Extension of Facilities; Contribution in Aid of Construction (Ch. 25-6)
Fla. Admin. Code R. 25-6.064
Florida Administrative Code
Rule: 25-6.064
Rule Title: Extension of Facilities; Contribution in Aid of Construction
Department:
PUBLIC SERVICE COMMISSION
Division:
Departmental
Chapter:
ELECTRIC SERVICE BY ELECTRIC PUBLIC UTILITIES
Latest version of the final adopted rule presented in Florida Administrative Code (FAC):
Effective Date:
12/10/2020
History Notes:
Rulemaking Authority 366.05(1) , 350.127(2) FS. Law Implemented 366.03 , 366.05(1) , 366.06(1) FS. History–New 7-29-69, Amended 7-2-85, Formerly 25-6.64, Amended 2-1-07, 12-10-20.
References in this version:
No reference(s).
History of this Rule since Jan. 6, 2006
Notice /
Adopted
Section
Description
Publish
Date
Final
25-6.064
Extension of Facilities; Contribution in Aid of Construction
Effective:
12/10/2020
Proposed
25-6.0343
......
To update and clarify the rules, including updating the rules to recognize the Commission’s adoption of Rule 25-6.030, Storm Protection Plan, and the repeal of Rule 25-6.0342.
Docket No. 20200091-EU
10/8/2020
Vol. 46/197
Variances
25-6.064
NOTICE IS HEREBY GIVEN by the Florida Public Service Commission that Tampa Electric Company’s petition for waiver of Rule 25-6.064, Limited Alternative Rate Increase, Florida Administrative Code, filed on January 6, 2020, ....
5/11/2020
Vol. 46/92
Variances
25-6.064
Tampa Electric Company in Docket No. 2020011-EI
1/9/2020
Vol. 46/06
Workshop
25-6.0143
......
Public electric utility storm protection plans and storm protection cost recovery clause rulemaking to implement
Section 366.96, F.S.
Docket ....
Tuesday, August 20, 2019, at 9:30 a.m.
Room 148, Betty Easley Conference Center, 4075 Esplanade Way, ....
8/6/2019
Vol. 45/152
Development
25-6.0143
......
To implement
Section 366.96, FS, which was passed by the Florida Legislature in the 2019 session.
Section 366.96, FS, requires public electric utilities to file storm protection plans with the Commission and allows a public ....
6/7/2019
Vol. 45/111
Final
25-6.064
Extension of Facilities; Contribution in Aid of Construction
Effective:
02/01/2007
Change
25-6.034
......
Standard of Construction, Location of the Utility’s Electric Distribution Facilities, Third-Party Attachment Standards and Procedures, Safety Standards for Construction of New Transmission and Distribution ....
12/22/2006
Vol. 32/51
Change
25-6.034
......
Standard of Construction, Extension of Facilities; Contribution in Aid of Construction,
Schedule of Charges, Facility Charges for Providing Underground Facilities of Public Distribution Facilities Excluding ....
7/28/2006
Vol. 32/30
Development
25-6.034
......
To amend rules to require utilities to meet higher standards for the construction of overhead electrical transmission and distribution facilities to better withstand the effects of extreme weather events, including the establishment ....
5/5/2006
Vol. 32/18
Development
25-6.033
......
To amend rules relating to the construction of new underground electrical transmission and distribution infrastructure, and amend rules relating to the conversion of existing overhead electrical infrastructure to underground ....
5/5/2006
Vol. 32/18
Development
25-6.034
......
To amend rules to require utilities to meet higher standards for the construction of overhead electrical transmission and distribution facilities to better withstand the effects of extreme weather events.
3/31/2006
Vol. 32/13
Development
25-6.033
......
To amend rules relating to the construction of new underground electrical transmission and distribution infrastructure, and amend rules relating to the conversion of existing overhead electrical infrastructure to underground ....
3/31/2006
Vol. 32/13
Final
25-6.064
Extension of Facilities; Contribution in Aid of Construction
Effective:
07/02/1985