2022 NLCA 27, 2022 NLCA 27
Opinion
Mastec Canada Inc. (first appellant) and Mastec Canada Projects Inc. (second appellant) v. FMR Management Inc. (first respondent) and NSP Maritime Link Incorporated (second respondent) (21/21) Indexed As: Mastec Canada Inc. v. FMR Management Inc. 2022 NLCA 27 7 C.A.N.L.R. 511 Court of Appeal of Newfoundland and Labrador Welsh, O’Brien and Butler JJ.A. April 28, 2022
Summary: FMR Management Inc. registered a lien on property against Mastec Canada Inc. and Mastec Canada Projects Inc. (together “Mastec”) for the supply of materials and labour in relation to construction work. The Court granted Mastec’s application to have the lien vacated and replaced with security in the form of a bond. Mastec subsequently applied for an order under section 26(6) of the Mechanics Lien Act for the delivery up of the bond for cancellation, and under section 23(4) of the Act to have the bond cancelled due to the passage of time. Mastec also filed an application for
summary trial pursuant to rule 17A, which was adjourned sine die . The applications judge was satisfied that regular steps to advance the matter had been taken, and dismissed the application for an order cancelling the bond. Mastec appealed the applications judge’s decision. Held: Appeal dismissed. Welsh J.A. (O’Brien J.A. concurring): Section 23(4) of the Mechanics Lien Act does not include reference to cancelling a bond which, as distinguished from a lien on property, is a financial obligation involving a promise to pay if certain circumstances arise.
The legislature provided a separate means for cancelling a bond under section 26(6) of the Act (paragraphs 11-13). Valid factors to be assessed on an application under section 26(6) include delay in proceeding with the claim, reasons for the delay, and prejudice to either party in maintaining or cancelling the bond, along with any other considerations that may be relevant in the particular circumstances. The applications judge considered the appropriate factors in assessing the application, being delay in the proceedings, reasons for the delay, and prejudice to Mastec.
There was no basis on which to find that the applications judge erred in refusing to grant Mastec’s application (paragraphs 14-26). Butler J.A. (concurring): Counsel had referred the judge to jurisprudence from other jurisdictions that led her to apply an incorrect test to the application. The inordinate delay test, applicable to the dismissal of an action, has no relevance on an application to vacate a certificate under section 23(4) .
Mastec, as the applicant, had the onus on the application under section 23(4) to establish the factual foundation that “a certificate of action has been registered for 1 year or more in the registry and no appointment has been taken out for the trial of the action”. The judge erred in failing to assess whether this factual foundation had been established. However, the error did not make a material difference as the factual foundation required to vacate the certificate of action pursuant to section 23(4) was not established; Mastec’s application for
summary trial was akin to taking an appointment as contemplated by section 23(4) (paragraphs 61-68).
With regard to section 26(6), Mastec did not establish that no appointment had been taken out for the trial of the action. Section 26(6),unlike section 23(4), makes no reference to a requirement to take an appointment for trial within one year. Further, the requirement toproceed to trial within the time period specified when a lien was in place has no relevance once a bond has been substituted. Mastec’sapplication under section 26(6) was appropriately dismissed (paragraphs 69-76). Cases cited: Welsh J.A.: Penney v. Lush (1996), (NL CA), 139 Nfld. & P.E.I.R. 113 (Nfld. C.A.) Pennecon Energy Ltd. v.
Metal World Inc., 2013 NLCA 67, 344 Nfld. & P.E.I.R. 32 Allen v. Sir Alfred McAlpine & Sons Limited, [1968] 1 All E.R. 543 Butler J.A. (concurring): Ring v. Canada (Attorney General), 2010 NLCA 20, 297 Nfld. & P.E.I.R. 86 Housen v. Nikolaisen, 2002 SCC 33, [2002] 2 S.C.R. 235 Metal World Inc. v. Pennecon Energy Ltd., 2013 NLCA 67, 344 Nfld. & P.E.I.R. 32 Penney v. Lush (1996), (NL CA), 139 Nfld. & P.E.I.R. 113 (Nfld. C.A.) Murray v. Danielski, 2011 NBQB 173 Omni-Mechel Ltd. v. 284800 Ontario Ltd. (1984), 24 A.C.W.S. (2d) 252, 5 C.L.R. 169 (Ont. S.C.) Haugen v.
Farm Credit Corp. (1981), 34 A.R. 204, 11 A.C.W.S. (2d) 409 (Alta. C.A.) Westfab Homes Ltd. v. Duncan, 1996 ABCA 382 1361556 Alberta Ltd. v. Ristorante Cosa Nostra Inc., 2021 ABQB 157 Kaulback v. Burke, (NS SC), [2000] N.S.J. No. 256, 186 N.S.R. (2d) 194 (NSSC) Re Driden Industries Ltd. v. Sieber et al, 1974 ALTASCAD 14 , [1974] A.J. No. 251, 44 D.L.R. (3d) 629 (Alta. C.A.) Lackie Industrial Contractors Ltd. v. Kinetics Technology International Corporation, (AB KB), [1985] A.J. No. 595,65 A.R. 392 (Alta. Q.B.) Statutes considered: Welsh J.A.: Mechanics Lien Act, RSNL 1990, c.
