Alberta Gazette — 15 November 2023 (Part II)
15 November 2023
Alberta — Gazette
Alberta Regulation 125/2023
Pipeline Act
PIPELINE RULES
Filed: October 31, 2023
For information only: Made by the Alberta Energy Regulator on October 30, 2023
pursuant to sections 3(1)(a)-(e), (g)-(i), (k), (l), (n)-(s), (u), (w), (w.1), (x)-(
z) and
(bb)-(ff) of the Pipeline Act.
Table of Contents
Interpretation
Part 1
Administration
2 Exemption from application of Act and Rules
3 Exemption - agents
4 Compliance with directives
5 Notification
6 Eligibility to hold a licence
7 Application for licence
8 Survey of right of way boundaries
9 Notice of construction commencement
10 Notice or application in case of delay or failure to complete
construction
11 Emergency response plan
12 Pipeline records and documents
13 Transfer of records
14 Safety and Loss Management System
15 Integrity Management Program
16 Financial information
Part 2
Materials and Design
17 Materials to be provided to Regulator
18 CSA standards
19 Approval of non-standard materials or methods
20 Limits on polymeric or composite pipe
21 Design for maintenance, inspection and purging
22 Pipeline maintenance pigs
23 Emergency shutdown devices and check valves
24 Control systems in blended gas streams
25 Equipment pressure ratings
26 Stress level limitations
27 Maximum noise levels
28 Pipeline crossing highway or road
29 Minimum earth cover
30 Installing surface pipelines
31 Operating pressure
Part 3
Pressure Testing
32 Placing pipeline into operation
33 Notice to Regulator
34 Conditions for pressure testing
35 Regulator's direction on pressure testing
36 Recording pressure test results
37 Unsatisfactory pressure test
38 Minimum test pressure
39 Pressure testing using liquid test media other than fresh water
40 Pressure testing using gaseous test media
41 Duration of pressure test
Part 4
Ground Disturbance
42 No fees for ground disturbance
43 Ground disturbance approval
44 Damage prevention service
45 Preparing for ground disturbance
46 Locating and marking of pipelines
47 Supervision of ground disturbance
48 Control of access over right of way
49 Vehicles crossing pipeline
50 Safety of adjacent pipeline
51 Exposing pipeline
52 Inspection prior to backfilling
Part 5
Warning Signs
53 Location of pipeline warning signs
54 Installation of pipeline warning signs
55 Maintenance of pipeline warning signs
56 Alternate signage
57 Temporary pipeline warning signs
58 HVP product
59 Group pipeline signs
60 Identification of pipeline installations
Part 6
Changes to Pipeline
61 Liner and internal protection installation
62 Liner and internal protection installation in sour service
63 Change in substance or pressure
64 Testing requirements for change in substance or pressure
Part 7
Relocation or Alteration of Pipeline or Other
Regulator Direction
65 Application for direction under
section 33 of Act
66 Notice to Regulator
Part 8
Release of Product and Contact Damage
67 Report of leak, break or contact damage
68 Containment of leak or break
69 Repair of leak, break or contact damage
70 Intentional release of gas
Part 9
Discontinuance, Abandonment, Removal
and Resumption
71 General
72 Duty to maintain and manage as operating
73 Application in case of discontinuance, abandonment or removal
74 Discontinuance or abandonment of entire pipeline system
75 Conducting discontinuance
76 Conducting abandonment
77 Closure quotas
78 Closure plans
79 Mandatory abandonment
80 Responsibility for discontinued or abandoned pipeline
81 Conducting removal
82 Resumption of pipeline operation
Part 10
Transitional Provisions, Repeal, Expiry and Coming into
Force
83 Transitional
84 Repeal
85 Expiry
86 Coming into force
Schedules
Interpretation
1(1) In these Rules,
(a) "Act" means the Pipeline Act;
(b) "active flowing service" means a pipeline conveying
substances in
(
i) continuous service,
(ii) intermittent service if the pipeline is used regularly at
predictable intervals, or
(iii) periodic service that occurs irregularly but based on the
pipeline's established actual operational need,
but does not include temporarily conveying substances for
short periods that are not part of regular operations of a
pipeline;
(c) "break" means the escape of substance from a pipeline in a
manner that immediately impairs the operation of the
pipeline;
(d) "closure" means the phase of the energy resource
development life cycle that involves the permanent end of the
operation of a pipeline, and includes abandonment and
reclamation of a pipeline;
(e) "composite" means consisting of a matrix of reinforcing
fibres, strands, wires or strips, encased within a polymeric
resin or structure, but does not include composite repair
wraps used to externally reinforce existing pipe;
(f) "contact damage" means damage occurring to an installed
pipeline during a ground disturbance and that results in
(
i) a puncture or crack in the pipeline,
(ii) a scratch, gouge, flattening or dent on the pipeline
surface, or
(iii) damage to the pipeline's protective coating that
compromises the functionality of the coating, with the
exception of minor damages that may occur during final
hand excavation and external cleaning;
(g) "CSA" means the Canadian Standards Association;
(h) "dead leg" means a pipeline
section open to an operating
pipeline on one end and closed at the other end that
consequently has no flow;
(i) "Directive 038" means Directive 038: Noise Control;
(j) "Directive 050" means Directive 050: Drilling Waste
Management;
(k) "Directive 056" means Directive 056: Energy Development
Applications and Schedules;
(l) "Directive 058" means Directive 058: Oilfield Waste
Management Requirements for the Upstream Petroleum
Industry;
(m) "Directive 060" means Directive 060: Upstream Petroleum
Industry Flaring, Incinerating, and Venting;
(n) "Directive 067" means Directive 067: Eligibility
Requirements for Acquiring and Holding Energy Licences
and Approvals;
(o) "Directive 071" means Directive 071: Emergency
Preparedness and Response;
(p) "Directive 077" means Directive 077: Pipelines -
Requirements and Reference Tools;
(q) "Directive 088" means Directive 088: Licensee Life-Cycle
Management;
(r) "distribution specification gas" means natural gas that does
not contain more than an average of 7 milligrams of
hydrogen sulphide gas per cubic metre of natural gas at an
absolute pressure of 101.325 kilopascals at a temperature of
15 degrees Celsius, equivalent to 5 parts per million;
(s) "drilling waste" means the mud and cuttings generated while
directional drilling for the purpose of pipeline construction;
(t) "emergency" means a present or imminent event, outside the
scope of normal operations, that requires prompt
coordination of resources to protect the health, safety or
welfare of people or to limit damage to property and the
environment;
(u) "engineering assessment" means an engineering assessment
conducted in accordance with CSA Z662;
(v) "expanded liner" means either a tight-fitting or expanded
thermoplastic corrosion barrier installed within, and in direct
contact with, the metallic pipeline that constitutes the
load-bearing member;
(w) "facility surface lease" means the area leased by a licensee
for a well, installation or facility connected to a pipeline, but
does not include an access road to the well, installation or
facility or a pipeline installation lease;
(x) "freestanding liner" means a loose-fitting or stand-alone
polymeric or composite pipeline having its own
pressure-retaining capability installed within a pipeline where
the latter serves only as a hollow conduit for the freestanding
liner;
(y) "group 1 water" means water meeting the criteria for group 1
water in Directive 077;
(z) "group 2 water" means water meeting the criteria for group 2
water in Directive 077;
(aa) "group 3 water" means water meeting the criteria for group 3
water in Directive 077;
(bb) "hand excavation" means excavation of a pipeline or part of a
pipeline by
(
i) manual labour using hand tools,
(ii) water or air jets and vacuum extraction equipment, or
(iii) any other method authorized by the Regulator;
(cc) "HVP product" means a high vapour pressure product,
including hydrocarbons or a hydrocarbon mixture, as defined
in CSA Z662;
(dd) "installed pipeline" means
(
i) the portion of pipeline that has been
(
A) backfilled, or
(
B) mounted to any necessary above-ground support
structures or pipe racks,
(ii) in the case of pipelines laid on the ground, the point at
which the pipeline is ready for pressure testing;
(ee) "Integrity Management Program" means an Integrity
Management Program developed under
section 15;
(ff) "landowner" means
(
i) the person in whose name a certificate of title has been
issued pursuant to the Land Titles Act,
(ii) if no certificate of title has been issued, the Crown or
other body administering the land, or
(iii) in the case of Metis land, the person registered in the
Metis Settlements Land Registry as owner of the Metis
title pursuant to the Metis Settlements Land Registry
Regulation (AR 361/91);
(gg) "leak" means the escape of substance from a pipeline in a
manner that does not immediately impair the operation of the
pipeline;
(hh) "occupant" means
(
i) a person, other than the owner, who is in actual
possession of land,
(ii) a person who is shown on a certificate of title or by
contract as having an interest in land that confers a right
to occupy the land,
(iii) an operator granted a right of entry in respect of land
pursuant to a right of entry order under the Surface
Rights Act,
(iv) in the case of Crown land, a person shown on the
records of the department or other body administering
the land as having an interest in the land,
(
v) the holder of a permit for a coal mine, or
(vi) in the case of Metis land, a person having a right or
interest in land recorded on the Metis title register
pursuant to the Metis Settlements Land Registry
Regulation (AR 361/91);
(ii) "% SMYS" means the hoop stress level expressed as a
percentage of the specified minimum yield strength of the
pipe based on nominal wall thickness;
(jj) "polymeric" means consisting of either thermoplastic or
thermoset polymer engineering materials;
(kk) "regulatory authority" means an entity having lawful
authority respecting the regulation of pipelines in a
jurisdiction other than Alberta;
(ll) "Safety and Loss Management System" means a Safety and
Loss Management System developed under
section 14;
(mm) "temporary surface pipeline" means a pipeline installed
primarily on the ground and not to be operated for more than
12 months unless otherwise authorized;
(nn) "temporary surface pipeline for water conveyance" means a
temporary surface pipeline used only for water conveyance
and not operating at a pressure greater than 3500 kilopascals;
(oo) "temporary surface pipeline for well testing or bypass"
means a temporary surface pipeline used only for well testing
or bypass purposes and that is in continuous use for no more
than 21 days;
(pp) "Uniform Color Code" means the Uniform Color Code for
marking underground utilities established and published by
the American Public Works Association;
(qq) "Utility Safety Partners" means the non-profit corporation
called Utility Safety Partners referred to in
Part 4, formerly
called Alberta One Call, and includes any successor
organization to Utility Safety Partners.
