Date: November 22, 2023.

_______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Village of Paradise Valley, Accreditation No. M000103, Order No. 1253

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Electrical

Consisting of all parts of the CSA C22.1-21 Canadian Electrical Code (25th Edition)

as amended from time to time.

Accredited Date: August 22, 2000 Issued Date: November 22, 2023.

______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Village of Paradise Valley, Accreditation No. M000103, Order No. 1254

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Gas

Consisting of all parts of the CSA-B149.1:20 Natural gas and propane installation

code, CSA-B149.2:20 Propane storage and handling code, CSA-B108.1:21

Compressed natural gas refuelling stations installation code, and CSA-B108.2:21

Liquefied natural gas refuelling stations installation code.

Excluding the CSA-B109:17 Natural gas for vehicles installation code, CSA-

B149.3:20 Code for the field approval of fuel related components on appliances and

equipment, and CSA B149.5:20 Installation code for propane fuel systems and

containers on motor vehicles.

Accredited Date: August 22, 2000 Issued Date: November 22, 2023.

_______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Village of Paradise Valley, Accreditation No. M000103, Order No. 1255

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Plumbing

Consisting of all parts of the National Plumbing Code of Canada 2020, and Alberta

Private Sewage Systems Standard of Practice 2021 as amended from time to time.

Accredited Date: August 22, 2000 Issued Date: November 22, 2023.

_______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Town of Canmore, Accreditation No. M000152, Order No. 333

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Fire

Consisting of all parts of the National Fire Code - 2019 Alberta Edition as amended

from time to time, except for those requirements pertaining to the installation,

alteration, and removal of the storage tank systems for flammable and combustible

liquids; and Fire Investigation (cause and circumstance).

Accredited Date: November 3, 1995 Issued Date: November 21, 2023.

_______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Town of Cochrane, Accreditation No. M000184, Order No. 511

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Building

Consisting of all parts of the National Building Code - 2019 Alberta Edition, and the

National Energy Code of Canada for Buildings 2017 as amended from time to time.

Accredited Date: December 17, 1995 Issued Date: January 1, 2024.

_______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Town of Cochrane, Accreditation No. M000184, Order No. 749

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Electrical

Consisting of all parts of the CSA C22.1-21 Canadian Electrical Code (25th Edition)

and Alberta Electrical Utility Code (6th Edition, 2022) as amended from time to time.

Accredited Date: March 7, 1996 Issued Date: January 1, 2024.

______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Town of Cochrane, Accreditation No. M000184, Order No. 510

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Fire

Consisting of all parts of the National Fire Code - 2019 Alberta Edition as amended

from time to time, except for those requirements pertaining to the installation,

alteration, and removal of the storage tank systems for flammable and combustible

liquids; and Fire Investigation (cause and circumstance).

Accredited Date: December 17, 1995 Issued Date: January 1, 2024.

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Town of Cochrane, Accreditation No. M000184, Order No. 714

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Gas

Consisting of all parts of the CSA-B149.1:20 Natural gas and propane installation

code, CSA-B149.2:20 Propane storage and handling code, CSA-B108.1:21

Compressed natural gas refuelling stations installation code, and CSA-B108.2:21

Liquefied natural gas refuelling stations installation code.

Excluding the CSA-B109:17 Natural gas for vehicles installation code, CSA-

B149.3:20 Code for the field approval of fuel related components on appliances and

equipment, and CSA B149.5:20 Installation code for propane fuel systems and

containers on motor vehicles.

Accredited Date: February 8, 1996 Issued Date: January 1, 2024.

_______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Town of Cochrane, Accreditation No. M000184, Order No. 713

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Plumbing

Consisting of all parts of the National Plumbing Code of Canada 2020, and Alberta

Private Sewage Systems Standard of Practice 2021 as amended from time to time.

Accredited Date: February 8, 1996 Issued Date: January 1, 2024.

_______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Town of Bassano, Accreditation No. M000192, Order No. 0591

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Building

Consisting of all parts of the National Building Code - 2019 Alberta Edition, and the

National Energy Code of Canada for Buildings 2017 as amended from time to time.

Accredited Date: December 21, 1995 Issued Date: November 30, 2023.

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Town of Bassano, Accreditation No. M000192, Order No. 2686

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Electrical

Consisting of all parts of the CSA C22.1-21 Canadian Electrical Code (25th Edition)

as amended from time to time.

Accredited Date: June 1, 2009 Issued Date: November 30, 2023.

______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Town of Bassano, Accreditation No. M000192, Order No. 2687

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Gas

Consisting of all parts of the CSA-B149.1:20 Natural gas and propane installation

code, CSA-B149.2:20 Propane storage and handling code, CSA-B108.1:21

Compressed natural gas refuelling stations installation code, and CSA-B108.2:21

Liquefied natural gas refuelling stations installation code.

Excluding the CSA-B109:17 Natural gas for vehicles installation code, CSA-

B149.3:20 Code for the field approval of fuel related components on appliances and

equipment, and CSA B149.5:20 Installation code for propane fuel systems and

containers on motor vehicles.

Accredited Date: June 1, 2009 Issued Date: November 30, 2023.

_______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Town of Bassano, Accreditation No. M000192, Order No. 2688

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Plumbing

Consisting of all parts of the National Plumbing Code of Canada 2020, and Alberta

Private Sewage Systems Standard of Practice 2021 as amended from time to time.

Accredited Date: June 1, 2009 Issued Date: November 30, 2023.

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Village of Andrew, Accreditation No. M000332, Order No. 637

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Building

Consisting of all parts of the National Building Code - 2019 Alberta Edition, and the

National Energy Code of Canada for Buildings 2017 as amended from time to time.

Accredited Date: December 22, 1995 Issued Date: December 1, 2023.

_______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Village of Andrew, Accreditation No. M000332, Order No. 923

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Electrical

Consisting of all parts of the CSA C22.1-21 Canadian Electrical Code (25th Edition)

as amended from time to time.

Accredited Date: November 18, 1996 Issued Date: December 1, 2023.

______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Village of Andrew, Accreditation No. M000332, Order No. 924

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Gas

Consisting of all parts of the CSA-B149.1:20 Natural gas and propane installation

code, CSA-B149.2:20 Propane storage and handling code, CSA-B108.1:21

Compressed natural gas refuelling stations installation code, and CSA-B108.2:21

Liquefied natural gas refuelling stations installation code.

