2019 QCCA 1072, 2019 QCCA 1072
Opinion
Churchill Falls (Labrador) Corporation Limited c. Hydro-Québec 2019 QCCA 1072 COURT OF APPEAL CANADA PROVINCE OF QUEBEC REGISTRY OF MONTREAL No.: 500-09-026327-163 (500-17-078217-133) DATE: June 20, 2019 CORAM: THE HONOURABLE JACQUES CHAMBERLAND, J.A. ALLAN R. HILTON, J.A. PATRICK HEALY, J.A. CHURCHILL FALLS (LABRADOR) CORPORATION LIMITED APPELLANT – Defendant v. HYDRO-QUÉBEC RESPONDENT – Plaintiff JUDGMENT [ 1 ] The appellant Churchill Falls (Labrador) Corporation Limited ( “CFLCo”) appeals a judgment of the Superior Court, District of Montreal (the Honourable Mr.
Justice Martin Castonguay) rendered on August 8, 2016 and corrected on November 8, 2016 which granted the respondent Hydro-Québec’s motion for a declaratory judgment and dismissed its contestation of that motion, with legal costs in favour of Hydro-Québec. [ 2 ] For the reasons of Chamberland, J.A., with which Hilton and Healy, JJ.A. concur, THE COURT: [ 3 ] ALLOWS CFLCo’s appeal in part; [ 4 ] REVERSES the trial judgment by substituting the following conclusions for those found at paragraphs 1149-1157: [1149] GRANTS Hydro-Québec’s motion for a declaratory judgment and Churchill Falls (Labrador) Corporation’s contestation in part; [1150] DECLARES that, under
Schedule III of the May 12, 1969 contract, the terms and conditions of which apply since September 1, 2016:
(1) Hydro-Québec does not have the exclusive right to purchase, and receive, all of the energy produced by the Upper Churchill power plant, as defined in
section 1.1 (in the definition of “ Plant ”) and as maintained in accordance with
section 4.1.4, but, rather, the right to purchase, and to receive, annually, a specific quantity of energy equivalent to the value of the Annual Energy Base (which value is then allocated monthly pursuant to the concept of Continuous Energy , according to a mathematical formula that provides for the calculation of the monthly payments owed by Hydro-Québec ); and
(2) Hydro-Québec has the right, at all times, to the power defined by the expression Firm Capacity (section 1.1/
Definitions ), as well as, upon request, all additional power which, in CF(L)Co’s opinion, is available (section 5.2) and, lastly, from November to March, all additional power whose availability Hydro-Québec ensured under the Guaranteed Winter Availability Contract (“GWAC”); [1151] DECLARES that the rights conferred on Hydro-Québec under sections 4.1.1 ( Operational Flexibility ) and 5.3 ( Firm Capacity Schedules ) of
Schedule III to the May 12, 1969 contract provide it with an operational flexibility very similar to the operational flexibility it enjoyed since the commissioning of the Upper Churchill plant, including its right to
schedule and plan its energy and power requirements and to postpone (or accelerate) the delivery of energy from one month to another, the whole without being limited to a quantitative cap established pursuant to the concept of Continuous Energy on a monthly basis; and last, [1152] DECLARES that, until August 31, 2041, CF(L)Co cannot sell to a third party, or use for the benefit of a third party, including Newfoundland and Labrador Hydro (“NLH”), any quantity of power whatsoever, with the exception of the power associated with the “ Recapture ” (300 MW) and “Twinco” (225 MW) blocks, and, since September 1, 2016, the power associated with the energy produced by the Upper Churchill plant over and above the value of the Annual Energy Base , regardless of whether such sales, or use, are made on a firm or interruptible basis;
[ 5 ] THE WHOLE with the legal costs on appeal in favour of CFLCo, each party paying its own costs at trial, including expert fees, given the divided outcome of the motion for a declaratory judgment and its contestation. JACQUES CHAMBERLAND, J.A. ALLAN R. HILTON, J.A. PATRICK HEALY, J.A.
Mtre Éric Mongeau Mtre Patrick Girard Mtre Romy Proulx STIKEMAN ELLIOTT Mtre Douglas Mitchell IMK For the appellant Mtre Pierre Bienvenu Mtre Sophie Melchers Mtre Horia Bundaru Mtre Andres Garin Mtre Vincent Rochette NORTON ROSE FULBRIGHT CANADA Mtre Lucie Lalonde HYDRO-QUÉBEC GANESAN FRASER For the respondent Date of hearing: December 4, 2018 REASONS OF CHAMBERLAND, J.A.
THE BACKGROUND .. 6 THE PROCEEDINGS .. 9 THE TRIAL JUDGMENT 11 THE ISSUES ON APPEAL AND THE ANALYSIS .. 16 The concepts of power and energy . 16 The standard of review .. 17 The characterization of the contract 17 The ambiguity of the contract 19 A. HQ’s right to all the power and energy . 22 Energy . 23 Power 41 B. CFLCo and sales of interruptible power . 41
The 300 MW and 225 MW blocks. 43 Firm Capacity. 43 The power associated with the excess energy. 44 C.
The conclusions of the judgment 44 CONCLUSION.. 46 [6] On November 2, 2018, the Supreme Court of Canada rendered judgment in the case in which Churchill Falls (Labrador)Corporation Limited (“CFLCo”) sought a court order compelling Hydro-Québec (“HQ”) to renegotiate the contract signed on May 12, 1969.[1] [7] Confirming the decisions of this Court[2] and the Superior Court,[3] the highest court in the land concluded that HQ had noobligation to renegotiate the 1969 contract. [8] That case was but one of many that had arisen between the same parties since the mid-1970s.
In his reasons, with which all themembers of the panel concurred (save one) concurred, Gascon, J. thus described this long judicial saga: [19] […] In 1976, it [the Government of Newfoundland and Labrador ] tried to force CFLCo to “recapture” more electricity thanCFLCo was entitled to under the Contract.
CFLCo responded that the inevitable result of doing so would be a failure to perform theprestations it owed Hydro-Québec, and it declined to comply, which led to the dispute being brought before the courts of both provinces.This Court heard and summarily dismissed appeals from the two series of decisions that had followed, in which the lower courts hadagreed with Hydro-Québec on all points: Newfoundland (Attorney General) v. Churchill Falls (Labrador) Corp., (SCC),[1988] 1 S.C.R. 1085; Hydro-Québec v.
Churchill Falls (Labrador) Corp., (SCC), [1988] 1 S.C.R. 1087. [20] Second, in 1980, the province’s legislature enacted a statute that provided for reversion to the government of the rights that hadbeen assigned to CFLCo in 1961. Another court challenge ensued.
The Newfoundland and Labrador Court of Appeal declared thelegislation to be valid, but this Court unanimously held that it was ultra vires the province, because its pith and substance was to interferewith rights that, under the Contract, were situate in Quebec, that is, the place where a party could bring an action for the enjoyment ofthose rights: Reference re Upper Churchill Water Rights Reversion Act, (SCC), [1984] 1 S.C.R. 297. [9] The present case involves a different approach to the 1969 contract between CFLCo and HQ.
The issue is no longer whetherthe contract should be renegotiated, but rather how it should be interpreted in order to assess the following two propositions: (1) sinceSeptember 1, 2016 (the date on which the additional period of 25 years began, following the expiry of the initial term of 40 years), HQwould be limited to specific capped quantities of electrical energy (monthly and yearly) and, therefore, would not have the exclusiveright to all the energy and power from the Churchill Falls power plant; and
(2) CFLCo would be entitled to sell power to third parties on an interruptible basis both before and after September 1, 2016.[4] [10] After a lengthy trial, the judge rejected both these propositions.[5] THE BACKGROUND [11] In order to shorten these reasons, I will refer to the background described by the Supreme Court in Churchill Falls 2018, subjectto later elaborating on certain points when dealing with the various issues this appeal raises: [8] In 1961, the Government of Newfoundland and Labrador signed a lease with the Hamilton Falls Power Corporation Limited(which later changed its name and became CFLCo), a subsidiary of the British Newfoundland Corporation Limited (“Brinco”).
Brincowas a consortium of industrial, banking and mining companies whose directors were, according to the trial judge, elite titans of industryat the time. The lease conferred on CFLCo the right to make use of the watershed of the Churchill Falls site to produce hydroelectricpower. The lease, which was for a fixed rent, had a term of 99 years, renewable for a further 99 years.