(2) Words and expressions used but not defined in these Rules have
the meanings assigned to them in the Act and in the standards referred
to in subsection (3).
(3) A reference in these Rules to CSA Z662 or any other CSA
standard refers to the standard with the equivalent identification
number issued by CSA, as updated from time to time.
(4) For the purposes of
section 1(1)(
e) of the Act, the controlled area
(
a) a strip of land 30 metres wide on each side of the pipeline,
measured from the pipe centreline, or
(
b) the distance from the pipe centreline to the edge of the right
of way,
whichever is wider.
(5) For the purposes of
section 19 of the Act and these Rules,
(
a) a licensee who is an individual is resident in a jurisdiction if
the individual makes his or her home in and is ordinarily
present in that jurisdiction, and
(
b) a licensee that is a corporation is resident in a jurisdiction if a
director or officer of the corporation or a person employed or
retained to provide services to the corporation makes his or
her home in that jurisdiction, is ordinarily present in that
jurisdiction and is authorized to
(
i) make decisions respecting a licence for a pipeline issued
(
A) the regulatory authority in that jurisdiction, or
(
B) in the case of Alberta, the Regulator,
(ii) operate the pipeline, and
(iii) implement directions from the regulatory authority, or
in the case of Alberta, the Regulator, relating to the
pipeline.
(6) Where these Rules refer to a directive by its number or title or
both, the reference is to be considered as a reference to that directive as
published by the Regulator and amended from time to time.
Part 1
Administration
Exemption from application of Act and Rules
2(1) A pipeline, regardless of length, that is contained wholly within
the boundary of a facility surface lease or of an adjacent and abutting
facility surface lease is exempt from the application of the Act and
these Rules.
(2) A natural gas pipeline that conveys distribution specification gas at
pressures of 700 kilopascals or less and that supplies fuel or gas to a
facility, scheme or other matter authorized under the Oil and Gas
Conservation Act or the Oil Sands Conservation Act from a gas
distribution company or a gas utility is exempt from the application of
the Act and these Rules.
(3) A natural gas pipeline that
(
a) conveys, on an alternating basis, distribution specification
gas at pressures of 700 kilopascals or less to a facility,
scheme or other matter authorized under the Oil and Gas
Conservation Act or the Oil Sands Conservation Act from a
gas distribution company or a gas utility, or
(
b) supplies distribution specification gas at pressures of 700
kilopascals or less to a gas distribution company or gas utility
from a facility, scheme or other matter authorized under the
Oil and Gas Conservation Act or the Oil Sands Conservation
Act,
is exempt from the application of the Act and these Rules.
(4) A temporary surface pipeline for water conveyance is exempt from
the application of these Rules except for sections 1, 4, 7(3)(
b) and (4),
14, 15, 27 and 30(2) and (4).
(5) A temporary surface pipeline for well testing or bypass is exempt
from the application of these Rules except for sections 1, 4, 7(3)(
c) and
(4), 14, 15, 20, 23, 26(2), 27 and 30(2) and (4).
(6) Section 35 of the Act does not apply to a temporary surface
pipeline for water conveyance.
Exemption - agents
3(1) In this section, "mutual recognition agreement" means a valid
and subsisting agreement made between the Minister and a regulatory
authority of another jurisdiction for the purpose of recognizing
substantial regulatory equivalency and enabling reciprocity between
Alberta and that jurisdiction.
(2) The Regulator may, on application, grant an exemption from the
requirement under
section 19 of the Act to appoint an agent if the
licensee applying for the exemption
(
a) is resident in a jurisdiction outside Alberta that is a party to a
mutual recognition agreement and is subject to the authority
of the regulatory authority in that jurisdiction,
(
b) is in compliance with all applicable legislation in Alberta and
in the jurisdiction in which the licensee is resident and all
applicable directives, orders, decisions, directions and other
instruments of the regulatory authority referred to in clause
(
a) and of the Regulator,
(
c) provides evidence satisfactory to the Regulator that the
licensee meets, and during the time the licence is in effect
will continue to meet, the requirements under subsection (3),
and
(
d) agrees to attorn to the jurisdiction of Alberta with respect to
all matters, obligations and liabilities pertaining to licences
issued by the Regulator.
(3) An exemption under subsection (2) is subject to the condition that,
in substitution for the requirements under
section 19(2)(a), (
b) and (
c) of the Act, the licensee must have
(
a) sufficient numbers of individuals who are trained and
competent to
(
i) carry out work relating to the pipelines for which the
licensee has been granted a licence in compliance with
the requirements of all applicable legislation and all
applicable directives, orders, decisions, directions and
other instruments of the Regulator, and
(ii) respond sufficiently to incidents and emergencies,
including, without limitation, leaks and breaks,
and
(
b) representatives at a pipeline site during any construction,
testing, maintenance, repair, ground disturbance and
abandonment activities at the pipeline site who are authorized
to make decisions respecting all aspects of those activities.
(4) An exemption under subsection (2) ceases to have effect
immediately on
(
a) the licensee ceasing to meet a requirement referred to in
subsection (2)(a), (
b) or (d), or
(
b) the Regulator determining that it is no longer satisfied that
the licensee meets or will continue to meet the requirements
set out in subsection (3).
Compliance with directives
4(1) A licensee must comply with the requirements of
(
a) Directive 060, subject to
section 70(3),
(
b) Directive 077, and
(
c) Directive 088.
(2) A person using a pipeline under
section 7(3)(
b) or (
c) must comply
with the requirements of Directive 077.
(3) A person using a pipeline under
section 7(3)(
c) must comply with
the requirements of Directive 060.
(4) Unless otherwise authorized by the Regulator, a licensee, or a
person using a pipeline under
section 7(3)(
b) or (c), must manage
drilling waste in accordance with Directive 050 and Directive 058.
Notification
5(1) Unless otherwise authorized by the Regulator, a licensee who is
required to notify the Regulator under these Rules must send the notice
electronically through the Regulator's applicable electronic submission
system.
(2) Despite subsection (1), a licensee who is required to notify the
Regulator of a pipeline leak, break or contact damage must
immediately do so by telephoning the Energy and Environmental
Emergency 24-Hour Response Line or applicable contact as amended
from time to time.
Eligibility to hold a licence
6(1) An applicant must meet the licence eligibility requirements set
out in Directive 067 in order to be eligible to hold a licence under the
Act.
(2) If an applicant meets the licence eligibility requirements of
Directive 067 to the satisfaction of the Regulator, the Regulator may
grant licence eligibility subject to any restrictions, terms or conditions
the Regulator considers appropriate.
(3) If an applicant does not meet the licence eligibility requirements of
Directive 067 to the satisfaction of the Regulator, the Regulator may
refuse to grant licence eligibility.
(4) The Regulator may revoke or restrict the licence eligibility of an
applicant if the applicant fails to acquire licences under the Act within
a year of the day of the licence eligibility being granted by the
Regulator.
(5) A licensee must continue to meet the licence eligibility
requirements of Directive 067.
(6) The Regulator may restrict a licensee's eligibility to hold a licence
if a licensee does not continue to meet the licence eligibility
requirements of Directive 067.
Application for licence
7(1) Unless otherwise authorized by the Regulator, an application
under
Part 4 of the Act for a licence to construct and operate a pipeline,
including any applicable installation, must be in accordance with the
requirements of Directive 056.
(2) Unless otherwise authorized by the Regulator, and in addition to
the requirements of subsection (1), for a steam distribution pipeline
having an internal aggregate capacity greater than 0.5 cubic metres or a
pipeline having a design temperature greater than 230 degrees Celsius,
the licensee must
(
a) confirm in its application to the Regulator that the licensee
has received design registration of the pipeline and associated
fittings in accordance with the Pressure Equipment Safety
Regulation (AR 49/2006), and
(
b) obtain all required approvals from the Alberta Boilers Safety
Association (ABSA) prior to putting the pipeline into
operation.