Excluding the CSA-B109:17 Natural gas for vehicles installation code, CSA-

B149.3:20 Code for the field approval of fuel related components on appliances and

equipment, and CSA B149.5:20 Installation code for propane fuel systems and

containers on motor vehicles.

Accredited Date: November 18, 1996 Issued Date: December 1, 2023.

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Village of Andrew, Accreditation No. M000332, Order No. 925

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Plumbing

Consisting of all parts of the National Plumbing Code of Canada 2020, and Alberta

Private Sewage Systems Standard of Practice 2021 as amended from time to time.

Accredited Date: November 18, 1996 Issued Date: December 1, 2023.

_______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Westlock County, Accreditation No. M000370, Order No. 1351

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Building

Consisting of all parts of the National Building Code - 2019 Alberta Edition, and the

National Energy Code of Canada for Buildings 2017 as amended from time to time.

Accredited Date: September 14, 2001 Issued Date: November 21, 2023.

_______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Westlock County, Accreditation No. M000370, Order No. 1350

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Electrical

Consisting of all parts of the CSA C22.1-21 Canadian Electrical Code (25th Edition)

as amended from time to time.

Accredited Date: September 14, 2001 Issued Date: November 21, 2023.

______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Westlock County, Accreditation No. M000370, Order No. 1349

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Gas

Consisting of all parts of the CSA-B149.1:20 Natural gas and propane installation

code, CSA-B149.2:20 Propane storage and handling code, CSA-B108.1:21

Compressed natural gas refuelling stations installation code, and CSA-B108.2:21

Liquefied natural gas refuelling stations installation code.

Excluding the CSA-B109:17 Natural gas for vehicles installation code, CSA-

B149.3:20 Code for the field approval of fuel related components on appliances and

equipment, and CSA B149.5:20 Installation code for propane fuel systems and

containers on motor vehicles.

Accredited Date: September 14, 2001 Issued Date: November 21, 2023.

_______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Westlock County, Accreditation No. M000370, Order No. 1348

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Plumbing

Consisting of all parts of the National Plumbing Code of Canada 2020, and Alberta

Private Sewage Systems Standard of Practice 2021 as amended from time to time.

Accredited Date: September 14, 2001 Issued Date: November 21, 2023.

______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Town of Banff, Accreditation No. M000396, Order No. 543

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Fire

Consisting of all parts of the National Fire Code - 2019 Alberta Edition as amended

from time to time, except for those requirements pertaining to the installation,

alteration, and removal of the storage tank systems for flammable and combustible

liquids; and Fire Investigation (cause and circumstance).

Accredited Date: December 19, 1995 Issued Date: November 23, 2023.

_______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Town of Fairview, Accreditation No. M000452, Order No. 3007

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Building

Consisting of all parts of the National Building Code - 2019 Alberta Edition, and the

National Energy Code of Canada for Buildings 2017 as amended from time to time.

Accredited Date: September 26, 2016 Issued Date: November 21, 2023.

______________

Pursuant to

Section 26 of the Safety Codes Act it is hereby ordered that

Municipality of Jasper, Accreditation No. M000461, Order No. 1452

provide services under the Safety Codes Act including applicable Alberta amendments

and regulations for the discipline of Fire

Consisting of all parts of the National Fire Code - 2019 Alberta Edition as amended

from time to time, except for those requirements pertaining to the installation,

alteration, and removal of the storage tank systems for flammable and combustible

liquids; and Fire Investigation (cause and circumstance).

Accredited Date: July 21, 2003 Issued Date: November 30, 2023.

Seniors, Community and Social Services

Office of the Public Guardian and Trustee

Property being held by the Public Trustee for a period of Ten

(10) Years

(Public Trustee Act)

Section 11(2)(

b) Name of Person Entitled

to Property

Description of

Property held

and its value or

estimated value

Property part of

deceased person's

Estate or held under

Court Order:

Deceased's Name

Judicial District

Court file number

Public Trustee

Office

Additional

Information

Estate of Gerald Joseph

Sheppard

$2,861.21

Gerald Joseph Sheppard,

Deceased,

DOD May 27, 2015

C064092

Estate of Samuel Wagner

$15,642.98

Samuel Wagner

C064091

Estate of Gordon

Demytryszyn

$8,538.01

Gordon Demytryszyn

C064097

Estate of Nery Abdias

Fernandes

$8,999.85

Nery Abdias Fernandes

C064141

Service Alberta and Red Tape Reduction

Notice of Intent to Cancel Extra-Provincial Registration

(Cooperatives Act)

Bioventus Cooperatief U.A.

Notice is hereby given that a notice of cancellation for the Extra-Provincial

Registration of Bioventus Cooperatief U.A. was received on November 17, 2023.

The Notice is in effect for 120 days.

Dated at Edmonton, Alberta, November 20, 2023.

Transportation and Economic Corridors

Contract Increases Approved Pursuant to Treasury Board Directive 02/2005

Contract: Clearing, Timber Salage, Grading, Granular Base Course, Asphalt

Concrete Pavement and Other Work for Highway 40 from South of Kakwa River to

North of Canfor Road including Seven Intersection Improvements (Contract No.

18341)

Contractor: Wapiti Gravel Suppliers, Division of N.P.A. Ltd.

Reason for Increase: The cost overrun is for addressing slides at two different

locations along Highway 40 - one on the sideslopes of the highway embankment

outside the project limits which was monitored for stability over the preceding years

which happened to deteriorate after the contract was awarded, and the other within the

project limits on the backslopes of the highway which happened to be caused by the

construction. Construction completion in 2022.

Contract Amount: $48,352,780.91

% Increase: 16.7%

Amount of Increase: $8,053,486.32

Contract: Culvert Liners and Other Work at Various Locations - Highway 16 West

of Mundare and near Vermilion, Highway 13 between Killan and Sedgewick and

Highway 2 between Innisfail and Red Deer (Contract No. 12327)

Contractor: In-line Contracting Ltd.