It provided that royalties were tobe paid to the Government of Newfoundland and Labrador, but prohibited the province from raising taxes or increasing the amount ofthe royalties. [9] At the time, Brinco wanted to exploit the watershed and build a hydroelectric plant there, but it was apparently unwilling either tofinance the plant by issuing shares in CFLCo or to commit its own funds. Instead, it tried to secure debt financing for the construction ofthe Plant.
For that purpose, CFLCo, its subsidiary that was to develop the project, sought customers that could guarantee that they wouldpurchase large quantities of electricity on a long-term basis, in part to assure its future creditors that the project was financially viable.The customers it sought would also need to have the technology required to transmit the electricity produced by the Plant to consumers.In the trial judge’s opinion, there was nothing to suggest that, at the time, CFLCo was in any way dealing with an urgent situation thatforced it to undertake the project in such circumstances. [10] Hydro-Québec, a state-owned enterprise created in 1944 that has had a monopoly on electricity in Quebec since 1963, met thesecriteria.
Furthermore, it was at that time facing an increase in the demand for electricity in Quebec. This did not make it the perfect
partner, however, as it was capable of developing its own hydroelectric projects. Hydro-Québec therefore had to be convinced that itwould be worth its while to participate in the construction of plants owned by third parties and to purchase their electricity rather thanproducing its own. […] [11] CFLCo approached Hydro-Québec immediately after the 1961 lease was signed, but Hydro-Québec rejected its initial offers. Itwas not until 1966 that the parties agreed on a development project. At that time, they signed a Letter of Intent setting out the terms ofthe project, although those terms required the approval of the governments of Quebec and Newfoundland and Labrador.
Article 2.0 ofthe Letter of Intent stipulated that a final contract remained to be signed. The Letter of Intent stated that CFLCo would be responsible forbuilding the Plant, and Hydro-Québec for building the transmission lines to Quebec. The parties expected Hydro-Québec to purchase afixed quantity of electricity from the Plant for 40 years at fixed prices that would decrease every 5 or 10 years and would be based on thecost of building the Plant.
That purchase guarantee took the form of a “take-or-pay” undertaking that would require Hydro-Québec to buyand pay for a fixed quantity of electricity whether it needed it or not. The Letter of Intent also provided that CFLCo would have the rightto receive 300 megawatts of electricity on request: this was the right of “recapture”. The parties also agreed that Hydro-Québec wouldguarantee up to $100 or $109 million in construction cost overruns. [12] Construction of the Plant began immediately, but both CFLCo and Hydro-Québec quickly realized that the work was proving tobe more costly than had been anticipated.
In addition, potential creditors were hesitant and were asking for additional security. Thisrequired the parties to make changes to their respective prestations, with the result that a new contractual equilibrium was establishedfollowing further negotiations. The 1969 Power Contract, which superseded and replaced the Letter of Intent, therefore differedfundamentally from the latter on certain key points. For example, Hydro-Québec now guaranteed any cost overruns for the Plant.
Aswell, the parties retained the initial 40-year term, but agreed to add a clause providing for automatic renewal of the Contract for anadditional 25 years. [13] In his rigorous analysis of the evidence, the trial judge reviewed the negotiations on this last point in detail. He noted that,because the electricity prices were based directly on the Plant’s construction costs, cost overruns had increased those prices and made theproject less attractive for Hydro-Québec.
He observed that, at the time, Hydro-Québec had therefore requested — in what the executivecommittees of the boards of directors of Brinco and CFLCo perceived as a “very firm” position — an option to renew the Contract for25 years at a single fixed price slightly lower than the rate it was to pay at the end of the initial term of the Contract.
It was clear,however, that Hydro-Québec would still be required to buy and pay for a fixed quantity of electricity. [14] The minutes of a joint meeting of those two committees indicate that they were of the view that such a commitment wouldproduce significant annual revenue, that there would be no debt outstanding for CFLCo at the time of the renewal and that, althoughhydroelectricity was an attractive source of power at the time of the negotiations, it was conceivable that it would be less economicalthan nuclear power 40 years later.
Ultimately, CFLCo acceded to Hydro-Québec’s request, although it thought that it would be better offwith an automatic renewal clause, a point on which Hydro-Québec conceded in the end. The Government of Newfoundland andLabrador was consulted before the final agreement was signed: Newfoundland (Attorney General) v. Churchill Falls (Labrador) Corp.(1985), (NL CA), 56 Nfld. & P.E.I.R. 91 (C.A.), at paras. 16 and 26. [15] When the Power Contract was signed, it reflected the parties’ legitimate expectations and seemed to them to be mutuallybeneficial.
The paradigm of the Contract, its organizing principle, can be easily summarized. On the one hand, Hydro-Québec assumedthe risks associated both with the Churchill River development project and with the uncertainty of market prices for electricity.
On theother, because CFLCo was receiving a Plant that it would not be paying for itself and was acquiring the certainty and stability thatresulted from having a long-term customer, it agreed in exchange to sell the electricity produced by the Plant to Hydro-Québec at lowprices, and over a very long period. […] [21] At that same time, Hydro-Québec and CFLCo began negotiations to settle their differences. The negotiations continuedsporadically for several years, but the parties never reached an agreement to reopen the 1969 Contract.
Instead, they chose to enter intoother contracts parallel to it. [22] Thus, in 1991, Hydro-Québec undertook to purchase the balance of the Plant’s production capacity for a limited time. In 1998,the parties changed the conditions for the exercise of CFLCo’s “recapture” right by agreeing that, for a period of time, CFLCo would sellthe electricity in question to NLH, which would resell it at a profit to Hydro-Québec under terms that were kept confidential.
Since 2009,the electricity to which the conditions respecting the recapture right apply has been resold in other markets and exported through Hydro-Québec’s transmission lines. Finally, in 1999, the parties signed the Guaranteed Winter Availability Contract, under which Hydro-Québec received the assurance that the Plant’s production capacity would be available during the winter months in exchange forsubstantial additional revenue for CFLCo.
Significantly, these last two contracts will expire at the same time as the Power Contract, in2041. [12] To simplify matters, the May 12, 1969 power contract provides for the purchase by HQ of the energy produced by the ChurchillFalls power plant, save for one block of a maximum of 300 MW and 2.362 billion kilowatthours,[6] called the “Recapture” block, whichis reserved for sale by CFLCo to a third party for consumption outside Quebec, and another block of 225 MW and 1.980 billionkilowatthours[7] which relates to CFLCo’s existing contractual obligations towards Twin Falls Corporation Limited (“Twinco”)) for aperiod of 65 years beginning on August 31, 1976 (the date on which the plant was in service at full capacity), under certain conditionsapplicable to the first period ending on August 31, 2016 and different conditions applicable to the second period (automatic renewal)beginning on September 1, 2016 and ending on August 31, 2041.
THE PROCEEDINGS [ 13 ] Over the years, especially as the initial 40-year term was coming to a close, the two parties disagreed on several points regarding the
interpretation of the contract, particularly with respect to the second 25-year period, such that, in 2013, HQ asked the Superior Court of Quebec to clarify certain aspects of its contractual relationship with CFLCo. [ 14 ] The motion for a declaratory judgment focused on two main issues, articulated as follows in the amended conclusions HQ sought: First issue : [ translation ] DECLARE that under the terms of
Schedule III (Renewed Contract) of the contract entered into on May 12, 1969 (Contract) between Churchill Falls (Labrador) Corporation (CF(L)Co) and Hydro-Québec, Hydro-Québec has the exclusive right to purchase all of the available power and all the energy produced at the Upper Churchill power plant , as such plant is defined in
section 1.1 of the Initial Contract and of the Renewed Contract (under the definition of “Plant”) and maintained in accordance with
section 4.2.4 of the Initial Contract and
section 4.1.4 of the Renewed Contract (Plant), with the exception of the power and energy associated with: (
i) the block of 225 MW which was reserved for CF(L)Co to meet its obligations towards Twin Falls Power Corporation Limited until December 31, 2014 [8] and which, subject to the conditions set forth in the Shareholders’ Agreement entered into between Newfoundland & Labrador Hydro (NHL), Hydro-Québec and CF(L)Co on June 18, 1999, may be sold by CFLCo for distribution and consumption in Labrador West as of January 1, 2015 (Twinco Block); and; (ii) the block of 300 MW reserved for CF(L)Co for sale to a third party for energy consumption outside Quebec (300 MW Block). DECLARE that the rights conferred on Hydro-Québec under
section 4.1.1 of the Renewed Contract, including its right to
schedule and plan power and energy, are not limited, restrained or restricted in any manner whatsoever, on a monthly basis, to the purchase of blocks capped on the basis of the concept of “Continuous Energy” set out in the Renewed Contract, and that they may be exercised with respect to all the available power and all the energy produced at the Plant, excluding the power and energy associated with the 300 MW Block and the Twinco Block.