(3) No application for a licence is required
(
a) for the replacement of parts of a pipeline or parts of an
expanded liner or freestanding liner if
(
i) the length of each individual replacement
section is less
than 100 metres, or longer in exceptional circumstances,
as the Regulator may allow,
(ii) the replacement sections are equivalent to the original
material or exceed the requirements and suitability for
the purpose of the original material,
(iii) the replaced sections of pipeline or pipeline liner are
removed, and
(iv) the replacement work is carried out wholly within the
existing right of way,
(
b) for a temporary surface pipeline for water conveyance that
conveys only group 1 water, group 2 water or group 3 water
if the pipeline meets all applicable requirements of Directive
077, and
(
c) for a temporary surface pipeline for well testing or bypass if
the pipeline meets all applicable requirements of Directive
(4) An approval is required in accordance with Directive 077 before
deploying and operating a temporary surface pipeline for water
conveyance that conveys group 2 water or group 3 water or a
temporary surface pipeline for well testing or bypass.
Survey of right of way boundaries
8(1) The applicant for a licence must ensure that right of way
boundaries for the pipeline are surveyed in accordance with the
Surveys Act.
(2) An applicant or licensee is exempt from the requirements of
subsection (1) with respect to repairs or modifications to a pipeline
within the existing right of way unless the repairs or modifications
require an additional right of way.
(3) The Regulator may exempt an applicant or licensee from the
requirements of subsection (1) or (2) in exceptional circumstances.
Notice of construction commencement
9(1) Licensees must provide notice of the commencement of
construction to the Regulator at least 24 hours but not more than 14
days before the commencement of any construction of a pipeline.
(2) The commencement of construction in subsection (1) includes
(
a) the fabrication, assembly or installation of a permitted or
licensed pipeline,
(
b) the fabrication, assembly, installation or modification of a
pipeline or part of a pipeline as approved in a licence
amendment,
(
c) the installation of a freestanding liner or expanded liner, or
the in-situ application of thin-film internal coating, as
approved in a licence amendment, and
(
d) the resumption of delayed construction following a licence
expiry and reapplication.
Notice or application in case of delay or
failure to complete construction
10(1) A licensee must notify the Regulator if the pipeline construction
has commenced but there is a delay of 3 months or more in the
construction of the pipeline.
(2) A licensee must apply to the Regulator for approval in accordance
with Directive 056 if
(
a) the licence has expired or will expire without the pipeline
construction having been commenced, or
(
b) the construction of the pipeline will not be completed.
Emergency response plan
11(1) In this section, "emergency response plan" means a
comprehensive plan to protect the public that includes criteria for
assessing an emergency and procedures for mobilizing response
personnel and agencies, establishing communications and ensuring
coordination of the emergency response.
(2) A licensee of a pipeline must prepare and maintain an emergency
response plan in accordance with the requirements of Directive 071.
Pipeline records and documents
12(1) A licensee must maintain records and documents pertaining to
the design, materials, construction, commissioning, operation,
maintenance, repair, engineering assessments and decommissioning of
pipelines in accordance with CSA Z662.
(2) All pipeline records and documents required under subsection
(1) must be provided to the Regulator on request in a manner and form
acceptable to the Regulator.
Transfer of records
13(1) On transfer of ownership of a pipeline, a licensee must transfer
to the successor licensee all available and existing records and
documents referred to in
section 12(1) applicable to the pipeline.
(2) The successor licensee must incorporate all records and documents
transferred under subsection (1) into its Safety and Loss Management
System and Integrity Management Program and determine if there is
additional work or information required to effectively manage the
pipeline.
(3) If relevant records or documents referred to in
section 12(1) are
lost, damaged, destroyed or incomplete, the successor licensee must
conduct an engineering assessment and be able to demonstrate that the
pipeline is fit for service.
Safety and Loss Management System
14(1) A licensee, or a person using a pipeline under
section 7(3)(
b) or
(c), must develop and implement a documented Safety and Loss
Management System for its pipeline as described in Annex A of CSA
Z662.
(2) The Safety and Loss Management System must include
(
a) abandoned pipelines identified under
section 25 of the Act
and these Rules,
(
b) temporary surface pipelines, and
(
c) pipelines that are not in active flowing service.
(3) The Regulator may, on request, allow a licensee, or a person using
a pipeline under
section 7(3)(
b) or (c), to use a Safety and Loss
Management System that is structured differently than described in
Annex A of CSA Z662 if the Safety and Loss Management System is
already developed and the licensee or the person using the pipeline
under
section 7(3)(
b) or (
c) can demonstrate to the Regulator that the
system achieves an equivalent level of protection as described in
Annex A of CSA Z662.
(4) On request from the Regulator, a licensee, or a person using a
pipeline under
section 7(3)(
b) or (c), must be able to demonstrate to the
Regulator that the Safety and Loss Management System of the licensee
or the person using the pipeline under
section 7(3)(
b) or (c), as the case
may be, provides for the protection of people, the environment and
property and includes a continuous improvement process as required in
CSA Z662.
(5) A licensee, or a person using a pipeline under
section 7(3)(
b) or
(c), must provide any records and documents related to the Safety and
Loss Management System developed under this
section to the
Regulator on request in a manner and form acceptable to the
Regulator.
Integrity Management Program
15(1) A licensee, or a person using a pipeline under
section 7(3)(
b) or
(c), must develop and implement a documented Integrity Management
Program for its pipeline as described in Annex N of CSA Z662.
(2) The Integrity Management Program must include programs for
(
a) abandoned pipelines according to
section 25 of the Act and
these Rules,
(
b) temporary surface pipelines, and
(
c) pipelines that are not in active flowing service.
(3) On request from the Regulator, a licensee, or a person using a
pipeline under
section 7(3)(
b) or (c), must be able to demonstrate to the
Regulator that its Integrity Management Program provides safe,
environmentally responsible and reliable pipeline service and is being
evaluated at appropriate set intervals.
(4) A licensee, or a person using a pipeline under
section 7(3)(
b) or
(c), must provide any records and documents related to the Integrity
Management Program to the Regulator on request in a manner and
form acceptable to the Regulator.
Financial information
16(1) A licensee must provide financial information to the Regulator,
as and when directed by the Regulator, for the purposes of
(
a) assessing the licensee's eligibility for holding a licence,
(
b) administering the liability management programs set out in
directives by the Regulator, and
(
c) ensuring the development of safe, orderly and
environmentally responsible energy resources and their
closure in Alberta.
(2) Any information provided under this
section must be kept
confidential by the Regulator for a period of 5 years.
Part 2
Materials and Design
Materials to be provided to Regulator
17(1) A licensee who is required to
(
a) take and analyze a representative sample of a substance being
conveyed by a pipeline under
section 34(1) of the Act, or
(
b) make inspections, investigations or tests of a pipeline under
section 34(2) of the Act
must, on request, submit to the Regulator the analysis, inspections,
investigations or tests in a manner and form acceptable to the
Regulator.
(2) The inspections, investigations or tests referred to in subsection
(1)(
b) may include
(
a) representative physical samples of materials used in the
construction or repair of a pipeline,
(
b) cut-outs from a pipeline, or
(
c) representative physical samples of defective materials.
CSA standards
18(1) Except as otherwise specified by these Rules, the minimum
requirements for the design, materials, construction, commissioning,
operation, maintenance, repair, engineering assessments and
decommissioning of pipelines are set out in CSA Z662.
(2) A licensee wishing to incorporate materials manufactured in
accordance with a previous edition of a CSA Z245 series standard
other than those referred to in the current CSA Z662 may use those
materials if an engineering assessment demonstrates equivalency with
the current CSA Z245 series standard.
Approval of non-standard materials or methods
19(1) Despite
section 18, if an applicant or licensee proposes to use a
polymeric or composite material for pipeline construction or repair,
other than those that are included in CSA Z662 or previously reviewed
and authorized for use by the Regulator, the applicant or licensee must
provide to the Regulator an engineering assessment concerning the
material and its potential application to allow the Regulator to
determine whether the material is acceptable for the proposed use.
(2) Despite
section 18, if an applicant or licensee proposes to use
pipeline materials, pipeline components, joining methods, construction
methods, repair methods or maintenance methods, other than those that
are included in CSA Z662 or previously reviewed and authorized for
use by the Regulator, the applicant or licensee must provide to the
Regulator an engineering assessment concerning the pipeline material,
pipeline components, joining methods, construction methods, repair
methods or maintenance methods and their potential application to
allow the Regulator to determine whether they are acceptable for the
proposed use.
(3) If the Regulator is satisfied that the materials, components or
methods referred to in either subsection (1) or (2) are acceptable for
the proposed use, the Regulator may approve the use of the materials,
components or methods, subject to such restrictions on or conditions
regarding their use as the Regulator considers necessary.
Limits on polymeric or composite pipe
20(1) Unless authorized by the Regulator, a licensee, or a person
using a pipeline under
section 7(3)(c), must not install polymeric or
composite pipe as either freestanding liner inside another pipeline or as
a freestanding pipe for the purpose of conveying natural gas containing
more than 10 moles of hydrogen sulphide gas per kilomole of natural
gas.
(2) A licensee, or a person using a pipeline under
section 7(3)(c),
installing polymeric or composite pipe or changing the service
conditions of such installed pipe must ensure the pipe employed is
suitable for the intended service conditions and intended service
according to the pipe manufacturer or its representative or, in the
absence of an available pipe manufacturer or representative, must
verify the suitability for use by conducting an engineering assessment.