Reason for Increase: The cost overrun is for a design change for auger boring new

culverts instead of lining the existing culverts for reducing the possibility of the

existing pavement pushing up, and increasing the quantity of grout associated with

the change. Construction completion in 2012.

Contract Amount: $670,010.00

% Increase: 30.7%

Amount of Increase: $205,532.00

Contract: Bridge Culvert Replacement and Other Work for a Bridge carrying

Highway 734 over a tributary to Seven Mile Creek, near Caroline

(Contract No. 22212)

Contractor: Kichton Contracting Ltd.

Reason for Increase: The cost overrun is for a design change during construction to

provide better long term passage for certain fish species in light of possible increased

environmental regulation of the site, and additional turbity monitoring of water flow

as the water flow was more than normal for the season the construction was

occurring. Construction completion in 2022.

Contract Amount: $871,495.00

% Increase: 15.7%

Amount of Increase: $137,161.47

Contract: Emergency Spillway and Related Work for the Jensen Dam Flood

Handling Upgrades (Contract No. 21462)

Contractor: Greenfield Construction Ltd.

Reason for Increase: The cost overrun is for increases in the quantities of topsoil

removal and placement that were not originally anticipated, as well as for the

quantities of excavation, fill and granular materials. Construction completion in

Contract Amount: $13,782,098.79

% Increase: 11.6%

Amount of Increase: $1,600,927.80

Contract: Minor Grading, Granular Base Course, Asphalt Concrete Pavement and

Other Work for an Intersection Improvement at Jct. Highway 3 and 61 St. in the

Municipality of Crowsnest Pass (Contract No. 11103)

Contractor: South Rock Ltd.

Reason for Increase: The cost overrun is for additional excavation for unsuitable

foundation materials discovered during construction, and additional paving quantities

for improving the matching between the new paving limits and existing pavement.

Construction completion in 2012.

Contract Amount: $583,975.00

% Increase: 18.6%

Amount of Increase: $108,451.67

Contract: Slide Repair and Other Work along Highway 64, West of Cleardale

(Contract No. 22505)

Contractor: Northern Roadbuilders LP

Reason for Increase: The cost overrun is for an additional quantity of paving that

was not originally anticipated, and additional quantity for granular fill material.

Construction completion in 2022.

Contract Amount: $590,198.95

% Increase: 20.0%

Amount of Increase: $118,036.90

Contract: Slide Repair and Other Work along Highway 682, West of Fairview

(Contract No. 22345)

Contractor: CTR Contracting Ltd.

Reason for Increase: The cost overrun is for excavating a greater volume of soft

ground than originally anticipated and the associated granular backfill, and additional

paving to cover the entire length of the project. Construction completion in 2022.

Contract Amount: $1,508,509.21

% Increase: 12.6%

Amount of Increase: $190,435.35

Contract: Construct Concrete Pile Wall and Other Work Adjacent to Old Highway 2

at 99 Avenue Intersection within the Town of Peace River (Contract No. 18262)

Contractor: Kichton Contracting Ltd.

Reason for Increase: The cost overrun is for changes in the means and methods of

the piling work as well as increasing the depth for pile installations resulting from

differing ground conditions, increased measures for erosion control becoming evident

after heavy rains during construction, and additional excavation and backfill to

address ground conditions behind the pile wall. Construction completion in 2022.

Contract Amount: $7,160,000.00

% Increase: 13.7%

Amount of Increase: $984,190.13

Contract: Cold Milling, Asphalt Concrete Pavement and Other Work for Highway

749 from 20 km South of Highway 2 to the Town of High Prairie, and Grading,

Granular Base Course, Asphalt Concrete Pavement and Other Work for an

Intersection Improvement at Jct. Highway 749 and Twp. Rd. 740 (Contract No.

21983)

Contractor: Sandstar Construction Ltd.

Reason for Increase: The cost overrun is for addressing a number of culverts that

were discovered to be in poor condition during construction, an addition for paving

areas of Highway 33 that required emergency repair, and a contractually mandated

price adjustment for increased fuel costs. Construction completion in 2022.

Contract Amount: $7,960,572.00

% Increase: 11.2%

Amount of Increase: $887,689.38

Contract: Clearing and Timber Salvage and Other Work for Highway 63 from South

of House River to North of Mariana Lake (Contract No. 724010)

Contractor: Command Equipment Ltd.

Reason for Increase: The cost overrun is for additional clearing and timber salvage

for another segment of Highway 63. Construction completion in 2013.

Contract Amount: $2,510,817.00

% Increase: 11.6%

Amount of Increase: $291,281.00

Contract: Bridge Rehabilitation and Other Work for Bridges carrying Highway 2

over the Spirit River, North of Rycroft, Highway 49 over Henderson Creek, North of

Gordondale and Highway 49 over the Spirit River, West of Rycroft (Contract No.

13657)

Contractor: Carmacks Enterprises Ltd.

Reason for Increase: The cost overrun is for additional repairs for abutments, piers

and girders, significantly more than anticipated, that were required for the bridges

over Spirit River, and for additional surface repair for the bridge over Henderson

Creek that was not anticipated. Construction completion in 2012.

Contract Amount: $1,105,300.00

% Increase: 21.2%

Amount of Increase: $234,512.00

Contract: Grading, Granular Base Course, Asphalt Concrete Pavement and Other

Work for Intersection Improvements at Jct. Highway 13 and Rge. Rd. 10 at the

Hamlet of Westerose and Jct. Highway 771 and Sunnyside Dr., South of the Summer

Village of Parkland Beach (Contract No. 10632)

Contractor: TBL Construction Ltd.

Reason for Increase: The cost overrun is for unanticipated additional work to deal

with remediation of hydrocarbon contaminated soil and deep muskeg, an improved

design configuration for a turn-around and additional work for matching roadway

accesses being reconfigured as part of a development by an adjacent County.

Construction completion in 2013.

Contract Amount: $867,318.00

% Increase: 64.4%

Amount of Increase: $558,439.43

Contract: Maintenance and Operations of a Road Weather Information System

(Contract No. 702005)

Contractor: Telvent Canada Ltd.

Reason for Increase: The cost overrun is for adding additional road weather stations

across the province, expanding the work for the summer season, and a one-year

contract extension. Construction completion in 2017.