DECLARE that under the Renewed Contract, Hydro-Québec is not bound to limit its requests for the delivery of energy to blocks subject to a monthly cap determined on the basis of the concept of “Continuous Energy” set out in the Renewed Contract. DECLARE that under the Renewed Contract, CF(L)Co is obliged to deliver to Hydro-Québec, at the latter’s request, all the available power and all the energy produced at the Plant, excluding the power and energy associated with the Twinco Block and the 300 MW Block.
Second issue: DECLARE that, as long as the Contract is in force, that is, until August 31, 2041, CF(L)Co shall not have any right to any quantity of power or energy produced at the Plant, except for the power and energy associated with the 300 MW Block and the Twinco Block.
DECLARE that, as long as the Contract is in force, that is, until August 31, 2041, CF(L)Co shall not have the right to sell to a third party, including NLH, any quantity of power or energy whatsoever exceeding the quantities associated with the 300 MW Block, whether such sales occur on a firm or so-called “interruptible” basis. [Emphasis added] [ 15 ] CFLCo contests HQ’s position as follows: First issue: DECLARE that under the terms of the Renewal Contract, the right of Hydro-Quebec to request and receive energy each month during the term of that contract is limited to the amount of Continuous Energy as defined under the said Renewal Contract, subject to the Minimum and Firm Capacity limits.
Second issue: DECLARE that in addition to the 300 MW of Recapture and in addition to the Twinco block, CF(L)Co is entitled under the Power Contract and the Renewal Contract to use the Churchill Falls power plant’s available capacity to increase the rate of delivery of energy to third parties , provided that by so doing it continues to make available to Hydro-Quebec its requested power and energy scheduled in accordance with the terms and conditions of the contracts.
DECLARE that, as owner and operator of the Churchill Falls power plant and holder of the hydraulic rights, CF(L)Co is entitled to operate the Churchill Falls plant as it deems appropriate and is entitled to derive revenues where possible from selling all electricity products that have not been specifically sold to Hydro-Quebec or third parties under the terms of a contract, provided that CF(L)Co fulfills its contractual obligations to Hydro-Quebec and third parties.
[Emphasis added] THE TRIAL JUDGMENT [ 16 ] After a 31-day trial that ended on December 18, 2015, judgment was rendered on August 8, 2016 and subsequently corrected as to form on November 8, 2016. The judgment is extremely detailed, consisting of 1157 paragraphs, as well as a complete glossary of the terms used (Schedule I), a lengthy time line (Schedule II) and, last, a list of the issues in dispute prepared by the parties at the request of the trial judge (Schedule III). [ 17 ] The judge spent over 600 paragraphs describing the events that preceded and followed the signing of the May 12, 1969 contract, and explaining certain exhibits in the court record. His
summary of the facts, from the very first contact between the Government of Newfoundland and Labrador and the Government of Quebec in 1953 until the signing of a letter of intent in 1966, and from the 1969 contract, and even subsequent thereto, until HQ brought the present dispute before the courts of Quebec in 2013, is meticulous, comprehensive and remarkable. I will return to it, when necessary, in the course of my analysis of the issues this appeal raises. [ 18 ] The judge then devoted over 150 paragraphs to discussing the reports and opinions of the experts each party retained as well as their qualifications.
I will return to this as well, if necessary, in the course of my analysis of the issues the appeal raises. [ 19 ] After distilling the dispute to the following two points: [9] [ translation ] - Under the renewed contract, does H.Q. have the right to all the power and energy produced by the Churchill Falls Plant, while enjoying the same flexibility it had throughout the term of the Principal Contract? - Does CF(L)Co have the right to sell to third parties, on an “interruptible” basis and at a rate exceeding the 300 MW recapture, the energy and power not requested by H.Q.? [Reference omitted] the judge divided his analysis into five chapters: the characterization of the contract; whether or not there is any ambiguity; HQ’s rights to the energy produced by the plant; CFLCo’s rights to the available power and the impact of the absence of any sales of power, when the trial took place, on the possibility of rendering a declaratory judgment on this subject. [ 20 ] With respect to the first question, the judge found that the Principal Contract and the Renewed Contract (i.e.,
Schedule III of the Principal Contract) were an inseparable contractual whole.
He was of the view, however, that the Guaranteed Winter Availability Contract (“GWAC”) signed by the parties on June 18, 1999 (retroactive to November 1, 1998), which sought to guarantee HQ access to a certain quantity of additional power during the peak winter period, was not part of that contractual whole, because it dealt with a matter which, although raised during discussions leading to the May 12, 1969 contract, had never been agreed upon. [ 21 ] With respect to the second question, the judge concluded that the contractual whole is ambiguous and that he was therefore required to interpret it.
This conclusion allowed him to apply the rules of contractual
interpretation set out in the Civil Code of Lower Canada (the situation being an existing contractual situation within the meaning of the transitional law), which, as the judge pointed out, are the same as those under the current Civil Code of Québec ( art. 1425 - 1432 ). In interpreting the contract, he therefore had to take into account the nature of the contract, the circumstances in which it was formed, the
interpretation that had already been given to it by the parties over time and, lastly, usage. [ 22 ] In dealing with the third question, the judge considered the meaning to be given to the terms and conditions of the contract applicable to the 25-year period that began on September 1, 2016. [ 23 ] With respect to the nature of the contract (or the contractual group), the trial judge found it to be a mixed contract containing a joint venture component and a sales component. [10] The existence of the joint venture component led him to conclude that he had to take into account the reasonable expectations of each of the shareholders of CFLCo at the time of the negotiations (HQ holding 34.2% of the shares and Brinco [11] holding 65.8%). [12] [ 24 ] With respect to the circumstances in which the 1969 contract was formed (including the documents peripheral to the contract and the parties’ objective in entering into the contract), the judge noted that the case was particular in that [ translation ] “none of the participants in the negotiations testified”. [13] The evidence, therefore, was strictly documentary. [14] The search for the common intention of the parties, he further stated, was thus dependent on [ translation ] “the identity of the individuals involved in the negotiations, the socio-economic and political context as well as the peripheral documents”. [15] [ 25 ] The trial judge concluded that CFLCo’s
interpretation of the expression Continuous Energy [16] in
Schedule III did not match what the parties had in mind during their negotiations. As a result, he found that HQ is entitled to all the energy produced by the plant, not just the quantities of energy associated with the definition of Continuous Energy . [17] According to him, CFLCo’s assertion would be a drastic change compared with the situation that existed during the first 40 years of the contract, and there was nothing in the evidence pointing to such a contemplated change; [18] the evidence, instead, indicating [ translation ] “an intention of continuity” [19] throughout the 65 years of the contract. [ 26 ] With respect to the parties’
interpretation of the contract, the judge concluded that the position CFLCo was now asserting had
been communicated to HQ only in June 2012, at the time the parties were discussing the five-year plan that included the year 2016-2017.
He was of the view that, until CFLCo came up with this [ translation ] “new theory”, it had always acted as if nothing was to change on September 1, 2016, particularly with respect to the operational flexibility HQ enjoyed on both a seasonal and multi-year basis (and not merely on a monthly basis, as CFLCo now argues). [ 27 ] With respect to usage, the judge found that the evidence did not support the conclusion that the expression Continuous Energy was known and used in the electricity industry at the time the 1969 contract was signed, nor did it establish that the sale of blocks of power and energy was commonplace. [ 28 ] The trial judge concluded his analysis of the third question by stating that CFLCo’s
interpretation of the expression Continuous Energy (as representing all the energy to which HQ is entitled) did not match what the parties had in mind. In his opinion, the expression refers to all the energy produced by the plant, thus including the so-called excess energy. As a result, with the exception of the power and energy associated with the block reserved for Twinco and the block recaptured by CFLCo, HQ’s right to plan for and
schedule power and energy according to its needs (the operational flexibility) is not limited, on a monthly basis, to the purchase of blocks of energy capped in accordance with the concept of Continuous Energy .
According to the judge, this concept, a new one, was intended only to ensure a stable flow of revenue for CFLCo, not to limit HQ’s rights in terms of the quantity of energy or power and of operational flexibility. [20] [ 29 ] The fourth and fifth questions dealt with the issue of sales of power on an interruptible basis. [ 30 ] The trial judge first questioned whether the fact that, at the time of the trial, there were no more sales of interruptible power [21] was an obstacle to a declaratory judgment.