Design for maintenance, inspection and purging
21(1) Unless otherwise authorized by the Regulator, all new pipelines
must be constructed in a manner that can accommodate the passage of
maintenance, inspection and purging pigs if pigging is
(
a) determined to be necessary by the licensee's Integrity
Management Program, or
(
b) required by CSA Z662.
(2) A new pipeline that may require pigging as determined by the
licensee's Integrity Management Program must either be initially
constructed with pigging equipment included or be constructed in a
manner that can readily accept the addition of pigging equipment.
(3) Where a change in operating conditions or an addition or
modification is being made to an existing pipeline, the licensee must
reassess whether it is necessary for the pipeline to accommodate the
passage of maintenance, inspection and purging pigs, either in
accordance with the licensee's Integrity Management Program or
under CSA Z662, and must implement the passage of maintenance,
inspection and purging pigs accordingly prior to operation under the
new operating conditions.
Pipeline maintenance pigs
22 Where a licensee determines that pigging is required under its
Integrity Management Program, the licensee must ensure that pigs
used for pipeline cleaning, corrosion control and purging are
appropriate for the intended purpose, properly sized and replaced if
worn beyond limits specified in the Integrity Management Program.
Emergency shutdown devices and check valves
23(1) A licensee, or a person using a pipeline under
section 7(3)(c),
must ensure that a pipeline conveying a substance that under operating
conditions contains a separate gas phase having gas containing more
than 10 moles of hydrogen sulphide gas per kilomole of natural gas, or
any lesser hydrogen sulphide content that the Regulator may stipulate,
is equipped with automatically actuated emergency shutdown devices
or check valves.
(2) A licensee, or a person using a pipeline under
section 7(3)(c), must
conduct an engineering assessment to define the pipeline operating
conditions and the closure parameters of the automatically actuated
emergency shutdown devices or check valves referred to in subsection
(1) to ensure the release volume used in calculating the emergency
planning zone in the event of a pipeline leak or break is as low as
reasonably practicable.
(3) A licensee, or a person using a pipeline under
section 7(3)(c), must
ensure that the automatically actuated emergency shutdown devices or
check valves referred to in subsection (1)
(
a) isolate the pipeline into segments whose volumes are in
accordance with the emergency response plan prepared under
section 11, and
(
b) automatically close as defined by the engineering assessment
required in subsection (2) if a pipeline leak or break occurs.
(4) A licensee, or a person using a pipeline under
section 7(3)(c), must
ensure that the automatically actuated emergency shutdown devices
referred to in subsection (1)
(
a) close on the failure of any control or operating component,
(
b) remain closed once the devices have closed due to actuation
or failure, and
(
c) require on-site human intervention to reopen once they have
closed unless they were closed due to a planned pipeline
shutdown.
(5) A licensee, or a person using a pipeline under
section 7(3)(c), must
not allow the pipeline or the automatically actuated emergency
shutdown devices to operate outside of the conditions defined within
the engineering assessment conducted under subsection (2).
(6) If the licensee, or a person using a pipeline under
section 7(3)(c),
determines that the pipeline or the automatically actuated emergency
shutdown devices could be operating outside of the conditions defined
by the engineering assessment conducted under subsection (2), the
licensee, or the person using a pipeline under
section 7(3)(c), must shut
down the pipeline until
(
a) the pipeline and the automatically actuated emergency
shutdown devices can be operated within the defined
conditions, or
(
b) the licensee, or the person using a pipeline under
section
7(3)(c), completes an engineering assessment, as specified in
subsection (2), and revises the emergency planning zone, as
required by Directive 071.
(7) Unless otherwise authorized by the Regulator, a licensee, or a
person using a pipeline under
section 7(3)(c), must maintain a record
of the current engineering assessment conducted under subsection
(2) and the actions taken under subsection (6) until the pipeline is
abandoned.
(8) A licensee, or a person using a pipeline under
section 7(3)(c), must
conduct all preventative maintenance required to ensure operability of
the automatically actuated emergency shutdown devices and check
valves referred to in subsection (1) and maintain a record of all
preventive maintenance.
(9) A licensee must conduct an annual inspection, assessment and test,
with a maximum interval of 18 months between such activities, of the
automatically actuated emergency shutdown devices and check valves
referred to in subsection (1) to ensure that the devices are operating as
required and maintain a record of the inspection, assessment and test.
Control systems in blended gas streams
24(1) Unless otherwise authorized by the Regulator, where gas
streams are blended for the purpose of maintaining a lower hydrogen
sulphide content in the final blended gas stream, and any inlet stream
conveys gas containing hydrogen sulphide, the licensee must ensure
that there are 2 independent safety systems to prevent a greater
hydrogen sulphide content in the blended gas stream than permitted in
the licence.
(2) A licensee must ensure that one of the 2 independent safety
systems referred to in subsection (1) provides, as a minimum, the
process control to achieve the blend ratio and that the other system
provides, as a minimum, monitoring and automatic shutdown.
(3) A licensee must
(
a) conduct an annual inspection, assessment and test, with a
maximum interval of 18 months between such activities, of
the 2 independent safety systems referred to in subsection
(1) to ensure that the safety systems are operating as required,
and
(
b) maintain a record of the inspection, assessment and test
referred to in clause (a).
Equipment pressure ratings
25 A licensee must ensure that any new construction or modification
of a pipeline complies with the following:
(
a) all components have pressure ratings equal to or greater than
the licensed maximum operating pressure and account for the
maximum design temperature of the pipeline;
(
b) the licensed maximum operating pressure for any pipeline
components, if manufactured using other non-CSA standards
as allowed by CSA Z662, must not exceed the values
expressed for the corresponding pressure nominal (PN) class
designations as expressed in the CSA Z245 series standards,
unless otherwise authorized by the Regulator.
Stress level limitations
26(1) For pipelines designed to convey gas with a content of more
than 10 moles of hydrogen sulphide gas per kilomole of natural gas,
the design stress levels may not be greater than 60% SMYS for all
underground and above-ground piping.
(2) For temporary surface pipelines, including temporary surface
pipelines for well testing or bypass that are used under
section 7(3)(c),
designed to convey gas with a content of more than 10 moles of
hydrogen sulphide gas per kilomole of natural gas, the design stress
levels may not be greater than 50% SMYS.
Maximum noise levels
27 A licensee, or a person using a pipeline under
section 7(3)(
b) or
(c), must operate pipeline facilities and conduct pipeline construction
and operations in accordance with the maximum noise level limitations
specified in Directive 038.
Pipeline crossing highway or road
28(1) When constructing a pipeline across a road, highway right of
way or road allowance, the licensee must apply the CSA Z662 pipeline
design requirements applicable to the crossing for the full width of the
road, highway right of way or road allowance.
(2) Prior to the initiation of any construction related to the building,
improving or widening of a road or highway over an existing pipeline,
or extending a road or highway right of way over an existing pipeline,
the pipeline at such locations must either be upgraded or otherwise
meet the requirements of CSA Z662 respecting crossings of existing
pipelines.
Minimum earth cover
29(1) Unless otherwise required by the Regulator, and subject to
subsection (2), the minimum earth cover for any operating or
discontinued pipeline must be the greater of
(
a) the earth cover specified in CSA Z662,
(
b) the applicable specified minimum of
(i) 1.4 metres within the entire right of way of a highway,
(ii) 1.2 metres within the entire right of way of a road, and
(iii) 0.8 metres in any other place,
and
(
c) the earth cover necessary to sufficiently protect the pipeline,
as demonstrated by an engineering assessment.
(2) Unless otherwise required by the Regulator, if the earth cover
permitted by the construction standards and regulatory requirements in
place at the time of a pipeline's construction was lesser than the one
referred to in subsection (1), and an engineering assessment
demonstrates the existing cover sufficiently protects the pipeline in its
present situation, that earth cover is acceptable.
(3) In addition to subsections (1) and (2), for pipelines constructed
after the Code of Practice for Pipelines and Telecommunication Lines
Crossing a Water Body came into force, the minimum earth cover for
any pipeline must comply with the applicable requirements of the
Code of Practice for Pipelines and Telecommunication Lines Crossing
a Water Body for ensuring scour protection of pipelines at pipeline
crossings of a water body.
(4) Where the earth cover for a pipeline does not meet the minimum
requirements under this section, a licensee must address any deficiency
by lowering the pipeline, adding the required earth cover or
implementing additional protective actions as may be allowed by the
applicable legislation.
(5) A licensee must ensure that any abandoned pipeline has adequate
earth cover so that
(
a) the pipeline does not interfere with the intended usage of any
land or water body it crosses, and
(
b) the earth cover complies with any applicable requirements
under the Water Act.
(6) Where a licensee becomes aware that any portion of a licensed
pipeline is exposed for any reason other than a planned ground
disturbance, the licensee must
(
a) immediately advise the appropriate regional field centre of
the Regulator, and
(
b) restore the earth cover as required under this
section or
remove the exposed pipeline.
Installing surface pipelines
30(1) A licensee who intends to install a surface pipeline must do so
in accordance with the requirements set out in this section,
section
26(2) and Directive 056.
