Design-Build Contracts

Cal. EDC § 81707

California Statutes

Each community college district governing board that adopts the design-build process for a project pursuant to this

chapter shall submit to the Legislative Analyst a report on the project at the completion of the project. Completion shall have the same meaning as defined in subdivision (

c) of

Section of the Public Contract Code. This report shall be submitted within days after completion of the project. The Legislative Analyst shall submit an interim report to the Legislature by January 1, 2005, and a final report to the Legislature by January 1, 2007. The reports shall include, but not be limited to, all of the following information as to each project: (

a) The type of facility. (

b) The gross square footage of the facility. (

c) The company or contractor who was awarded the project. (

d) The estimated and actual length of time to complete the project. (

e) The estimated and actual project cost. (

f) A description of the relative merits of a project procured pursuant to this

chapter and similar projects procured pursuant to other provisions of this code. (

g) A description of any written protest concerning any aspect of the solicitation, bid, proposal, or award of the design-build project, including the resolution of the protest. (

h) Other pertinent information that may be instructive in evaluating whether the design-build method of procurement should be continued, expanded, or prohibited. (

i) The findings established pursuant to

Section and a postcompletion evaluation as to whether the findings were achieved. (

j) Any Labor Code violations discovered during the course of construction or following completion of the project, as well as any fines or penalties assessed.

Document details

CollectionCalifornia Statutes
CitationCal. EDC § 81707
Date2003-01-01
Typestatute
Languageen
SourceCA_STAT
IdentifierEDC81707.20026371

Design-Build Contracts

Cal. EDC § 81707

California Statutes

Design-Build Contracts

Cal. EDC § 81707

California Statutes

Each community college district governing board that adopts the design-build process for a project pursuant to this

chapter shall submit to the Legislative Analyst a report on the project at the completion of the project. Completion shall have the same meaning as defined in subdivision (

c) of

Section of the Public Contract Code. This report shall be submitted within days after completion of the project. The Legislative Analyst shall submit an interim report to the Legislature by January 1, 2005, and a final report to the Legislature by January 1, 2007. The reports shall include, but not be limited to, all of the following information as to each project: (

a) The type of facility. (

b) The gross square footage of the facility. (

c) The company or contractor who was awarded the project. (

d) The estimated and actual length of time to complete the project. (

e) The estimated and actual project cost. (

f) A description of the relative merits of a project procured pursuant to this

chapter and similar projects procured pursuant to other provisions of this code. (

g) A description of any written protest concerning any aspect of the solicitation, bid, proposal, or award of the design-build project, including the resolution of the protest. (

h) Other pertinent information that may be instructive in evaluating whether the design-build method of procurement should be continued, expanded, or prohibited. (

i) The findings established pursuant to

Section and a postcompletion evaluation as to whether the findings were achieved. (

j) Any Labor Code violations discovered during the course of construction or following completion of the project, as well as any fines or penalties assessed.

Document details

CollectionCalifornia Statutes
CitationCal. EDC § 81707
Date2003-01-01
Typestatute
Languageen
SourceCA_STAT
IdentifierEDC81707.20026371
Design-Build Contracts | CaseLite