He found that no such obstacle existed, given the forthcoming availability of a new transmission line [22] which CFLCo would be able to use to access the Northeastern American market without having to go through HQ’s transmission lines. [ 31 ] With respect to the fifth question, the judge concluded that the concept of sales of interruptible power existed at the time of the negotiations leading to the signing of the May 12, 1969 contract.
The mechanism for these sales, however, was vastly different from what it is now, [23] such that “interruptible power” as a product at the beginning of the 21st century is different from what it was forty years ago.
He therefore concluded that the parties had never contemplated this subject in their negotiations leading to the signing of the contract. [ 32 ] The trial judge finished this part of his analysis by linking his conclusion on the meaning of the expression Continuous Energy (namely, all the energy produced by the plant, including the excess energy (but excluding the Twinco and Recapture blocks), as established through 40 years of experience and reflected in the Annual Energy Base at the end of this 40-year period) to the answer to be given to this last question.
He pointed out that HQ must pay for this energy, whether or not it takes delivery thereof (the take-or-pay concept). It therefore follows, he found, that CFLCo [ translation ] “cannot sell what it has already sold to H.Q.” [24] CFLCo thus has [ translation ] “no right to the power and energy not used by H.Q., but which H.Q. is entitled to use because it has paid for it”. [25] [ 33 ] At the end of his reasons, the trial judge stated that, under
Schedule III to the May 12, 1969 contract, HQ has the exclusive right to purchase, and to receive, all the available power and all the energy produced at the Upper Churchill plant, except for the power and energy associated with the Twinco and Recapture blocks. [26] [ 34 ] The trial judge further declared that under
Schedule III to the May 12, 1969 contract, the rights conferred on HQ in terms of operational flexibility (including the scheduling and planning of power and energy) are not limited in any manner whatsoever, on a monthly basis, to the purchase of blocks capped on the basis of the concept of Continuous Energy , and that they may be exercised with respect to all the available power and all the energy produced at the plant, excluding the power and energy associated with the Twinco and Recapture blocks. [27] [ 35 ] Lastly, the trial judge declared that, until August 31, 2041, CFLCo will not have the right to sell to anyone whomsoever any quantity whatsoever of power and energy exceeding the quantities associated with the Recapture block, whether such sales are made on a firm or interruptible basis. [28] [ 36 ] Finally, the trial judge condemned CFLCo to pay the legal costs in favour of HQ, including the costs pertaining to the expert report and presence in court of Carlos Lapuerta. [29] THE ISSUES ON APPEAL AND ANALYSIS [ 37 ] In essence, the appeal raises three questions: 37.1.
Did the trial judge err by concluding that, under the terms and conditions of
Schedule III of the May 12, 1969 contract, HQ still has the exclusive right to purchase, and to receive, all the available power and all the energy produced at the Churchill Falls plant, with the exception of the power and energy associated with the Twinco and Recapture blocks, without being limited, on a monthly basis, to a quantitative cap established on the basis of the concept of Continuous Energy ? 37.2. Did the trial judge err by concluding that, under the terms and conditions of said
Schedule III, CFLCo cannot, until August 31, 2041, sell to anyone whomsoever (including Newfoundland and Labrador Hydro (“NLH”)) [30] any quantity whatsoever of power or
energy over and above the quantities associated with the Twinco and Recapture blocks, whether such sales are made on a firm or interruptible basis? 37.3. Do the conclusions of the judgment go beyond what the trial judge was entitled to decide? [ 38 ] Before analyzing these questions, it would be useful to quickly address certain preliminary matters.
The concepts of power and energy [ 39 ] First, the concepts of power and energy. “ Power ”, as defined in the May 12, 1969 contract, is the rate at which electrical energy is delivered at any point, measured in kilowatts (KW, 1000 watts) or multiples thereof. [31] Similarly, “ Energy ” is the result of power multiplied by the time during which the power is used, measured, in the case of electrical energy, in kilowatthours (KWh) [32] or multiples thereof.
Energy and power (or capacity) are therefore two different, albeit interconnected, concepts; the trial judge rightly explained that it is [ translation ] “useful to point out, once again, that power is used to deliver energy”. [33] The standard of review [ 40 ] Second, the standard of review. The case at bar deals essentially, if not exclusively, with the
interpretation of the contract the parties signed on May 12, 1969. The standard of review, as the Supreme Court noted in Churchill Falls 2018, is that of a palpable and overriding error: [34] [49] That being said, it should be borne in mind that, in this case, both the
interpretation and the characterization of the Contract are questions of mixed fact and law: Uniprix inc. v. Gestion Gosselin et Bérubé inc. , 2017 SCC 43 , [2017] 2 S.C.R. 59, at paras. 41-42 ; see also Sattva Capital Corp. v. Creston Moly Corp. , 2014 SCC 53 , [2014] 2 S.C.R. 633, at para. 50 . Because the trial judge’s
interpretation and characterization of the Contract are based on a particular set of circumstances that are unlikely to have any precedential value, they may not be overturned absent a palpable and overriding error: Housen v. Nikolaisen , 2002 SCC 33 , [2002] 2 S.C.R. 235, at paras. 28 and 36 . The characterization of the contract [ 41 ] Third, the characterization of the contract. The trial judge concluded that the contract dated May 12, 1969 and its
Schedule III constitute an inseparable contractual whole.
He found it to be a mixed contract containing a joint venture component and a sales component. [ 42 ] In Churchill Falls 2018 , however, the Supreme Court concluded that the contract is neither a joint venture contract [35] nor a relational contract. [36] It is, rather, a very long-term (65-year) innominate contract [37] whose “various prestations owed for the whole of that term have been defined with precision since day one”. [38] The Supreme Court found that the contract is a synallagmatic contract [39] governing “the financing of the Plant and the sale of electricity produced there”. [40] [ 43 ] The Supreme Court did not refer to an inseparable contractual whole, but rather to a single contract “[providing] for its automatic renewal 40 years after the Plant has been installed and is in service at full capacity”, [41] under the terms and conditions set out in
Schedule III. [ 44 ] The May 12, 1969 contract has a very long term: 65 years from the plant’s commissioning. The terms and conditions for implementing the agreement between the parties vary depending on whether the parties are in the first 40-year period (the “Initial Contract”) or the second 25-year period (“Schedule III”). [42] [ 45 ] With all due respect for the trial judge, his error regarding the characterization of the contract is not without its consequences.
Viewing the document as an inseparable contractual whole created the risk of commingling the terms and conditions applicable to one period with those applicable to the other, together with all aspects of their negotiation, contrary to the clear wording of the third paragraph of
section 3.2 of the Contract: 3.2 Renewal of Contract This Power Contract shall be renewed on the basis stated in this Section, for a further term of 25 years from the expiry date hereof. The renewed Power Contract shall be that set forth in
Schedule III hereof, which shall come into force automatically without any further signature being required. Any or all Articles or Sections of this Power Contract, other than this
Section 3.2, as well as any or all undertakings or promises not specifically contained in
Schedule III shall have no force and effect beyond the expiry date hereof and shall not thereafter be binding upon the parties to the renewed Power Contract . [Emphasis added] [ 46 ] It is clearly wrong to say that the agreement relating to the first 40 years and the agreement relating to the following 25 years form an indivisible whole, when
section 3.2 states the opposite in no uncertain terms. Both are contained in the same legal document, but each has a separate existence.
[ 47 ]
Schedule III describes a set of terms and conditions that are independent of the agreement that ended on August 31, 2016 and differ from it in many respects.
Entire sections have completely disappeared, [43] while others have been added or entirely rewritten. [44] [ 48 ] Similarly, the fact that the trial judge saw a joint venture where there was none led him to write that he had to [ translation ] “take into account the reasonable expectations of each shareholder”, [45] to the detriment of the wording of the terms and conditions which the parties determined in 1969 would apply as of the start of second 25-year period.
This problem is all the more serious here given that, for obvious reasons resulting from the passage of time, the persons involved directly in the negotiations from 1961 until the contract was signed on May 12, 1969 did not testify at the trial held in 2015, such that the evidence on this matter is strictly documentary. The ambiguity of the contract [ 49 ] Fourth, the ambiguity of the contract. The trial judge concluded that
Schedule III is ambiguous and that he therefore had to interpret it, as regards both HQ’s right to the plant’s power and energy and CFLCo’s right to sell power to third parties on an interruptible basis: [46] CONTINUOUS ENERGY [ translation ] [873] In the case at bar, the ambiguity results from the presence of the operational flexibility clause both in the Principal Contract and in the Renewed Contract. [874] In particular, the presence of this clause in the Renewed Contract, coupled with the definition of Continuous Energy, which does not appear in the Principal Contract, creates a real ambiguity, thereby allowing the Court to interpret the disputed clauses.