(2) A licensee, or a person using a pipeline under
section 7(3)(
b) or
(c), must install
(
a) a form of pressure-relieving device if any possibility of a
pressure increase above the allowable maximum operating
pressure exists due to a rise in ambient air temperature or
solar heating,
(
b) a system to allow for adequate expansion or contraction due
to temperature change,
(
c) temperature monitoring equipment if the pipeline material
has temperature limitations,
(
d) suitable restraints to adequately control lateral or vertical
movement, and
(
e) any other safety or operational systems as the Regulator
considers appropriate.
(3) A licensee must bury the pipeline at all road and trail crossings and
must install pipeline warning signs at the point of pipeline entry and
exit of each crossing.
(4) A licensee, or a person using a pipeline under
section 7(3)(
b) or
(c), must take additional precautions, including adding extra pipeline
warning signs or providing other warnings to indicate the presence of a
surface line when
(
a) equipment may be operating in the vicinity of the pipeline,
(
b) off-road vehicular traffic may endanger the pipeline, or
(
c) any conditions may obscure or endanger the pipeline.
Operating pressure
31(1) Unless otherwise authorized by the Regulator, a licensee must
design and maintain each pipeline segment in a manner suitable for the
maximum operating pressure permitted in the licence.
(2) Unless otherwise authorized by the Regulator, the operating
pressure of a pipeline at all points must not exceed the licensed
maximum operating pressure except as allowed by CSA Z662.
(3) Where 2 or more pipelines or pipeline segments having different
licensed maximum operating pressures are connected and the
difference between the licensed maximum operating pressures is
greater than 5% of the lowest licensed maximum operating pressure,
the licensee must either
(
a) amend the licensed maximum operating pressure as
necessary to not exceed a difference of 5% of the lowest
licensed maximum operating pressure, or
(
b) install a pressure control system and overpressure protection
system in accordance with CSA Z662 to ensure that the
lower licensed maximum operating pressure pipeline is
operated in accordance with the maximum operating pressure
permitted in its licence.
(4) The requirements in subsection (3) do not apply
(
a) if the pipeline incorporates point-specific pressure design due
to varying elevation,
(
b) where the pressure source or sources, with or without
pumping or compression, cannot exceed the lowest licensed
maximum operating pressure of any of the connected
pipelines, or
(
c) where the pressure source or sources, with or without
pumping or compression, can exceed the lowest licensed
maximum operating pressure of any of the connected
pipelines, but each pressure source is equipped with
individual pressure control and overpressure protection in
accordance with CSA Z662 that prevents exceeding the
lowest licensed maximum operating pressure of any of the
connected pipelines.
(5) Unless otherwise authorized by the Regulator, the maximum
operating pressure of a
section of a pipeline must be determined using
the test pressure recorded or calculated at the highest point in the
section.
Part 3
Pressure Testing
Placing pipeline into operation
32(1) Unless otherwise authorized by the Regulator, a licensee must
not place a newly constructed or modified pipeline into operation until
a satisfactory pressure test has been completed in accordance with
CSA Z662, as applicable, and these Rules.
(2) Unless otherwise authorized by the Regulator, a licensee resuming
the operation of a pipeline from licensed discontinuance, abandonment
or a period of non-use must confirm pipeline integrity by conducting
an engineering assessment, inspection or a pressure test in accordance
with CSA Z662 and these Rules.
(3) Unless otherwise authorized by the Regulator, a licensee returning
a pipeline to service following repair must confirm pipeline integrity
by conducting an engineering assessment, inspection or a pressure test
in accordance with CSA Z662 and these Rules.
Notice to Regulator
33(1) A licensee must notify the Regulator at least 48 hours before
the commencement of any pressure test.
(2) Despite subsection (1), no notice is required to conduct a pressure
test that does not exceed the licensed maximum operating pressure of
the pipeline.
(3) A licensee must immediately notify the Regulator of any leak or
break that occurs in a pipeline during any pressure test.
Conditions for pressure testing
34(1) A licensee must pressure test a pipeline that will be buried
during operation with the full depth of earth cover applied other than at
the bell-holes where joints are intended to be visually inspected or the
test heads.
(2) A licensee is exempted from the requirements in subsection (1) if
the pipeline is a pull
section being pre-tested on the surface of the land,
prior to trenchless or open cut installation techniques and is to be
followed by a pressure test after final installation.
Regulator's direction on pressure testing
35(1) The Regulator may specify the maximum length of pipe to be
pressure tested in any pressure test.
(2) The Regulator may prohibit a pressure test if the Regulator
believes it to be unsafe or unsuitable.
(3) The Regulator may require a pipeline to be retested if in the
opinion of the Regulator it may be unsafe for the pipeline to continue
to operate.
Recording pressure test results
36(1) A licensee must record the data during a pressure test and retain
the record or chart of the results in accordance with the licensee's
Integrity Management Program and Safety and Loss Management
System.
(2) A licensee's record or chart of a pressure test must be continuous
and legible over the full test period, regardless of the type of recording
equipment used, and include start and end dates and times, a
continuous pipeline temperature trace, a legal land description of to
and from locations, the licence number, the segment number and any
additional information required by CSA Z662 and the Regulator.
(3) A licensee may use electronic pressure-recording and charting
instruments if
(
a) a permanent copy of the pressure test data is retained by the
licensee in a manner accessible to the Regulator on request,
and
(
b) the sampling rate, resolution and instrument range are
sufficient to properly record the expected data.
(4) Each pressure-recording instrument must be periodically calibrated
in accordance with CSA Z662, and the Regulator may require
verification of such calibration.
Unsatisfactory pressure test
37 If evidence of a satisfactory pressure test is not provided to the
Regulator on request, or the Regulator does not find the test
satisfactory, the Regulator may order that the pipeline be
(
a) depressurized,
(
b) purged, if necessary, and
(
c) pressure tested as directed by the Regulator.
Minimum test pressure
38 For a pressure test, a licensee must use a minimum test pressure of
(
a) not less than 700 kilopascals for any pipeline, unless the
Regulator approves a lower test pressure, and
(
b) not less than 1.4 times the maximum operating pressure for
gas pipelines conveying gas containing more than 10 moles
of hydrogen sulphide gas per kilomole of natural gas.
Pressure testing using liquid test media other than fresh water
39 A licensee intending to pressure test a pipeline using a liquid test
media other than fresh water must comply with the liquid test media
pressure testing requirements of Directive 077.
Pressure testing using gaseous test media
40 A licensee intending to pressure test a pipeline using air or other
gaseous test media must comply with the gaseous media pressure
testing requirements of Directive 077.
Duration of pressure test
41 A licensee, in exceptional circumstances, may apply to the
Regulator to pressure test a pipeline or
section of a pipeline for a
shorter period than the minimum specified in CSA Z662.
Part 4
Ground Disturbance
No fees for ground disturbance
42 A licensee must locate and mark its pipeline, execute consents and
approvals required for ground disturbance and perform supervision and
inspections of ground disturbance as required by this Part without
charging any fee or requiring the party undertaking the ground
disturbance to pay for expenses.
Ground disturbance approval
43(1) No ground disturbance may be undertaken in the right of way of a
pipeline until an approval specified in
section 42 of the Act is obtained.
(2) No person shall undertake a ground disturbance within 5 metres of
the centreline of a pipeline where there is no pipeline right of way until
an approval is obtained
(
a) from the licensee of the pipeline, or
(
b) from the Regulator, if approval cannot reasonably be
obtained from the licensee.
(3) A request for an approval under this
section is to be made
(
a) to the licensee, who must respond in writing within 21 days
from the date of the request, or
(
b) to the Regulator, if the licensee is unable to respond to the
request, who may grant approval on such terms and
conditions as the Regulator considers appropriate in the
circumstances.
Damage prevention service
44 Every licensee must register with the Utility Safety Partners'
damage prevention service and must
(
a) register all of its licensed pipeline with Utility Safety
Partners regardless of the operational status of the pipeline,
(
b) for new construction, register the pipeline prior to putting it
into operation, and
(
c) update the registered inventory as often as necessary to
ensure the licensee's pipeline data is accurate.
Preparing for ground disturbance
45(1) For the purposes of
section 32(1)(a)(i)(
B) of the Act, the
distance from the perimeter of the area in which a person proposes to
undertake a ground disturbance within which the person must take all
precautions reasonably necessary to ascertain whether a pipeline exists
before commencing any work, operation or activity is 30 metres.
(2) A person proposing to undertake a ground disturbance within
either the controlled area of a pipeline or within the right of way of a
pipeline must notify Utility Safety Partners at least 3 days and not
more than 10 days, excluding Saturdays, Sundays and holidays, before
commencing the ground disturbance to allow Utility Safety Partners to
notify the licensee of any buried pipeline of the intent to disturb the
ground and request that the licensee identify and mark the location of
the pipeline.
(3) Should Utility Safety Partners be unable to notify the licensee of
any buried pipeline, the person proposing to undertake the ground
disturbance must make reasonable efforts to directly notify the licensee
of the pipeline to request that the licensee identify and mark the
location of the pipeline.
Locating and marking of pipelines
46(1) A licensee who has been given notice of a proposed ground
disturbance in the controlled area or right of way of its pipeline must,
before the commencement of the ground disturbance, accurately locate
and mark on the surface of the ground the horizontal position and
alignment of the pipeline with clearly distinguishable warning signs
and markers at adequate intervals in accordance with the Uniform
Color Code, and provide documentation of the markings to the person
conducting the ground disturbance.