Contract Amount: $14,096,387.00

% Increase: 79.5%

Amount of Increase: $11,205,139.34

Contract: Clearing and Timber Salvage, Selective Grading and Other Work on

Highway 40 from South of Pinto Creek to North of Berland River (Contract No.

20671)

Contractor: Acres Prime Inc.

Reason for Increase: The cost overrun is a result of subsurface ground conditions in

areas both inside and outside the project limits requiring more grading work to

address than originally anticipated. Construction completion in 2019.

Contract Amount: $3,556,009.77

% Increase: 11.0%

Amount of Increase: $390,901.38

Contract: Grading, Storm Sewers, Mechanically Stabilized Earth Walls, Granular

Base Course, Asphalt Concrete Pavement, Street Lighting, Sign Structures for

Interchange Construction at the Jct. of Highway 63 and Thickwood Blvd. and the Jct.

of Highway 63 and Confederation Way, and Construct Structural Steel Girder Bridges

carrying Thickwood Blvd. and Confederation Way over Highway 63 and Demolition,

Construct Steel Arch Culvert and Other Work for carrying Highway 63 over Conn

Creek in Fort McMurray (Contract No. 7884/09)

Contractor: South Rock Ltd.

Reason for Increase: The cost overrun is a result of a number of items, in particular,

access construction for a land lot purchased from the Regional Municipality of Wood

Buffalo, paving quantity increases for Thickwood Boulevard, updating painted

roadway lines to high visibility wet night paint and durable pavement markings, and a

number changes at the Confederation Way interchange, in particular, a design change

for dedicated bus lanes, additional ground stabilization measures, providing better

transitioning for the new alignment, additional traffic accommodation during

construction and

schedule changes to advance the opening of Confederation Way.

Construction completion in 2015.

Contract Amount: $75,623,199.00

% Increase: 22.0%

Amount of Increase: $16,652,164.68

Contract: Demolition and Construct Structural Plate Corrugated Steel Pipe Culvert

and Other Work for a Bridge carrying Highway 28 over Cache Creek, West of

Spedden (Contract No. 10588)

Contractor: Cruickshank West Inc.

Reason for Increase: The cost overrun is a result of poor subsurface ground

conditions discovered during construction requiring deeper excavation for removing

and disposing ground materials and replacing with suitable excavated materials.

Construction completion in 2014.

Contract Amount: $687,240.00

% Increase: 24.7%

Amount of Increase: $169,481.00

Contract: Grading, Storm Sewer Installation Granular Base Course, Asphalt

Concrete Pavement, Street Lighting and Other Work on Highway 63 from Morrison

St. to the Athabasca River in Fort McMurray, Construct Structural Steel Girder

Bridge and Other Work for a Grade Separation carrying Highway 63 over Franklin

Ave. in Fort McMurray, and Bridge Superstructure Replacement and Other Work for

a Bridge carrying the South Bound Lanes of Highway 63 over the Athabasca River in

Fort McMurray (Contract No. 10704)

Contractor: Flatiron Constructors Canada Ltd.

Reason for Increase: The cost overrun is for adding a retaining wall to the project to

address the existing highway embankment encroaching upon an adjacent parcel of

land, and

schedule adjustments. Construction completion in 2015.

Contract Amount: $50,309,391.40

% Increase: 10.2%

Amount of Increase: $5,143,729.83

Contract: Grading, Granular Base Course, Asphalt Concrete Pavement, Sideslope

Trail) from Jct. Highway 1 to Jct. Highway 2 in the City of Calgary (Contract No.

10983)

Contractor: South Rock Ltd.

Reason for Increase: The cost overrun was largely for a design revision adding

access and egress ramps at the 14th Street NW Interchange on a cost-reimbursable

basis from the City of Calgary. Construction completion in 2015.

Contract Amount: $10,062,531.00

% Increase: 24.0%

Amount of Increase: $2,413,431.31

Contract: Bridge Painting and Other Work for a Bridge carrying Highway 49 over

the Little Smoky River, South of Guy (Contract No. 11466)

Contractor: Park Derochie Inc.

Reason for Increase: The cost overrun is a result of delays from migratory birds

nesting on the bridge requiring the work to be deferred further into the winter months

in turn requiring additional heating and hoarding measures and causing productivity

impacts, along with maintenance repairs for corrosion that was discovered upon

commencing the work. Construction completion in 2015.

Contract Amount: $4,035,402.00

% Increase: 12.0%

Amount of Increase: $482,977.62

Contract: Bridge Culvert Replacement and Other Work for a Bridge carrying

Highway 772 over a watercourse, West of Balzac (Contract No. 11672)

Contractor: Ironclad Earthworks Ltd.

Reason for Increase: The cost overrun is a result of delay costs stemming from a

wetland within the proximity of the project where the environmental permits had not

been acquired before construction but were required in order for the project to

proceed. Construction completion in 2015.

Contract Amount: $642,795.00

% Increase: 33.3%

Amount of Increase: $213,762.99

Contract: Cold Milling, Crack Repair, Asphalt Concrete Pavement and Other Work

from North of Lessard Road to the Whitemud Drive Interchange and from Webber

Green Drive/87 Ave., West of Jct. Highway 216 to East of Jct. Highway 216 in the

City of Edmonton (Contract No. 11711)

Contractor: Earthwise Contracting Ltd.

Reason for Increase: The cost overrun is a result of adding auxiliary driving lanes

for both directions of travel to address safety concerns that arose, requiring grading,

granular base course and asphalt concrete pavement. Construction completion in

Contract Amount: $5,327,403.34

% Increase: 37.0%

Amount of Increase: $1,971,974.10

Contract: Design, Supply and Install Bridge Deck De-Icing System and Other Work

for a Bridge carrying the North Bound Lanes of Highway 63 over the Athabasca

River in Fort McMurray (Contract No. 12255)

Contractor: Graham Construction and Engineering, a JV

Reason for Increase: The cost overrun was required to re-match the final

configuration of the de-icing system to the adjoining bridge rather than to a temporary

detour that was in use for the construction of the bridge, for providing a power feed

that was originally intended to be performed under another contract, and for field

revisions to match the design to existing conditions. Construction completion in

Contract Amount: $3,177,750.00

% Increase: 15.5%

Amount of Increase: $493,569.11

Contract: Cold Milling, Asphalt Concrete Pavement and Other Work on Highway 2

from North of Jct. Highway 590 to South of Red Deer (Contract No. 12300)

Contractor: Carmacks Enterprises Ltd.