SALES OF INTERRUPTIBLE POWER [875] The situation regarding sales of interruptible power is different. While the concept existed at the time of the negotiations, it was only with the easing of the rules for the transmission of electricity products that this market developed. [876] Therefore, the ambiguity can be phrased as the following questions: Based on
section 6.6. of the Principal Contract and
section 5.4 of the Renewed Contract, can CF(L)Co sell energy and power to third parties not required by H.Q., and thereby exceed the 300 MW Recapture limit? In other words, does H.Q. have the right to all the power and energy that the Plant can produce? [ 50 ] CFLCo argues that the trial judge erred in concluding as to the existence of ambiguity. According to CFLCo, the presence of an Operational Flexibility clause , whose wording is identical in the Contract and in
Schedule III, does not create any ambiguity, because the clause deals with the manner in which HQ can plan deliveries of energy, not with the quantity of energy to which it is entitled. Thus, it argues, the clause does not in any way contradict the concept of Continuous Energy , which provides for the limited and fixed quantity of energy to which HQ is entitled each month. Moreover, CFLCo submits that the definition of Continuous Energy is not ambiguous, because its literal
interpretation properly conveys its meaning. [ 51 ] Lluelles and Moore have thoroughly summarized the process a judge must follow to determine whether a contract, or a portion thereof, is ambiguous: [47] [ translation ] 1571. The mere fact that parties disagree on the meaning of a clause does not make that clause ambiguous or vague. It is up to the judge to determine vagueness, through a preliminary analysis of the contract. If, after this pre-interpretation phase, the court determines that the intention of the parties is doubtful, there is room for
interpretation. Strangely enough, during this preliminary phase, the judge must, in a way, interpret the contract, but only superficially, in a process that has been referred to as interpretative screening . In principle, in this phase, the judge should not rely on articles 1425 and ff., because the purpose of this phase is precisely to determine whether or not these articles apply. 1572. The pre-interpretation phase, however, sometimes calls upon the same tools as the
interpretation phase. For example, the entirety of the contract, a major rule of
interpretation, may also be useful for determining ambiguity. Indeed, a clause that appears clear when considered separately from the rest of the contract, may become ambiguous when read with other elements of the text. Conversely, an apparently ambiguous clause may become clear when combined with other contractual clauses. In this regard, it is understandable that some may doubt the relevance of the two-phase approach (pre-interpretation/interpretation), calling into question, de lege ferenda , the need for an ambiguous text. 1573.
Sometimes, doubt arises from the use of an inadequate term or from a contradiction between two clauses. Most often, however, ambiguity results from a lack of precision, although lack of precision in not necessarily the same as ambiguity. Lack of precision may be avoided through the use of
definitions, although this technique can, in and of itself, also result in ambiguity or, at the very least, be difficult to apply to the facts of the case! 1574. One should be wary of apparent clarity. A text may be clear in isolation, but vague within the context of the rest of the document, or it may be entirely unambiguous on its face, but contradict the parties’ manifest objective. In such cases, the judge can conclude that a doubt exists and apply the rules of
interpretation. Indeed, the rule that a clear text “accurately reflects the intention of the parties” is only a relative presumption. When the wording of the contractual document (the instrumentum ) misrepresents the common intention of the parties (the negotium ), the court may even go so far as to correct the text of the contract, as well as the official administrative forms (particularly in taxation matters) filled out following the signing of the contract. However, such “reconciliation between the will of the parties and the document evidencing it”, which may be effected by the court simply replacing the exhibits originally filed, must be based
on a legitimate need and must not adversely affect third parties. 1575. Before concluding that a doubt exists, the judge must be convinced that the difficulty in understanding the document is serious enough that an ordinarily intelligent person would be confounded.
Clumsy drafting is insufficient to conclude that a doubt exists. [References omitted] [ 52 ] This is a [ translation ] “discretionary process that gives the judge called upon to interpret the text a certain degree of latitude to decide on the matter” [48] and [ translation ] “a question of fact requiring restraint and deference, such that an appeal court must not intervene unless a palpable and overriding error has been proven”. [49] [ 53 ] With all due respect for the contrary opinion, I am not convinced that the trial judge committed a palpable and overriding error by concluding that the contractual texts are ambiguous with respect to the meaning of the concept of Continuous Energy and that of sales of interruptible power. [ 54 ] Nonetheless, I would like to stress the prudence with which one must proceed in seeking out the intention of the parties in a case such as this one where, first, none of the persons involved in the negotiations from 1961 (when CFLCo first approached HQ) to 1969 (when the Contract and its schedules was signed) testified and, second, the parties to the Contract stipulated, in a clause which is unambiguous (section 3.2), “Any or all Articles or Sections of this Power Contract, […], as well as any or all undertakings or promises not specifically contained in
Schedule III shall have no force and effect beyond the expiry date hereof and shall not thereafter be binding upon the parties […]”. [50] In short, the words the parties used in
Schedule III to describe their rights and obligations as of the first day of the second 25-year period are vitally important. [ 55 ] I now turn to my analysis of the issues this appeal raises. A. HQ’s right to all the power and energy [ 56 ] The trial judge concluded that HQ has the exclusive right to purchase [ translation ] “all the available power and all the energy produced at the Upper Churchill plant”, except for the power and energy associated with the two blocks reserved for CFLCo (225 MW for Twinco and 300 MW for Recapture ). [51] [ 57 ] The right to the energy produced and the right to the available power can be split up (as appears from the table attached as
Schedule II to the May 12, 1969 contract), although power and energy are intimately related, since the second (kWh) is generated through the first (kW) being used over a certain period of time (h). The water that accumulates in the reservoirs serves to produce this energy. [ 58 ] I will deal with energy fist and then power. Energy [ 59 ] The trial judge concluded that HQ has the right to all the energy produced by the plant, as was the case during the 40-year period that ended on August 31, 2016. [ 60 ] To reach this conclusion, the trial judge considered that he was justified to go beyond the wording of
Schedule III because of its ambiguity. Given that, according to him, the agreement has a joint venture component, he was of the view that he had to take into account the reasonable expectations of each of the shareholders of CFLCo at the time of the negotiations, including HQ. He also examined the circumstances surrounding the signing of the May 12, 1969 agreement in order to find the parties’ intention, particularly with respect to the meaning of the expression Continuous Energy (Schedule III), which is included, word for word, in the Initial Contract under the definition of Basic Contract Demand .
The judge then considered the manner in which the parties interpreted their contract after it was signed, as well as usage in the electrical energy industry. [ 61 ] With all due respect for the trial judge, I am of the opinion that, in concluding that nothing had changed on September 1, 2016, he committed a manifest error in his
interpretation of the terms and conditions of
Schedule III. [ 62 ] Upon reflection, I see two flaws in his logic. First, it seems to me that, under the pretext that the texts were ambiguous, he was so focused on seeking out what the parties had wanted to say that he minimized the importance of what they had written. While
interpretation requires going beyond the wording of the text, nevertheless, the text should not be treated as if it did not exist. [ 63 ] Second, it appears that the trial judge’s examination focused on a single paradigm, namely, that operational flexibility [52] is meaningless unless HQ has access to all the energy produced by the plant, as it did before September 1, 2016.