(2) The locating and marking referred to in subsection (1) must be
provided no later than 3 days, excluding Saturdays, Sundays and
holidays, after the licensee is notified of the proposed ground
disturbance, unless a longer period is necessary due to locator
availability constraints, or as the licensee and the person conducting
the ground disturbance agree otherwise.
(3) If the person proposing to undertake the ground disturbance wishes
to carry out the locating and marking of the pipeline in accordance
with the requirements under subsection (1) and obtains the prior
agreement of the licensee to do so, the licensee may delegate its
responsibility and associated expenses under subsection (1) and the
supervision of the ground disturbance in the absence of the licensee to
that person.
(4) If the person conducting the ground disturbance requests the
locating and marking of the pipeline by contacting Utility Safety
Partners and also by attempting to contact the licensee directly, and
neither effort succeeds, the person conducting the ground disturbance
is responsible for arranging for the accurate locating and marking of
the pipeline in accordance with subsection (1) and for the supervision
of the ground disturbance in the absence of the licensee.
(5) The person conducting the ground disturbance must
(
a) keep all pipeline warning signs or markers referred to in
subsection (1) visible and legible and in their original
position for the duration of the ground disturbance, and
(
b) in the event that any warning sign, marking or marker is
moved or becomes illegible,
(
i) restore or re-mark it if the original position is exactly
known, or
(ii) request for new locating and marking if the original
position is uncertain.
(6) Despite subsection (1), alternative methods of locating and
marking a pipeline may be used if the licensee and the person
conducting the ground disturbance agree.
(7) The locating and marking referred to in subsection (1) is not
required if
(
a) the ground disturbance is proposed to be undertaken in the
controlled area outside the right of way of an existing
pipeline,
(
b) the right of way or pipeline is clearly separated from the
proposed ground disturbance by a highway, road or other
visible improvement, and
(
c) the licensee of any affected pipeline agrees to the exemption
from the requirements under subsection (1).
(8) The requirements under subsections (1) and (2) do not apply if the
Regulator is satisfied that
(
a) a ground disturbance is undertaken in connection with the
restoration of essential public services in an emergency or
containment of an environmental emergency, and
(
b) the licensee of any affected pipeline agreed to alternative
notification, location and excavation procedures to ensure the
safe excavation of the pipeline.
Supervision of ground disturbance
47 A licensee of an existing pipeline who has been notified under
section 32(1)(
b) of the Act of a proposed ground disturbance must
(
a) have a representative inspect the pipeline before the
commencement of the ground disturbance to ensure that the
locating and marking referred to in
section 46(1) have been
properly carried out,
(
b) if the ground disturbance is within the right of way, ensure
that its representative on-site at the time of the ground
disturbance has a copy of the written approval for the ground
disturbance in the representative's possession,
(
c) ensure that its representative is certified in supervisory level
ground disturbance, and
(
d) carry out, document and retain any inspections of the ground
disturbance that are necessary to ensure the continued safety
of the pipeline.
Control of access over right of way
48(1) Before commencing a ground disturbance in the controlled
area of a pipeline where uncontrolled access over the pipeline by
equipment may cause damage to the pipeline, the person conducting
the ground disturbance must consult with the licensee and install any
access controls needed to protect existing pipelines.
(2) Before commencing a ground disturbance referred to in subsection
(1), the licensee and the person conducting the ground disturbance
must determine and agree on the location of crossings and the
precautions to be taken to protect pipelines from damage during
ground disturbance.
Vehicles crossing pipeline
49(1) Except where otherwise provided in this section, no person
shall operate a vehicle or equipment across a pipeline at a point that is
not within the upgraded and traveled portion of a highway or public
road without first obtaining consent from the licensee of the pipeline.
(2) A person seeking consent in subsection (1) must notify the
licensee at least 7 days, not including Saturday, Sunday or holidays,
before the proposed crossing.
(3) On receiving notification under subsection (2), a licensee must
respond to the person proposing the crossing within 7 days, not
including Saturday, Sunday or holidays, and the response must include
any precautionary measures that must be applied to safeguard the
pipeline from potential damage before the crossing is made.
(4) The consent of the licensee under subsection (1) is not required for
a vehicular crossing by
(
a) a vehicle or equipment designed to minimize ground
pressure,
(
b) a vehicle used for agricultural operations,
(
c) an off-highway vehicle as defined in
section 117(a)(iii) to
(viii) of the Traffic Safety Act, or
(
d) a commercial vehicle or a private passenger vehicle as
defined in the Traffic Safety Act, having a nominal chassis
rating of not greater than 2 tonnes.
Safety of adjacent pipeline
50 The Regulator may require that an existing pipeline located
adjacent to a ground disturbance in the controlled area of the pipeline
be depressurized, operated at a reduced pressure or otherwise protected
throughout the period of the ground disturbance.
Exposing pipeline
51(1) When a ground disturbance approaches within 5 metres of a
pipeline, the person conducting the ground disturbance must expose
the existing pipeline using hand excavation methods until positive
identification and orientation of the pipeline is achieved, and before
any further mechanical excavation may continue.
(2) If hand excavation of polymeric or composite pipelines is being
conducted by high-pressure water or air excavation methods, those
methods and procedures must be in accordance with the pipeline
manufacturer's recommendations or industry best practices, as
available, and must be acceptable to the licensee of the existing
pipeline.
(3) Under this section, at the time the pipeline is being exposed, either
a representative of the licensee of the existing pipeline or a designated
delegate the licensee agreed to accept, who meets the requirements of
section 47(c), must be present.
(4) Despite subsection (1) and subject to subsection (5), an existing
pipeline does not need to be fully exposed if
(
a) the existing pipeline is located, marked and inspected in
accordance with sections 46(1) and 47, and hand excavation
to a distance of 5 metres on each side of the centreline of the
marked position and to a depth at least 0.6 metres greater
than that required for the ground disturbance has not exposed
the pipeline,
(
b) the position of the existing pipeline has been verified to the
satisfaction of the licensee of the existing pipeline by
comparison with recorded measurements of the pipeline
taken during a previous exposure,
(
c) the proposed ground disturbance will be parallel to and
within 5 metres of an existing pipeline, in which case the
pipeline must be exposed at intervals along the pipeline, with
the length of the intervals being at the discretion of the
licensee of the existing pipeline, or
(
d) in the case of a trenchless excavation technique, the drill or
bore path is confirmed during the drilling process to be more
than 5 metres deeper than the confirmed depth of the existing
pipeline.
(5) After an existing pipeline has been exposed in accordance with
this section, no mechanical excavation equipment shall be used within
0.6 metres of the pipeline or within any distance beneath a pipeline,
except under the direct supervision of either a representative of the
licensee of the existing pipeline or a designated delegate the licensee
agreed to accept, who meets the requirements of
section 47(c).
(6) Where a ground disturbance is conducted using trenchless
excavation techniques and the intended tool path is expected to pass
within 5 metres of the existing pipeline, that pipeline must be first
exposed to allow for its identification and confirmation of direction
and depth, and to allow for confirmation that the trenchless tool path
does not encroach on and endanger the pipeline.
(7) For the purpose of subsection (6), for a trenchless excavation
crossing the path of the existing pipeline, the hand excavation must
(
a) be located within 5 metres of the existing pipeline,
(
b) extend to a depth of at least one metre deeper than the
existing pipeline,
(
c) run parallel to the existing pipeline for a distance of at least 2
metres on each side of the intended tool path, and
(
d) be of adequate width to allow for effective visual monitoring
of the tool path.
(8) For the purpose of subsection (6), for a trenchless excavation
running parallel to, or otherwise not crossing the path of the existing
pipeline, the hand excavation must
(
a) run parallel to and be offset from the existing pipeline,
(
b) extend to a depth of at least one metre deeper than the
existing pipeline,
(
c) be located between the intended tool path and the existing
pipeline,
(
d) be installed at intervals adequate to identify any critical
deviation of the tool from the intended tool path, and
(
e) be of adequate width and length to monitor for deviation of
the tool path.
(9) If a pipeline is to be exposed by the licensee of the pipeline, the
licensee may make a written request to the Regulator for approval to
use alternate pipeline exposure methods and procedures in exceptional
situations.
Inspection prior to backfilling
52 A person undertaking a ground disturbance who exposes any part
of a pipeline must notify the licensee at least 24 hours before
backfilling the pipeline, and on being so notified, a representative of
the licensee who meets the requirements of
section 47(
c) must inspect
without delay the exposed part of the pipeline before backfilling to
ensure that no damage has occurred.
Part 5
Warning Signs
Location of pipeline warning signs
53 A licensee must install pipeline warning signs as follows:
(
a) at each side of the crossing where a pipeline crosses
(
i) a highway, road, railway, irrigation canal, or
(ii) a creek, stream or river where water is present
year-round;
(
b) where a pipeline right of way meets the right of way of a
highway, road or railway, on the common boundary of the
rights of way but not within the right of way of the highway,
road or railway;
(
c) where a pipeline is located in a ditch or unpaved area and
running parallel to the right of way of a highway or road, at
intervals that clearly and continuously mark the location of
the pipeline;
(
d) where the pipeline is conveying HVP products in an urban
area, at intervals that will clearly and continuously mark the
location of the pipeline.