Reason for Increase: The cost overrun resulted from adding improvement work for

the Interchange of Highway 2 and Highway 27 to the contract. Construction

completion in 2015.

Contract Amount: $12,700,001.00

% Increase: 10.7%

Amount of Increase: $1,353,016.94

Contract: Slide Repair along Highway 726, South of Worsley (Contract No. 13204)

Contractor: Kichton Contracting Ltd.

Reason for Increase: The cost overrun is for a river bank repair and armoring the toe

of a pile wall for protection from erosion arising from heavy snowfall the previous

winter along with a wet spring and summer, and improving the construction detour

for better traffic accommodation over the winter. Construction completion in 2015.

Contract Amount: $7,299,500.00

% Increase: 16.6%

Amount of Increase: $1,211,285.51

Contract: Grade Widening, Granular Base Course, Asphalt Concrete Pavement,

Street Light Installation, Traffic Signals and Other Work for an Intersection

Improvement at the Jct. Highway 43 and the Grande Prairie Airport Access

(Contract No. 14337)

Contractor: Wapiti Gravel Suppliers, Division of N.P.A. Ltd.

Reason for Increase: The cost overrun was for adding durable pavement messages

for improved traffic safety and rotatable street light bases to accommodate high loads.

Construction completion in 2014.

Contract Amount: $1,445.587.90

% Increase: 16.7%

Amount of Increase: $240.976.64

Contract: Riparian Outlet Rehabilitation and Other Work at Coal Lake Dam,

Northeast of the Hamlet of Gwynne (Contract No. 14477)

Contractor: Jacob Bros. Construction Ltd.

Reason for Increase: The cost overrun is for increased care of water measures

arising from differing site conditions as well as increased cost for concrete work

arising from differing ground conditions and contributing to project delay and

associated cost. Construction completion in 2016.

Contract Amount: $1,946,840.00

% Increase: 37.3%

Amount of Increase: $725,886.21

Contract: Grading and Other Work for Highway 63 from North of the Hangingstone

River to South of Jct. Highway 881 (Contract No. 15035)

Contractor: North American Enterprises Ltd.

Reason for Increase: The cost overrun resulted from carrying out topsoil excavations

from outside of the project limits from another contract, and for supplying and

utilizing a drying agent for conditioning excavated material incorporated into

roadway embankment. Construction completion in 2015.

Contract Amount: $15,979,000.00

% Increase: 40.7%

Amount of Increase: $6,503,364.70

Contract: Slide Repair, Slope Stabilization and Other Work adjacent to Highway

744, South Peace River (Contract No. 15153)

Contractor: Kichton Contracting Ltd.

Reason for Increase: The cost overrun was to address a second slide of similar size

that occurred adjacent to the project prior to construction commencing on the first

project. Construction completion in 2016.

Contract Amount: $9,416,408.50

% Increase: 106.7%

Amount of Increase: $10,049,226.18

Contract: Cast-in-Place Concrete Floor, Precast Roof Slab, and Other Work for a

Bridge carrying Highway 2 over Pats Creek - Phase 2 (Contract No. 15253)

Contractor: Glen Armstrong Construction Ltd.

Reason for Increase: The cost overrun is for installing steel plates to protect exposed

untreated timber components within the existing structure from water damage.

Construction completion in 2014.

Contract Amount: $1,108.203.00

% Increase: 12.2%

Amount of Increase: $134,828.00

Contract: Bridge Rehabilitation and Other Work for a Bridge carrying Highway 547

over Highwood River (Contract No. 15394)

Contractor: Eastern Infrastructure Inc.

Reason for Increase: The cost overrun resulted from project delays during

construction for mitigating distress to migratory birds nesting within the bridge

structure. Construction completion in 2014.

Contract Amount: $999,691.00

% Increase: 18.9%

Amount of Increase: $189,353.65

Contract: Drainage Improvements, Slope Repairs and Other Work on Highway 63

from Thickwood Blvd. to Confederation Way (Contract No. 15942)

Contractor: In-Line Contracting Ltd.

Reason for Increase: The cost overrun is for a design change for auger boring

culverts to deal with differing conditions, as well as increased topsoil and seeding

quantities that were originally under-estimated. Construction completion in 2015.

Contract Amount: $3,280,970.00

% Increase: 22.1%

Amount of Increase: $725,844.68

Contract: Bridge Rehabilitation and Other Work for a Bridge carrying Highway 582

over Kneehills Creek (Contract No. 15958)

Contractor: CWP Constructors Ltd.

Reason for Increase: The cost overrun was for replacing reinforcing steel, the

condition of which could not be determined until the bridge deck was exposed during

construction, and other elements which were corroded. Construction completion in

Contract Amount: $691,931.68

% Increase: 18.5%

Amount of Increase: $128,086.38

Contract: Grade Widening, Storm Sewer, Granular Base Course, Cold Milling,

Asphalt Concrete Pavement, Street Light Installation and Other Work from South of

Jct. Highway 36 to Jct. Highway 36, Intersection Improvements at Jct. Highway 36

and Highway 45 and at Jct. Highway 29 and Highway 45, and Urban Approach Road

150 from Jct. Highway 45 to the Hamlet of Hairy Hill (Contract No. 16740)

Contractor: TBL Construction Ltd.

Reason for Increase: The cost overrun was for redesigning the pavement structure to

accommodate delivery of large industrial modules for the Ft. McMurray industrial

area that were delayed from the 2016 Wood Buffalo Wildfire, increases for design

improvements to numerous contract items such as highway illumination, local road

paving, culverts and erosion control. Construction completion in 2017.

Contract Amount: $4,404,487.03

% Increase: 58.6%

Amount of Increase: $2,583,182.59

Contract: Cold Milling, Asphalt Concrete Pavement and Other Work on Highway 26

from 6 Km West of Highway 855 to 3 Km West of Highway 857 and Highway 834

from Highway 13 to Highway 26 (Contract No. 18353)

Contractor: Central City Asphalt Ltd.