In doing so, the judge distorted the meaning and scope of the concepts of Annual Energy Base and Continuous Energy , while also obscuring, without an explanation, certain significant differences between the terms and conditions applicable to the first 40-year period and those applicable to the subsequent 25-year period. [ 64 ] He could have done otherwise, however, by recognizing that, contrary to the situation that existed during the first 40 years of the agreement, HQ’s right to the energy produced by the Churchill Falls plant is now limited, while at the same time recognizing that, contrary to CFLCo’s position, HQ still has an operational flexibility very similar to the operational flexibility both parties acknowledged it had prior to September 1, 2016. * [ 65 ] For a better understanding of the reasons that follow, I have chosen to reproduce certain portions of the Initial Contract and
Schedule III. [ 66 ] They are presented as a table, side by side, to highlight the differences between the two periods, one running until August 31, 2016 and the other, a subsequent period, running until August 31, 2041: Agreement up to August 31, 2016 (May 12, 1969 contract, excluding
Schedule III) Agreement as of September 1, 2016 (Schedule III) 2.1 Object […] Hydro-Quebec agrees to purchase from CFLCo and CFLCo agrees to sell to Hydro- Quebec each month (i) […] (ii) from and after the Effective Date, the Energy Payable and the Firm Capacity ; all at the prices, on the terms and conditions, and in accordance with the provisions, set forth herein. 2.1 Object […] Hydro-Quebec agrees to purchase from CFLCo and CFLCo agrees to sell to Hydro- Quebec each month the Continuous Energy and the Firm Capacity , at the price, on the terms and conditions, and in accordance with the provisions, set forth herein. 1.1
Definitions “ Energy Payable ” means […] (
b) in respect of any month commencing on or after the Effective Date , (
i) the amount of energy which is taken by Hydro-Quebec during such month plus (ii) the amount of energy equivalent to water spilled during such month, as determined pursuant to Sections 4.2.6 and 4.6 and after excluding spillages attributable to the fact that CFLCo has, during the 12 months preceding the spillage, either incurred any penalty under
Article X or avoided such penalty only by virtue of Sections 10.3.4 or 10.3.6. Such spillage shall not cause the total Energy Payable for the 12 month period which terminates with the cessation of spilling to exceed the amount obtained when the total amount of all prior recaptures is deducted from 35.4 billion kilowatthours. 1.1
Definitions “ Continuous Energy ” means, in respect of any month, the number of kilowatthours obtainable, […], when the Annual Energy Base is multiplied by the number which corresponds to the number of days in the month concerned and the result is then divided by the number of days in the year concerned. […] “ Annual Energy Base ” means 31.50 billion kilowatthours per year or, in the event of an adjustment […], the number of kilowatthours per year established as a result of such adjustment, […] “ Annual Energy Base ” means the number of kilowatthours per year represented by the Annual Energy Base in effect at the time of expiry of the Power Contract which is hereby renewed. [53]
8.4 Price after the Effective Date [54] […] the monthly price for power and energy shall be: (
i) the product of the Basic Contract Demand multiplied by 66.67% of the Applicable Rate (earned whether or not taken or made available), plus (ii) the product of Energy Payable as calculated for the month then ended multiplied by 33.33% of the Applicable Rate. Such price shall be subject to adjustment as provided in
Section 8.5. 7.1 (Article VII – Price and Price Adjustment) For all Continuous Energy , Hydro-Quebec shall pay CFLCo 2.0 mills per kilowatthour. In the event that in any month CFLCo is unable due to Plant deficiencies to make available at least 90% of the Continuous Energy , the price payable by Hydro-Quebec for such month shall be 2.0 mills per kilowatthour for that part only of the Continuous Energy which is made available. 1.1
Definitions “ Basic Contract Demand ” means, in respect of any month, the number of kilowatthours obtainable, […], when the Annual Energy Base is multiplied by the number which corresponds to the number of days in the month concerned and the result is then divided by the number which corresponds to the number of days in the year concerned. ———— 6.2 Sale and Purchase of Power and Energy CFLCo shall deliver to Hydro-Quebec at the Delivery Point such power and energy as Hydro Quebec may request, subject to the provisions of Sections 4.2 and 4.3. […] ———— [Emphasis added] [ 67 ] What can one learn from this comparative table? [ 68 ] First, the wording of the object of the contract for the 40-year period is very different from the wording of that object for the subsequent 25-year period.
The expression Energy Payable does not appear in
Schedule III, while the term Continuous Energy , which does appear, was not included in the terms and conditions applicable from September 1, 1976 to August 31, 2016. As for the definition of Continuous Energy , it is identical to the definition of Basic Contract Demand , which appears in the Contract, but not in
Schedule III. [ 69 ] The manner in which the power and energy purchased by HQ are billed differs from one period to the other. I will return to this later, but, for now, suffice it to note that monthly billing based on two components, [55] one fixed (a predetermined quantity of energy billed at 66.67% of the applicable rate) and the other, variable (another quantity of energy billed at 33.33% of the applicable rate), during the first 40 years of the agreement, was abandoned in favour of a more straightforward and linear formula of 2.0 mills per kilowatt-hour until the end of the agreement. [ 70 ] Last, it should be noted that
section 6.2 ( Sale and Purchase of Power and Energy ), which was in effect until August 31, 2016, does not appear in
Schedule III. [ 71 ] In my view, the table itself illustrates the difference between the two periods (40 years, 25 years) as regards the quantity of energy to which HQ is entitled. [ 72 ] During the first 40 years, the agreement between the parties clearly recognized HQ’s right to all the energy it required: first, in its Object (“Hydro-Quebec agrees to purchase and CFLCo agrees to sell […]”), then in the definition of Energy Payable (“in respect of any month […] the amount of energy which is taken by Hydro-Quebec during such month”) [56] and, last, in
section 6.2— Sale and Purchase of Power and Energy (“CFLCo shall deliver to Hydro-Quebec […] such power and energy as Hydro-Quebec may request […]”) .
[ 73 ] The situation is different for the 25 years beginning on September 1, 2016. HQ’s exclusive right is limited to the quantities of energy contemplated by the inseparable concepts of Annual Energy Base (annual limit) and Continuous Energy (monthly limit) found in
Schedule III. What is particularly telling, in my opinion, is that CFLCo’s undertaking set out in s. 6.2 of the Initial Contract was not included in
Schedule III. [ 74 ] It is not contested that HQ is required to purchase and pay for, and CFLCo is required to sell to HQ, a fixed and predetermined quantity of energy. And, in my opinion, nothing less, but nothing more either.
Section 2.1 ( Object ) of
Schedule III and the concepts of Annual Energy Base / Continuous Energy are too clear to allow for another conclusion. [ 75 ] Unlike the Initial Contract,
Schedule III does not contain anything that would lead to the conclusion that HQ is entitled to all the energy produced by the Churchill Falls plant, over and above the quantities defined by the concepts of Annual Energy Base / Continuous Energy .
The first establishes the annual quantity of energy to which HQ is entitled, while the second, as the trial judge rightly noted, allocates this quantity from month to month, on a purely mathematical basis, essentially to ensure CFLCo has a regular and stable flow of revenue throughout the year. [ 76 ] The problem that such a mathematical allocation of energy would inevitably create (given the seasonal demand for electrical energy in Quebec) is resolved, in my opinion, just as it was prior to September 1, 2016, by the operational flexibility granted to HQ with respect to the scheduling of its requests for the delivery of energy (section 4.1.1) and its power requirements (section 5.3). * [ 77 ] In my opinion, and with all due respect for the work done by trial judge, the reasons that led him to conclude that HQ continues, even after August 31, 2016, to have the exclusive right to purchase all the energy produced at the Churchill Falls plant, contrary to the text of
Schedule III, are undermined by certain palpable and overriding weaknesses. [ 78 ] To convince himself that the concept of Continuous Energy refers to all the available energy, [57] notwithstanding the parties’ definition of that concept in
Schedule III by reference to the concept of Annual Energy Base , the trial judge cites excerpts from two drafts of a letter of intent from HQ to CFLCo, the first dated June 15, 1965 (exhibit D-78), “The term ‘Continuous Energy’, for the purposes hereof, shall mean all energy made available on a monthly basis at the agreed point of delivery, […]”, and the second dated July 12, 1965 (exhibit D-81), “The term ‘Continuous Energy’ for the purposes hereof shall mean all energy made available at the agreed point of delivery, […]”. [58] [ 79 ] These excerpts, however, are incomplete, such that the parties seem to be saying the very opposite of what they were actually saying at the time within the context of their negotiations with a view to abandoning the Split Tariff billing formula in favour of another formula as of the forty-first year of their agreement. [ 80 ] The full text of the relevant passage concerning the concept of Continuous Energy in the draft dated July 12, 1965 states the following: [59] The term “continuous energy” for the purposes hereof shall mean all energy made available at the agreed point of delivery, from all generating units commissioned less one unit, up to but not exceeding 105% of the corresponding amounts of energy shown in column 5 of the Table
Article 9, and subject to the provisions of
Article 8.1(
a) below. 9.0 CAPACITY AND ENERGY SURPLUS TO PRESENT REQUIREMENTS OF NEWFOUNDLAND Estimated Amounts at Agreed Point of Delivery Column 1 Column 2 Column 3 Column 4 Column 5 Units Installed Firm Capacity (KW) Spare Capacity (KW) Continuous Energy (Millions of KMH Per Month) Date March 1, 1971 2 435,500 444,500 320.1 June 1, 1971 3 881,000 444,500 644.57 [ 81 ] The words “all energy […], from all generating units commissioned less one unit, up to but not exceeding 105% of the corresponding amounts of energy shown in column 5” clearly do not refer to all the energy, but rather to a specific and limited quantity of energy, which is necessarily less than the plant’s total energy production.