Installation of pipeline warning signs
54 Pipeline warning signs required by
section 53 must be installed
(
a) prior to the commencement of operation of the pipeline,
(
b) in accordance with any of the formats set out in
Schedule 1
that is consistent for the entire pipeline under the licence,
(
c) within the land acquired for the pipeline and with writing
facing towards the most likely point of viewing,
(
d) no more than 0.3 metres from a fence line, if one exists,
(
e) as close to the centreline of the pipeline as reasonable
without risking striking the pipeline,
(
f) so that each sign is fully visible,
(
g) as a freestanding structure not attached to any structure other
than fencing surrounding the licensee's equipment or facility,
and
(
h) without indicating on the sign that a pipeline is abandoned.
Maintenance of pipeline warning signs
55 A licensee must, for all pipelines, including abandoned pipelines,
(
a) replace or restore any pipeline warning sign that becomes
defaced, illegible, missing or destroyed,
(
b) update the information on the sign when necessary, either by
replacing the sign or applying durable permanent adhesive
decals,
(
c) in the event of a change to the emergency telephone number,
update the signs before the displayed phone number becomes
invalid,
(
d) in the event of a change to any other information as required
by
Schedule 1, update the signs within 180 days of the
change of information, and
(
e) where a pipeline or part of a pipeline has been removed,
remove any existing warning signs applicable to that area.
Alternate signage
56 Despite
section 54, a licensee may request, in exceptional
circumstances, from the Regulator permission to install warning signs
other than in accordance with
Schedule 1.
Temporary pipeline warning signs
57(1) Despite
section 54, a licensee may install temporary pipeline
warning signs not in accordance with
Schedule 1 during surface
restoration activities.
(2) The temporary signs installed under subsection (1) must be
replaced with permanent signs in accordance with
Schedule 1 as soon
as restoration activities are completed.
HVP product
58 Warning signs for a pipeline conveying HVP product must clearly
indicate the name of the highest vapour pressure product that may be
conveyed in accordance with
Schedule 1.
Group pipeline signs
59(1) A licensee may install group pipeline warning signs for a group
of pipelines in the same right of way or adjoining rights of way, rather
than a separate sign for each pipeline, if
(
a) the licensee is the same for each pipeline in the group,
(
b) each pipeline in the group conveys the same product,
(
c) the warning sign, in accordance with
Schedule 1, identifies
that there are other pipelines close by, including at what sides
of the sign the pipelines are located, and
(
d) none of the pipelines in the group convey HVP product or
gas containing more than 10 moles of hydrogen sulphide gas
per kilomole of natural gas.
(2) The warning signs referred to in subsection (1)
(
a) must be placed at both sides of the right of way or adjoining
rights of way containing the group of pipelines,
(
b) must not be more than 60 metres apart, and
(
c) must be placed at each side of the crossing.
Identification of pipeline installations
60(1) A licensee must install pipeline warning signs in accordance
with
Schedule 1 adjacent to all pipeline installations, including meter
regulator stations and regulator stations, valve stations, field manifolds
and line heaters.
Schedule 2 at the entrance to any gas compressor station or liquid
pump station that is licensed as a pipeline installation showing the
following as set out in
Schedule 2:
(
a) the name of the installation;
(
b) the legal land location of the installation;
(
c) the name of the licensee;
(
d) an emergency telephone number and any warning symbols.
(3) Warning symbols identifying the hazard at a pipeline installation
referred to in subsection (2) must include, if applicable,
(
a) Category I: Flammable (gas or liquid), and
(
b) Category II: Poisonous Gas.
Part 6
Changes to Pipeline
Liner and internal protection installation
61 Unless otherwise authorized by the Regulator, an application to
the Regulator for approval to install a liner in a pipeline, whether
expanded or freestanding or an in-situ application of a thin-film
internal coating as internal protection, must be in accordance with the
requirements of Directive 056.
Liner and internal protection installation in sour service
62 If an expanded liner or an in-situ-applied thin-film internal
coating as internal protection is to be installed in a pipeline to be used
in sour service, as defined in CSA Z662, and the hoop strength
capability of the lined system depends on the strength of the exterior
pipeline, the exterior pipeline must be in accordance with the sour
service requirements of CSA Z662 and these Rules.
Change in substance or pressure
63 Unless otherwise authorized by the Regulator, an application must
be made to change the substance or the licensed maximum operating
pressure of a pipeline in accordance with the requirements of Directive
Testing requirements for change in substance or pressure
64 The Regulator may establish any testing requirements it considers
necessary for the approval of a change in substance conveyed or in
licensed maximum operating pressure.
Part 7
Relocation or Alteration of Pipeline
or Other Regulator Direction
Application for direction under
section 33 of Act
65(1) An application to the Regulator for a direction under
section 33
of the Act must include
(
a) a sketch, map or drawing that identifies
(
i) the present location of the pipeline where the alteration,
relocation or addition is proposed,
(ii) the name of the licensee and the licence number of the
pipeline,
(iii) the proposed pipeline alteration, relocation or addition,
and
(iv) details of any surface work or improvement at the
pipeline location if the alteration, relocation or addition
is to accommodate the surface work or improvement,
(
b) the specifications of the pipeline and any associated casing,
(
c) a statement concerning
(
i) the purpose of the pipeline alteration, relocation or
addition and the reason the applicant considers it to be
in the public interest,
(ii) any documented evidence relating to prior knowledge
by the licensee, landowner or another licensee of the
surface work or improvement affecting the pipeline, and
(iii) the opinion of the applicant about allocation of costs
necessary to complete the pipeline alteration, relocation
or addition and the reasons for it,
(
d) an estimate of total costs for the alteration, relocation or
addition, if known,
(
e) a list of landowners and occupants of property affected by the
proposed pipeline alteration, relocation or addition, and
(
f) a list of the status of acquisition of right of way, working
space and consents of owners and occupants for any
proposed pipeline alteration, relocation or addition.
(2) The Regulator may require the licensee to perform any testing that
it considers necessary prior to making a direction under
section 33 of
the Act.
Notice to Regulator
66(1) A licensee must notify the Regulator when the work according
to a direction under this Part has been completed.
(2) After receiving a notice under subsection (1), the Regulator may
amend the licence.
Part 8
Release of Product and
Contact Damage
Report of leak, break or contact damage
67(1) For the purpose of
section 35 of the Act, if a leak, break or
contact damage occurs in a pipeline or from the part of a pipeline or its
isolation valves that differentiate the pipeline from any other
equipment of a pipeline installation, the licensee must immediately
report the incident to the Regulator in accordance with
section 5(2).
(2) Subject to any other reporting obligations, if a release occurs on a
surface lease or public lands disposition containing a pipeline
installation but not from the pipeline or its isolation valves that
differentiate the pipeline from any other equipment located on the
lease or disposition, as the case may be, notification is required if the
release
(
a) is of a volume of 2 cubic metres or more, or
(
b) may cause, is causing or has caused an adverse effect as
defined in the Environmental Protection and Enhancement Act.
(3) If a leak, break or contact damage has been reported to the
Regulator in accordance with subsection (1), the licensee, on request,
must submit to the Regulator a written report indicating
(
a) the time the leak, break or contact damage occurred,
(
b) the approximate quantity of substance lost, if any,
(
c) the method of repair, if applicable,
(
d) the conditions that caused or contributed to the leak, break or
contact damage and any substantiating reports,
(
e) the steps to be taken to prevent similar occurrences in the
future,
(
f) information regarding the spill containment and recovery
techniques, and
(
g) any other information that the Regulator may request.
(4) If a leak, break or contact damage has been reported to the
Regulator in accordance with subsection (1),
(
a) the Regulator may require the licensee to conduct
inspections, investigations, testing or an engineering
assessment of an affected pipeline, and
(
b) the licensee must maintain a record of the incident in
accordance with the licensee's Integrity Management Program
and Safety and Loss Management System.
Containment of leak or break
68 If substances escape from a leak or break in a pipeline, the
licensee, on detection of the leak or break, must take immediate steps
to stop the source of release and contain and clean up the substances.
Repair of leak, break or contact damage
69 If a leak, break or contact damage occurs in a pipeline, the
Regulator may specify the method of repair.
Intentional release of gas
70(1) Unless otherwise authorized by the Regulator, and subject to
subsection (2), no licensee shall intentionally release to the atmosphere
any natural gas not meeting the definition of distribution specification
gas in
section 1(1)(
r) either without combusting the gas in an approved
manner or otherwise treating the gas to meet the distribution
specifications.
(2) Subsection (1) does not apply to gas released for short duration
and intermittently from
(
a) corrosion coupon fittings and corrosion probe fittings,
(
b) composite pipe vents or the annulus vents of a pipeline with
an expanded liner,
(
c) pigging traps and associated venting valves, once purged
with clean gas, or
(
d) the blowdown of water traps or drains.
(3) Gas vented from the equipment described in subsection (2)
(
a) does not require an approval under Directive 060,
(
b) must not be vented continuously, except as allowed under
subsection (4), and
(
c) must not cause off-lease or off-right of way odours.