Reason for Increase: The cost overrun was for addressing deteriorated sections of

Highway 56 with paver laid patching, and for installing and grouting steel liners for

two culverts that required repair. Construction completion in 2018.

Contract Amount: $4,010,466.20

% Increase: 10.1%

Amount of Increase: $404,440.49

Contract: Bridge Superstructure and Abutment Substructure Replacement and Other

Work for a Bridge carrying Highway 689 over Beaton Creek, West of Dixonville

(Contract No. 18418)

Contractor: DCL Construction Services Ltd. and A & A Paving Ltd.

Reason for Increase: The cost overrun was for costs associated with delays by the

Province and additional embankment structure and geotechnical measures to address

loading for heavy traffic on highway accesses, and for addressing unanticipated high

water events from an unusually wet construction season. This contract was started

but not finished by DCL Construction Services Ltd.; A & A Paving Ltd. finished the

project in 2022 as the replacement contractor.

Contract Amount: $4,062,588.40

% Increase: 15.7%

Amount of Increase: $637,917.37

Contract: Site Remediation and Other Work for the Former Imperial Oil Ltd. Site

adjacent to 94th St., North of Highway 2 in the Town of Peace River (Contract No.

18436)

Contractor: Kichton Contracting Ltd.

Reason for Increase: The cost overrun is for additional temporary structural support

for the excavation, and remediation work to address wider and deeper areas of

contamination from what was originally anticipated. Construction completion in

Contract Amount: $2,002,500.00

% Increase: 19.9%

Amount of Increase: $397,672.13

Contract: Grading, Bridge Culverts and Other Work for Highway 63 from North of

Algar Tower to South of Horse Creek (Contract No. 745410)

Contractor: Prairie North Const. Ltd.

Reason for Increase: The cost overrun is for removing and handling aggregate that

was discovered beneath the proposed highway for use for granular base course and

pavement for other highway projects, raising the design elevations of the highway to

mitigate the impacts of potential floods, and additional quantities for geotextile for

soil stabilization for soft ground areas throughout the project. Construction

completion in 2014.

Contract Amount: $33,022,506.00

% Increase: 26.2%

Amount of Increase: $8,640,635.26

Contract: Grading and Other Work for Service Road Construction along Highway 43

from the West to East Boundaries of the Sturgeon Lake Indian Reserve (Contract No.

803510)

Contractor: Petrowest Construction LP

Reason for Increase: The cost overrun is related to adding bridge size culverts for

service roads on Sturgeon Lake Cree Nation's land along both sides of Highway 43

and a bridge file replacement on Highway 43 that became necessary after construction

commenced, as well as increased volumes of excavation to address unsuitable

existing ground material. Construction completion in 2014.

Contract Amount: $16,602,368.30

% Increase: 68.3%

Amount of Increase: $11,336,035.89

Contract: Grading, Granular Base Course, Asphalt Concrete Pavement, Bridge

Culverts, Street Lighting and Other Work for Highway 43 from East of Crooked

Creek to West of the Sturgeon Lake Indian Reserve (Contract No. 806710)

Contractor: Richardson Bros. (Olds) Ltd.

Reason for Increase: The cost overrun is for a design change addressing

geotechnical challenges in construction through muskeg over a portion of the project,

the additions of a safety rest area and a service road extension that become possible

after construction commenced, and culvert replacements that became apparent after

construction commenced, and a contractually mandated price adjustment for

increased fuel costs. Construction completion in 2014.

Contract Amount: $24,832,355.00

% Increase: 19.0%

Amount of Increase: $4,727,237.58

Treasury Board and Finance

Insurance Notice

(Captive Insurance Companies Act)

Effective November 22, 2023, HAR Insurance LP became licensed to transact

Property insurance in Alberta.

David Sorensen

Deputy Superintendent of Insurance.

Insurance Notice

(Insurance Act)

Effective November 14, 2023, Omega General Insurance Company changed its

name to Accelerant Insurance Company of Canada.

David Sorensen

Deputy Superintendent of Insurance.

_______________

Effective January 1, 2024, Waterloo Insurance Company, The Missisquoi

Insurance Company, Perth Insurance Company and Definity Insurance

Company amalgamated and continue as one company under the name Definity

Insurance Company pursuant to

section 159 of Alberta's Insurance Act.

David Sorensen

Deputy Superintendent of Insurance.

Notice of Adjustment to the Minor Injury Amount

(Insurance Act)

Pursuant to the Minor Injury Regulation, the maximum amount awarded for minor

injuries is adjusted to $6,061 and is applicable to minor injuries caused in automobile

accidents occurring in Alberta on or after January 1, 2024.

The following appendix sets out the method of calculating the adjustment to the

minor injury amount.

Dated at Edmonton this 21st day of November, 2023.

Mark Brisson, Superintendent of Insurance.

Ref: Insurance Act

Minor Injury Regulation

Appendix

The maximum amount recoverable as damages for non-pecuniary losses for all minor

injuries sustained by a claimant as a result of an automobile accident, occurring

during the 2024 calendar year, is $6,061.

This amount is based on the annual change in the Alberta Consumer Price Index

(CPI), and calculated using the following formulas:

(

a) The annual change in the Alberta CPI was calculated to one-tenth of a

percentage point using the formula X = (A-B) / B where:

X is the annual change in the Alberta CPI;

A is the sum of the 12 individual monthly CPI indexes for the 12 month

period ending on September 30, 2023; and

B is the sum of the 12 individual monthly CPI indexes for the 12 month

period ending on September 30, 2022;

(

b) The result in (

a) is multiplied by the 2023 minor injury amount and rounded

to the nearest whole dollar to derive the increase in the minor injury amount

for 2024; and

(

c) The increase in (

b) is added to the 2023 minor injury amount and rounded to

the nearest whole dollar to establish the 2024 minor injury amount.