First, the quantity is limited: a maximum of 105%, and nothing more. Second, the same draft letter contains a clause entitled Excess Energy (section 8.2), which describes the energy produced over and above what is covered by the concept of Continuous Energy due, for example, to increased water availability in the reservoirs or to the
improved efficiency of the facilities. Lastly, the calculations are based on one turbine-generator unit being taken out of service every month. It goes without saying that a more rapid return to service of that unit, if only for a few days, could result in additional energy production. [ 82 ] In short, the definition of Continuous Energy in the drafts of the letter of intent does not contradict the definition in
Schedule III which, together with the Annual Energy Base , refers to a defined and limited quantity of energy. [ 83 ] In its brief, HQ acknowledges that the judge truncated the definition of Continuous Energy , but it concludes that this is of no consequence because the concept of Annual Energy Base , to which the concept of Continuous Energy refers, includes all of the plant’s proven energy potential, and therefore includes the excess energy. [ 84 ] Indeed, HQ argues that on September 1, 2016, the value of the Annual Energy Base was identical to the value of that in effect the previous day, August 31, 2016. [60] It points out that the adjustments to this value throughout the period from September 1, 1976 to August 31, 2016 [61] took into account all energy deliveries to HQ, the equivalent kilowatthours of any spilled water and the equivalent number of kilowatthours represented by the change (up or down) in the reservoir level as compared with the reservoir level on the date the plant was commissioned (section 9.2— Basis for Adjustment ).
In short, it reflected the entire proven energy potential of the hydroelectric complex. [ 85 ] As brilliant as the argument may seem at first, it loses much of its luster when one considers the limits the parties contractually agreed on with respect to the adjusted value of the Annual Energy Base (section 9.3— Limitations on Adjustment of Annual Energy Base ). The upward adjustment could not exceed 3⅓% and the adjusted value itself could never exceed “the amount obtained when the amount of all recaptures of energy is deducted from 32.2 billion kilowatthours per annum”.
In fact, the amount of 32.2 TWh was reduced to 29.84 TWh as a result of CFLCo taking all of the “recaptures of energy” on March 9, 1998. [62] [ 86 ] It is therefore highly doubtful that the value of the Annual Energy Base represents the plant’s entire proven energy potential. [63] [ 87 ] Another fact must also be taken into account. Since September 1, 2016, the value of the Annual Energy Base is no longer subject to periodic adjustments. It is frozen in time, until the end of the 25-year period.
During this period, knowledge of hydroelectricity will undoubtedly continue to grow, to increase the efficiency of the facilities and, inevitably, to drive the energy potential of the hydroelectric complex upwards, but without being reflected in the Annual Energy Base . [ 88 ] It is therefore clear to me that, contrary to the trial judge’s conclusion, the value of the Annual Energy Base (and its monthly counterpart, Continuous Energy ) does not include all the energy produced by the Churchill Falls hydroelectric complex. [ 89 ] All things being equal, there is, and will continue to be, a certain quantity of energy over and above the value of the Annual Energy Base .
As a matter of fact, why would this dispute have arisen if both parties did not believe in the existence of a certain quantity of energy over and above the value of the Annual Energy Base ? [ 90 ] Regardless, one can only question the probative value of an argument based on prior versions of a document whose wording the parties refined over the course of their discussions, before arriving at a final version set out in the letter of intent dated October 13, 1966 and in
Schedule III of the May 12, 1969 contract. The exercise is all the more perilous given that the parties were careful to state that “all undertakings or promises not specifically contained in
Schedule III shall have no force and effect beyond the [31st of August 2016] and shall not thereafter be binding upon the parties to the renewed Power Contract” (section 3.2, third paragraph). The wording of this
section also highlights the fact that the Initial Contract and
Schedule III constitute two separate agreements.
This is not a mere renewal where, as sometimes occurs, the parties simply extend the initial term by a few years without amending the terms and conditions of their agreement. [ 91 ] In any event, the entire set of documents that led to the signing of the October 13, 1966 letter of intent and the May 12, 1969 contract confirm that the expression Annual Energy Base (and its monthly counterpart, Continuous Energy ) refers to a specific and limited quantity of energy, and not to the plant’s entire production, from the very first time it is defined in the draft letter of intent dated March 9, 1964 [64] until the letter of intent signed by the parties on October 13, 1966, [65] and in all versions in-between. [ 92 ] With all due respect, the trial judge is therefore mistaken when he states that [ translation ] “the only time this expression (Continuous Energy) was used, other than during the construction phase, it referred to the Plant’s entire production”. [66] This is a palpable error, and because it involves a fundamental element of his logic, it is potentially an overriding one. [ 93 ] On the same subject, it is worthwhile noting that, as of 1966, the parties had already provided for the fact that there would be a certain quantity of energy available over and above the Continuous Energy .
Section 7.3 of the letter of intent dated October 13, 1966, entitled Excess Energy (“ énergie excédentaire ” in the signed French version of the same letter), refers to this expression as “all energy other than continuous energy” (“ toute l’énergie autre que l’énergie continue ”). [67] [ 94 ] With all due respect for the trial judge, the texts to which he refers state the opposite of what he concluded. The concept of Annual Energy Base (and its monthly counterpart, Continuous Energy) refers to a limited quantity of energy, any additional quantity of energy being excess energy.
Therefore, it does not refer to all the energy produced by the plant. [ 95 ] This conclusion is also consistent with the evolution of the renewal clause contained in the May 12, 1969 contract (section 3.2). In an internal memo dated March 7, 1968, [68] CFLCo stated, under the heading “3.2 Renewal ”, that the sale of energy “shall be on a continuous energy basis, whereby, up to the limit of the number of kilowatthours per year which shall constitute […] the Annual Energy Base, Hydro-Quebec shall pay for all energy made available to it by CFLCo, whether or not taken”.
The quantity of energy covered by this purchase guarantee [69] was clearly defined in relation to the Annual Energy Base, and was limited. It did not refer to all the energy produced by the plant. [ 96 ] The same terms are found in subsequent versions of the renewal clause (such as those dated April 19, 1968 [70] and April 25,
1968 [71] ), until the final version dated May 12, 1969. The only difference is that in
section 2.1 of
Schedule III, the parties refer to a monthly limit ( Continuous Energy ), which is calculated in relation to an annual limit, which is itself a specific and limited quantity ( Annual Energy Base ). [ 97 ] Lastly, the terms and conditions of the agreement by which the parties bound themselves for the 40 years following the full commissioning of the plant included
section 6.2, which stated, in its first paragraph, that “CFLCo shall deliver to Hydro-Quebec at the Delivery Point such power and energy as Hydro-Quebec may request, subject […]”. This clause clearly expressed CFLCo’s undertaking to provide HQ with all the energy HQ might request, subject, of course, to the plant’s production capacity. This text was not included in
Schedule III. CFLCo submits, with good reason in my opinion, that this is a further argument confirming that HQ’s right to the energy produced by the plant is now subject to a contractual cap that did not exist during the first 40 years of the agreement. And yet, CFLCo points out, in his judgment, the trial judge completely failed to address the absence of
section 6.2. * [ 98 ] One of the arguments the trial judge puts forward, mistakenly, I believe, in order to conclude that Continuous Energy [72] is only a payment term, and not the monthly reflection of the maximum quantity of energy to which HQ is entitled each year, is that its definition matches, word for word, that of Basic Contract Demand , a concept found in the billing formula applicable until August 31, 2016, in the first of the two elements of the Split Tariff: [73] “(
i) the product of the Basic Contract Demand multiplied by 66.67% of the Applicable Rate […]”. [ 99 ] This exact match between the two texts, however, is of no consequence if one simply considers the payment structure in effect until August 31, 2016 and the one in effect as of September 1, 2016. [ 100 ] Until August 31, 2016, for reasons that we know, [74] the parties opted for a two-tier monthly billing formula, the first tier being fixed and calculated according to a mathematical formula that refers to the Basic Contract Demand / Annual Energy Base , whether or not HQ takes delivery of the energy (take or pay) [75] (billed at 2/3 of the applicable rate), and the second tier, being variable and calculated on the basis of the energy actually delivered to HQ, plus the energy equivalent to water spilled during the same month ( Energy Payable ) (billed at 1/3 of the applicable rate). [76] [ 101 ] As of September 1, 2016, the formula changes.