(4) Annulus vents of a pipeline with an expanded liner must not be left
open beyond the time recommended by the liner manufacturer or
installer unless the vents are permanently connected to a gas treatment
system designed for continuous operation and that treats any gas
vented to meet the distribution specifications.
(5) Any other gas vented from a pipeline must be vented in
accordance with the requirements of Directive 060.
Part 9
Discontinuance, Abandonment,
Removal and Resumption
General
71(1) Unless otherwise authorized by the Regulator and subject to
section 72, any pipeline that has not been in active flowing service for
24 months must be discontinued, abandoned or returned to active
flowing service.
(2) The licensee must manage a pipeline that is not in active flowing
service in accordance with the licensee's Integrity Management
Program.
(3) The licensee, on request of the Regulator, must provide records or
documents that demonstrate that any pipeline not in active flowing
service is being managed in accordance with the licensee's Integrity
Management Program.
Duty to maintain and manage as operating
72(1) Despite
section 71, if a pipeline or part of a pipeline cannot be
physically isolated or disconnected from an operating pipeline, it shall
not be discontinued or abandoned but must be maintained as an
operating pipeline under the licensee's Integrity Management Program.
(2) Dead legs that are continually exposed to operating pipeline
conditions must be managed as an operating pipeline according to the
licensee's Integrity Management Program and are considered to be
operating for the purposes of
section 82.
Application in case of discontinuance, abandonment or removal
73(1) Unless otherwise authorized by the Regulator, a licensee
discontinuing, abandoning or removing a pipeline or discontinuing or
abandoning an entire pipeline system under this Part must apply to the
Regulator for approval in accordance with the requirements of
Directive 056 within 90 days of the completion of the discontinuance,
abandonment or removal operation, as the case may be.
(2) An application for discontinuance or abandonment of an entire
pipeline system under subsection (1) must include a cover letter
explaining the scope and circumstances of the system abandonment or
discontinuation, as the case may be, and a listing of all line segments.
Discontinuance or abandonment of entire pipeline system
74 Where a licensee intends to discontinue or abandon an entire
pipeline system by isolating or disconnecting the pipelines within that
system from every well, facility or pipeline that could provide a
pressure source, the discontinuance or abandonment may take place
without the removal of underground tie-ins within the system subject
to the following:
(
a) an application for approval for discontinuance or
abandonment of the entire pipeline system is made under
section 73;
(
b) all other requirements applicable to discontinuance or
abandonment in this Part shall apply.
Conducting discontinuance
75 Unless otherwise authorized by the Regulator, the licensee must
ensure that the pipeline or the part of the pipeline that is discontinued
(
a) pigged or cleaned to remove any free conveyed substances
and debris as thoroughly as reasonably possible,
(
b) protected effectively against internal corrosion by purging
with air or inert gas, or fresh water that is suitable for the
pipeline materials, with any remaining pressure not to exceed
103 kilopascals gauge (kPag),
(
c) protected effectively against external corrosion by
maintaining effective cathodic protection,
(
d) physically isolated or disconnected from any pressure source,
well, facility or other pipeline and plugged or capped by
mechanical or welded means, except as allowed by
section
74,
(
e) not isolated or disconnected in a manner that results in an
adjoining operating pipeline being left with connection points
that could be subject to internal corrosion due to stagnant
fluid traps or dead legs,
(
f) left in a safe condition that does not pose a threat to the
environment or to a person who may come into proximity
with the pipeline, and
(
g) individually identified as discontinued, with its own line
number, on the amended licence.
Conducting abandonment
76 Unless otherwise authorized by the Regulator, the licensee must
ensure that the pipeline or the part of the pipeline that is being
abandoned is
(
a) pigged or cleaned to remove any free conveyed substances
and debris as thoroughly as reasonably possible,
(
b) physically isolated or disconnected from any pressure source,
well, facility or other pipeline, except as allowed by
section
74,
(
c) completed by the removal of all associated surface
equipment, including pig traps, risers, block valves, line
heaters and support structures or pipe racks unless used by
other equipment,
(
d) isolated by cutting off the riser at the pipeline level or as
close to the pipeline level as practical,
(
e) plugged or capped by mechanical or welded means,
(
f) not isolated or disconnected in a manner that results in an
adjoining operating pipeline being left with connection points
that could be subject to internal corrosion due to stagnant
fluid traps or dead legs,
(
g) left without corrosion inhibition and without cathodic
protection,
(
h) not releasing gases from polymeric components that could
result in flammable or toxic hazard,
(
i) left in a safe condition that does not pose a threat to the
environment or to a person who may come into proximity
with the pipeline, and
(
j) individually identified as abandoned, with its own line
number, on the amended licence.
Closure quotas
77(1) The Regulator may establish closure quotas that are applicable
to some or all licensees with respect to the required amount of work or
the amount to be spent, or both, as directed by the Regulator and for
the period determined by the Regulator, with respect to the closure of
the licensee's pipelines.
(2) A licensee must comply with any closure quota applicable to it,
unless otherwise directed by the Regulator.
Closure plans
78(1) When requested by the Regulator, a licensee must submit a
closure plan regarding some or all of its pipelines, in accordance with
any direction of the Regulator given under subsection (3).
(2) A closure plan must contain the information required by the
Regulator and the plan must be approved by the Regulator subject to
(3) The Regulator may direct the timing and priority for performing
work with respect to the closure of the licensee's pipelines.
approved closure plan.
Mandatory abandonment
79 Despite
section 76, a licensee must abandon a pipeline if
(
a) the Regulator suspends or cancels the licensee's licence
because the licensee has contravened the Act, these Rules or
an order or direction of the Regulator,
(
b) the Regulator notifies the licensee that in the opinion of the
Regulator the pipeline may constitute an environmental or
safety hazard,
(
c) the licensee
(
i) is not or ceases to be resident in Alberta,
(ii) has not appointed an agent in accordance with
section
19 of the Act, and
(iii) does not hold a subsisting exemption under
section 3
from the requirement to appoint an agent,
(
d) the licensee is deceased,
(
e) the licensee is a corporation registered, incorporated or
continued under the Business Corporations Act that is not
active or has been dissolved, or if the corporate registry
status of the licensee is struck or rendered liable to be struck
under any legislation governing corporations,
(
f) the licensee has not discontinued the pipeline in accordance
with the Act, these Rules or an order or direction of the
Regulator,
(
g) the pipeline is associated with a well or facility that has been
abandoned or has been ordered to be abandoned by the
Regulator and the pipeline is not used for any other well or
facility,
(
h) the licensee has sold or disposed of the licensee's interest in
the pipeline and has not transferred it to a person who is
eligible to hold a licence for the pipeline, or
(
i) the licensee is otherwise ordered to do so by the Regulator.
Responsibility for discontinued or abandoned pipeline
80 An approval by the Regulator for discontinuance or abandonment
operations does not relieve the licensee from the responsibility for
further discontinuance or abandonment or other operations with
respect to the same pipeline or part of a pipeline that may become
necessary.
Conducting removal
81(1) Unless otherwise authorized by the Regulator, the licensee must
ensure that any pipeline or part of a pipeline that is removed
(
a) is first pigged or cleaned to remove any free conveyed
substances and debris as thoroughly as reasonably possible,
(
b) is not disconnected in a manner that results in an adjoining
operating pipeline being left with connection points that
could be subject to internal corrosion due to stagnant fluid
traps or dead legs, and
(
c) is individually identified as removed, with its own line
number on the amended licence.
(2) Unless otherwise authorized by the Regulator, any associated
surface equipment, including pig traps, risers, block valves, line
heaters, support structures and pipe racks must be removed unless used
by other equipment.
(3) Any remaining pipeline, if discontinued or abandoned, must be
capped or plugged by mechanical or welded means at the terminated
end.
(4) Removed pipe and equipment must be transported from the right
of way of the removed pipeline in a timely manner and must not be
allowed to remain on the right of way longer than 60 days after
removal of the pipeline, unless otherwise authorized by the Regulator.
Resumption of pipeline operation
82 Unless otherwise authorized by the Regulator, a licensee intending
to resume the operation of a pipeline or part of a pipeline
(
a) that was discontinued or abandoned,
(
b) that has not been in active flowing service for a period longer
than 24 months, or
(
c) the licence of which has been transferred by the direction of
the Regulator under
section 18(7) of the Act
must make an application to the Regulator for approval of resumption
in accordance with the requirements of Directive 056.
Part 10
Transitional Provisions, Repeal,
Expiry and Coming into Force
Transitional
83(1) In this section, "former Rules" means the Pipeline Rules
(AR 91/2005) as they read immediately before the coming into force of
these Rules.
(2) A licence or approval granted by the Regulator under the former
Rules remains in force according to its terms until it expires or is
amended, suspended or cancelled or a subsequent licence or approval
is granted under the Act or these Rules.
Repeal
84 The Pipeline Rules (AR 91/2005) are repealed.
Expiry
85 For the purpose of ensuring that these Rules are reviewed for
ongoing relevancy and necessity, with the option that they may be
repassed in their present or an amended form following a review, these
Rules expire on January 31, 2031.
Coming into force
86 These Rules come into force on November 15, 2023.
Schedule 1
Pipeline Warning Signs
(sections 53 - 60(1))
Schedule 2
Pipeline Installation Identification Signs
(section 60(2))