The following data were used in the calculation:

12-m period

ending

Sept 30, 2022

Alberta

Consumer

Price Index

12-m period

ending

Sept 30, 2023

Alberta

Consumer

Price Index

Oct-21

151.5

Oct-22

161.8

Nov-21

151.6

Nov-22

161.6

Dec-21

151.7

Dec-22

160.8

Jan-22

152.8

Jan-23

160.5

Feb-22

154.5

Feb-23

160.1

Mar-22

156.5

Mar-23

161.7

Apr-22

157.0

Apr-23

163.7

May-22

159.2

May-23

164.1

Jun-22

161.4

Jun-23

164.4

Jul-22

161.4

Jul-23

166.0

Aug-22

160.0

Aug-23

166.8

Sep-22

160.1

Sep-23

166.0

Summation (B)

1877.7

Summation (A)

1957.5

Based on the above, the annual change in the Alberta CPI, rounded to one-tenth of a

percentage point, is .042499 (or 4.2 per cent). The increase in the minor injury

amount for 2024 is 4.2 per cent of the 2023 minor injury amount of $5,817 rounded to

the nearest whole dollar (or $244). Accordingly, the 2024 minor injury amount is set

at $6,061.

The historical maximum minor injury amounts, reported by effective date, are:

Effective Date Range

Minor Injury Amount

October 1, 2004 - December 31, 2006

$4,000

January 1, 2007 - December 31, 2007

$4,144

January 1, 2008 - December 31, 2008

$4,339

January 1, 2009 - December 31, 2009

$4,504

January 1, 2010 - December 31, 2010

$4,518

January 1, 2011 - December 31, 2011

$4,559

January 1, 2012 - December 31, 2012

$4,641

January 1, 2013 - December 31, 2013

$4,725

January 1, 2014 - December 31, 2014

$4,777

January 1, 2015 - December 31, 2015

$4,892

January 1, 2016 - December 31, 2016

$4,956

January 1, 2017 - December 31, 2017

$5,020

January 1, 2018 - December 31, 2018

$5,080

January 1, 2019 - December 31, 2019

$5,202

January 1, 2020 - December 31, 2020

$5,296

January 1, 2021 - December 31, 2021

$5,365

January 1, 2022 - December 31, 2022

$5,488

January 1, 2023 - December 31, 2023

$5,817

January 1, 2024 - December 31, 2024

$6,061

ADVERTISEMENTS

Law Society of Alberta

Election of Benchers - November 21, 2023

(Legal Profession Act)

Deanna Steblyk, KC

Sandra Petersson, KC

Bud G. Melnyk, KC

L. Grant Vogeli, KC

Ryan D. Anderson, KC

Kelsey J. Meyer

Stephanie Dobson

Sony Singh Ahluwalia, KC

Stacy Petriuk, KC

Arman Chak

Nicole Stewart

Sharilyn C. Nagina, KC

Jim M. Lutz, KC

Ronald A. Sorokin

Moira V ne

Scott Matheson

David Tupper

Malcolm Lavoie

A. Danielle Bourgeois

Kene Ilochonwu, KC

Public Sale of Land

(Municipal Government Act)

Mackenzie County

Notice is hereby given that, under the provisions of the Municipal Government Act,

Mackenzie County will offer for sale, by public auction, in the Council Chambers,

4511 46 Avenue, Fort Vermilion, Alberta, on Wednesday, February 28, 2024, at

1:00 p.m., the following lands:

Lot

Block

Plan

LINC

C. of T.

Address

994 Tower Rd

1001 Tower Rd

1054 Industrial Dr

2016 Dusty Ln

2018 Dusty Ln

2020 Dusty Ln

2025 Dusty Ln

188TR

4302 - 50 Ave

188TR

4316 - 52 Ave

2938RS

4410 - 50 St

2938RS

4802 - 50 St

2938RS

4810 - 46 Ave

188TR

5005 - 43 St

4357MC

5007 - 45 St

N/A

Each parcel will be offered for sale, subject to a reserve bid and to the reservations

and conditions contained in the existing certificate of title. Additional conditions of

building demolition and levelling of lot and/or repair of unsightly conditions will

apply.

The land is being offered for sale on an "as is, where is" basis, and Mackenzie County

makes no representation and gives no warranty whatsoever as to the adequacy of

services, soil conditions, land use districting, building and development conditions,

absence or presence of environmental contamination, or the developability of the

subject land for any intended use by the purchaser. No bid will be accepted where the

bidder attempts to attach conditions precedent to the sale of any parcel. No terms and

conditions of sale will be considered other than those specified by Mackenzie County.

No further information is available at the auction regarding the lands to be sold.

Mackenzie County may, after the public auction, become the owner of any parcel of

land not sold at the public auction.

Terms: 25% of the bid amount (not to be less than $1,000) by cash, certified cheque

or money order, of which $1,000 will be non-refundable to the successful bidder at

time of the sale. Balance to be paid to Mackenzie County within 30 (thirty) calendar

days of the date of the auction.

This list is subject to deletions. Redemption may be effected by payment of all arrears

of taxes and costs at any time prior to the sale.

Dated at Fort Vermilion, Alberta, November 30, 2023.

Darrell Derksen, Chief Administrative Officer.

_______________

Village of Innisfree

Notice is hereby given that, under the provisions of the Municipal Government Act,

the Village of Innisfree will offer for sale, by public auction, in the Village Office,

5116 50 Avenue, Innisfree, Alberta, on Thursday, January 25, 2024, at 5:00 p.m., the

following lands:

LINC

Legal Desc.

C. of T.

SW 11-51-11-W4M

0018368266 / 0018368274

4175R; 6; 4-6

8621236; 22; 2

952260994 +2

8621236; 22; 3

902047092 +1

1. These parcels are being offered for sale by auction, subject to a reserve bid and to

certain registrations shown on the existing certificate of title as described in

section 423(1) of the Municipal Government Act.

2. These parcels are being offered for sale on an "as is, where is" basis, and the

Village of Innisfree makes no representation and gives no warranty whatsoever

as to the adequacy of services, soil conditions, land use districting, building and

development conditions, absence or presence of environmental contamination, or

the developability of the parcel for any intended use by the successful bidder. No

bid will be accepted where the bidder attempts to attach conditions precedent to

the sale of any parcel. No Terms or Conditions of Sale will be considered other

than those specified by the Village of Innisfree.

3. The parcels listed above shall be subject to the tax sale if the total outstanding

property tax arrears remain outstanding prior to the tax sale.