The Split Tariff is abandoned, but the willingness to ensure a certain degree of stable revenue for CFLCo remains. In addition, on that date, the parties will have had 40 years of experience calculating the Annual Energy Base . From then on, the object of their agreement concerns the purchase by HQ, each year, of a specifically defined and limited quantity of energy, at a firm price of 2.0 mills per KWh for the entire 25-year term.
The concept of Continuous Energy is used at that time to convert the total quantity of energy that HQ agrees to pay for, regardless of its actual needs, into a monthly quantity. [ 102 ] The basis for the calculation, be it for the Basic Contract Demand or Continuous Energy , is the same, namely, the Annual Energy Base (or, in French, [ translation ] “the assumed annual production of energy”), but the two terms reflect two different realities.
The first was used for a purely mathematical calculation, irrespective of HQ’s actual needs, with the possibility of an adjustment every four years depending on whether the energy payable was less, or more, than the Annual Energy Base (Initial Contract,
section 8.5 — Direct Price Adjustments ). The second describes, on a monthly basis, the quantity of energy that HQ will pay for, whether or not it needs it, and that CFLCo will sell to it, with a billing adjustment if CFLCo is unable, due to a failure of its facilities ( Plant [77] deficiencies), to make available at least 90% of the promised energy (Schedule III,
Article VII,
section 7.1— Price and Price Adjustment ). [ 103 ] In the first case, it was only a payment term which, ultimately, had nothing to do with the energy made available to HQ, i.e., all the energy produced by the plant, excluding the Twinco and Recapture blocks. In the second case, it is both a payment term intended to ensure regular and steady revenue for CFLCo and a monthly allocation of the energy that HQ binds itself to purchase, and CFLCo binds itself to sell to it, annually. * [ 104 ] The use of the concepts of Annual Energy Base and Continuous Energy in
Schedule III also explains the disappearance of
section 6.2, which existed in the Initial Contract (“CFLCo shall deliver to Hydro-Quebec at the Delivery Point such power and energy as Hydro-Quebec may request […]”).
Indeed, as of September 1, 2016, the quantity of energy no longer depends solely on HQ’s needs; it is predetermined. * [ 105 ] The trial judge also based his conclusion as to HQ’s exclusive right to all the energy produced by the plant on the presence of an identical operational flexibility clause in both periods (before and after September 1, 2016) [78] and on an alleged incompatibility between CFLCo’s position and the GWAC signed by the parties in 1998. [79] [ 106 ] Was he correct in that regard? [ 107 ] The following is the text of
section 4.2.1 (4.1.1 in
Schedule III), whose wording is the same, [80] both before and after August 31, 2016: 4.2.1 Operational Flexibility The parties hereto acknowledge that it is desirable for Hydro-Quebec to have the benefit of operational flexibility of CFLCo’s facilities in relation to the Hydro-Quebec system. Accordingly: (
i) Hydro-Quebec may request CFLCo to operate the Plant so as to supply Hydro-Quebec’s
schedule of power requirements, provided that no such request shall be less than the Minimum Capacity or, except as provided in
Section 6.4 [Section 5.2, in
Schedule
III], more than the Firm Capacity; (ii) Hydro-Quebec may require deliveries which have the effect of varying the amount of water to be carried in storage at any time, provided that, in so doing, sufficient water is left in storage so that Minimum Capacity can always be maintained; (iii) CFLCo agrees to make available to Hydro-Quebec information relating to the hydrology of the drainage basin and the levels of the reservoirs and the measurement and metering of any spillage from the reservoir [reservoirs, in
Schedule III]; and to co- operate fully with Hydro-Quebec in the forecasting of energy which can be made available. [ 108 ] It is also worthwhile to reproduce the clause entitled Firm Capacity Schedules (section 6.5 of the Initial Contract,
section 5.3 of
Schedule III), whose text is identical [81] for both periods and which, with respect to power , completes the concept of operational flexibility to which I will refer in this
section of my reasons: 6.5 Firm capacity Schedules At least seven days in advance of the first Delivery Date [date upon which this renewed Power Contract shall take effect, in
Schedule III] and at weekly intervals thereafter Hydro-Quebec shall furnish to CFLCo: (
a) an hourly
schedule of its proposed capacity requirements over the week following, and (
b) an estimate of what Hydro-Quebec is likely to
schedule over the three weeks thereafter. Each such seven-day
schedule shall constitute Hydro-Quebec’s request for availability of such capacity over the period scheduled to the various extents and at the various times indicated by the schedule, but subject to Hydro-Quebec’s right to make further requests for changes in capacity during the period within the limits of Firm Capacity and Minimum Capacity. Any such request shall be considered as revising the
schedule to the required extent and for the required time. [ 109 ] As for the GWAC, after some ten years of negotiations, it was signed on June 18, 1999, with an effective date retroactive to November 1, 1998. The GWAC provides HQ with guaranteed additional power (682 MW) for the winter period, without the restriction present in the Initial Contract (section 6.4) as well as in
Schedule III (section 5.2): “whenever additional capacity can, in the opinion of CFLCo , be made available” [emphasis added]. This additional capacity, which is over and above the Firm Capacity provided for in the contract, [82] increases the power made available to HQ during the winter months (November 1 to March 31) from 4382 MW to 5064 MW. [83] The term of the GWAC coincides with the term of the contract signed on May 12, 1969, i.e., August 31, 2041.
According to HQ, the compensation to be paid for this additional power guarantee will total nearly $1.5 billion dollars by the end of the contract, [84] on August 31, 2041. [ 110 ] Operational flexibility was the subject of drawn-out discussions between CFLCo and HQ.
This was a crucial point for HQ, whose objective was to operate the Churchill Falls plant (and its reservoirs)—through seasonally adjusted requests for the delivery of energy based on demand—in the same manner as it operates its own plants, to incorporate the Churchill Falls plant within its own network of plants and to coordinate it all efficiently. [ 111 ] On April 17, 1968, CFLCo finally agreed to include this operational flexibility in the agreement that was to bind it to HQ until 2041, during the 65 years following the plant’s commissioning. [ 112 ] Sections 4.2.1 and 6.5 of the Initial Contract gave HQ full operational flexibility allowing it, through its requests for the delivery of energy, to control production and manage water levels in the reservoirs.
This allowed HQ to adapt its requests for energy and power based on the seasonal demand for energy in Quebec, reducing its requests in the summer (thereby allowing water to accumulate in the reservoirs) and increasing them in the winter, when demand was higher. Given that HQ had access to all the energy produced by the plant, it also adapted its requests for energy on a multi-year basis, by scheduling deliveries above the value of the Annual Energy Base during years of high hydraulicity and below that value during years of weaker hydraulicity. [ 113 ] Sections 4.1.1 and 5.3 of
Schedule III are identical to sections 4.2.1 and 6.5 of the Initial Contract. The trial judge concluded therefrom that operational flexibility is necessarily inseparable from HQ’s access to all the energy produced by the plant and, therefore, that the presence of the same operational flexibility clauses in
Schedule III necessarily implies that HQ still has access to all the energy produced by the plant, because limited monthly deliveries of energy would deprive it of the operational flexibility it has always enjoyed. [ 114 ] With all due respect for the trial judge, I believe this logic is flawed. First, the operational flexibility clause does not deal with the quantity of energy or power. Rather, it deals with flexibility in scheduling deliveries.
Both before and as of September 1, 2016, even without taking the excess energy into account, the quantities of energy and power that CFLCo is required to deliver to HQ each year are significant. It is reasonable to conclude that HQ still requires scheduling flexibility for deliveries. [ 115 ] Second, it would be surprising if the presence of the operational flexibility clause in
Schedule III were to infer that HQ is entitled to all the energy produced by the plant, when
section 2.1 (object of the agreement) and the concepts of Annual Energy Base / Continuous Energy explicitly state otherwise. [ 116 ] In my view, one must try to reconcile the concept of operational flexibility with the notion that HQ has access to a limited, albeit considerable, quantity of energy. On this point, I agree with HQ. It would be surprising if the parties had intended a purely intra-monthly flexibility (i.e., solely within each month), as CFLCo proposes, despite the fact that HQ enjoyed full operational flexibility for 40 years and that, even after August 31, 2016, HQ still needs to efficiently coordinate th
[…]
Loading document…