4. Successful bidders shall be required to execute a Sale Agreement in a form and

substance acceptable to the Village of Innisfree.

5. A non-refundable deposit equal to 10% of the purchase price, by bank draft or by

lawyer's trust cheque shall be due on the sale date, with the balance of the

purchase price due on closing.

6. Purchasers are responsible for obtaining vacant possession.

7. If no offer is received for a parcel, or if the reserve bid is not met, the parcel will

not be sold at the public auction. The Village of Innisfree may, after the public

auction, become the owner of any parcel of land not sold at the public auction.

8. All sales are subject to current taxes.

9. GST shall apply on parcels sold at the public auction.

10. Redemption may be affected by payment of all arrears of taxes and costs at any

time prior to the date of the sale. Parcels may be deleted from this sale as the tax

arrears and costs are paid.

Dated at Innisfree, Alberta, November 28, 2023.

Thelma Rogers, Interim Chief Administrative Officer.

Village of Marwayne

Notice is hereby given that, under the provisions of the Municipal Government Act,

the Village of Marwayne will offer for sale, by public auction, in the ATB Financial

Board Room, 34 Center Street, Marwayne, Alberta, on Monday, February 12, 2024,

at 7:00 p.m., the following parcel:

Roll

Lot

Block

Plan

C. of T.

56HW

1. Any parcel of land offered for sale may be redeemed by payment of all arrears,

penalties and costs by guaranteed funds at any time until the property is declared

sold.

2. Each parcel of land offered for sale will be subject to a reserve bid and title will

be subject to the reservations and conditions contained in the existing certificate

of title.

3. The lands are being offered for sale on an "as is, where is" basis, and the

municipality makes no representation and gives no warranty whatsoever as to the

state of the parcel nor its suitability for any intended use by the successful bidder.

4. The auctioneer, councillors, the chief administrative officer and the designated

officers and employees of the municipality must not bid or buy any parcel of land

offered for sale, unless directed by the municipality to do so on behalf of the

municipality.

5. The purchaser of the property will be responsible for property taxes and utilities

for the current year. There will be no adjustment to the date of sale.

6. The purchaser will be required to execute a sale agreement in form and substance

provided by the municipality.

7. The successful purchaser must, at the time of sale, make payment in cash,

certified cheque or bank draft payable to the municipality as follows:

a. The full purchase price if it is $10,000 or less; OR

b. If the purchase price is greater than $10,000, the purchaser must

provide a non-refundable deposit in the amount of $10,000 and the

balance of the purchase price must be paid within 20 days of the sale.

(if the certified cheque or bank draft exceeds the final purchase price, the

excess will be refunded within a reasonable time)

8. GST will be collected on all properties subject to GST.

9. The risk of the property lies with the purchaser immediately following the

auction.

10. The purchaser is responsible for obtaining vacant possession.

11. The purchaser will be responsible for registration of the transfer including

registration fees.

12. If no offer is received on a property or if the reserve bid is not met, the property

cannot be sold at the public auction.

13. The municipality may, after the public auction, become the owner of any parcel

of land that is not sold at the public auction.

14. Once the property is declared sold at public auction, the previous owner has no

further right to pay the tax arrears.

Dated at Marwayne, Alberta, November 20, 2023.

Shannon Harrower, Chief Administrative Officer.

NOTICE TO ADVERTISERS

The Alberta Gazette is issued twice monthly, on the 15th and last day.

Notices and advertisements must be received ten full working days before the

date of the issue in which the notices are to appear. Submissions received after

that date will appear in the next regular issue.

Notices and advertisements should be typed and on a sheet separate from the covering

letter. An electronic submission by email is preferred. Email submissions may be sent

to the Editor of The Alberta Gazette at albertagazette@gov.ab.ca. The number of

insertions required should be specified and the names of all signing officers typed or

printed. Please include the name and complete contact information of the individual

submitting the notice or advertisement.

Proof of Publication: Statutory Declaration is available upon request.

A copy of the page containing the notice or advertisement will be emailed to each

advertiser without charge.

The dates for publication of Tax Sale Notices in The Alberta Gazette are as follows:

Issue of

Earliest date on which

sale may be held

December 30

February 9

January 15

February 25

January 31

March 12

February 15

March 27

February 29

April 10

March 15

April 25

March 30

May 10

April 15

May 26

April 30

June 10

May 15

June 25

May 31

July 11

June 15

July 26

The charges to be paid for the publication of notices, advertisements and documents

in The Alberta Gazette are:

Notices, advertisements and documents that are 5 or fewer pages $20.00

Notices, advertisements and documents that are more than 5 pages $30.00

Please add 5% GST to the above prices (registration number R124072513).

PUBLICATIONS

Annual Subscription (24 issues) consisting of:

Part I/Part II, and annual index - Print version $150.00

Part I/Part II, and annual index - Electronic version $150.00

Alternatives:

Single issue (Part I and

Part II) $10.00

Annual Index to

Part I or

Part II $5.00

Alberta Gazette Bound

Part I $140.00

Alberta Gazette Bound Regulations $92.00

The following shipping and handling charges apply for orders delivered outside of

Alberta, but within Canada:

Annual Subscription - Print version $50.00

Individual Gazette publications $10.00 on orders of $49.99 or less

Individual Gazette publications $15.00 on orders from $50.00 to $99.99

Individual Gazette publications $25.00 on order of $100.00 or more

Please add 5% GST to the above prices (registration number R124072513).

Copies of Alberta legislation and select government publications are available from:

Alberta King's Printer

Suite 700, Park Plaza

10611 - 98 Avenue

Edmonton, Alberta T5K 2P7

Phone: 780-427-4952

(Toll free in Alberta by first dialing 310-0000)

kings-printer@gov.ab.ca

kings-printer.alberta.ca

Cheques or money orders (Canadian funds only) should be made payable to the

Government of Alberta. Payment is also accepted by Visa, MasterCard or American

Express. No orders will be processed without payment.

Document details

CollectionAlberta — Gazette
CitationFriday, December 15, 2023
Typegazette
Volume / chapter23 Dec15 Part1
Languageen
Formathtml
SourcePROVINCIAL
Identifier68c1cdb805f1cafbfe522064720377bc55d84be1

Source file is stored in the law ingest library (html).