M-3, sections 23, 26 Butler J.A. (concurring): Mechanics’ Lien Act, RSNL 1990, c. M-3, sections 17, 21, 23(4), 26(2), 26(3), 26(6) Mechanics’ Lien Act, RSNB 1973, c. M-6,
section 52.1(1) Mechanics’ Lien Act, RSO 1980, c. 261, section 24(3) Builders’ Lien Act, RSA 1970, c. 35, section 33(2) Builders’ Lien Act, RSA 2000, c. B-7, section 46(2) Rules considered: Welsh J.A.:
Rules of the Supreme Court, 1986 , rules 17A, 40.11 Butler J.A. (concurring): Rules of the Supreme Court, 1986 , rules 17A, 40 Counsel: Raymond G. Critch, for the first and second appellants; Cletus Flaherty, for the first respondent; No appearance, for the second respondent. The appeal was heard on January 18, 2022 before Welsh, O’Brien and Butler JJ.A.
The following judgment was filed on April 28, 2022 by Welsh J.A., concurred in by O’Brien J.A., with separate concurring reasons by Butler J.A. ______________________________________________________________ Welsh J.A.: [ 1 ] This is an appeal by Mastec Canada Inc. and Mastec Canada Projects Inc. (together, “Mastec”) against the order of a judge dismissing Mastec’s application for cancellation of a bond which it had deposited in lieu of a lien registered pursuant to the Mechanics’ Lien Act , RSNL 1990, c. M-3 . BACKGROUND [ 2 ] A lien was registered by FMR Management Inc. on August 18, 2017.
Its statement of claim was issued on September 8, 2017. Upon application by Mastec, on September 21, 2017, pursuant to section 26(2) of the Mechanics Lien Act , the Court ordered that the lien “is vacated”, to be replaced with security in the form of a bond “which shall take the place of the Property” upon which the lien is claimed. [ 3 ] Thereafter, the proceedings continued during 2017 to 2019 with filings of defences and counterclaims, demands for particulars, lists of documents, and examinations for discovery. On October 24, 2019, Mastec applied for a
summary trial pursuant to rule 17A of the Rules of the Supreme Court, 1986 . That application was adjourned sine die . [ 4 ] Delays occurred in the proceedings related, among other things, to governmental actions imposed to deal with the covid-19 pandemic. Also on October 24, 2019, Mastec applied for an order under section 26(6) of the Mechanics Lien Act for delivery of the bond for cancellation.
As set out in the decision, in September 2020, Mastec again applied, this time, pursuant to section 23(4) of the Act , to have the bond cancelled due to the passage of time. [ 5 ] The applications judge was satisfied that regular steps to advance the matter had been taken with the agreement of all the parties.
While the judge recognized that Mastec was suffering “serious prejudice” through the expenditure of significant funds to maintain the bond in place, she dismissed the application for an order cancelling the bond. [ 6 ] It is unclear in the oral decision of the applications judge whether she was proceeding under
section 23 or 26 of the Act , and whether she was referring to both the certificate of action and cancellation of the bond when she dismissed Mastec’s application. However, on appeal, Mastec’s submissions were addressed to cancellation of the bond, the lien having been vacated in an earlier decision. The request for relief is for cancellation of the bond. Accordingly, it is cancellation of the bond that is the subject of this appeal, and to which the decision and reasons of the Court are properly directed. I am concerned about addressing issues that were not argued by the parties, and are not properly before the Court on the appeal. [ 7 ] NSP Maritime Link Incorporated took no
part in the proceedings in this Court or in the court appealed from. ISSUES [ 8 ] At issue is whether:
(1) The legislation authorizes the court to order a bond, deposited pursuant to section 26(2) of the Act , to be delivered up for cancellation under section 23(4) of the Act ; and
(2) The applications judge applied the appropriate factors in determining whether to grant Mastec’s application to have the bond delivered up for cancellation.
ANALYSIS The Legislation [9]
Section 23 of the Mechanics Lien Act provides for registration and subsequent vacating of a certificate of action and relatedliens: ...
(2) Upon an action under this Act being started, a certificate of action shall be registered in the registry. ...
(4) Where a certificate of action has been registered for 1 year or more in the registry and no appointment has been taken out for thetrial of the action, the judge may, upon the unilateral application of an interested person, make an order vacating the certificate of actionand discharging all liens depending on the certificate of action. [10]
Section 26 of the Act authorizes the substitution of security for the claim to take the place of a lien, and provides, in relevantparts: ...
(2) Upon application, the court may (
a) allow security for or payment into court of the amount of the claim of the lien ..., and order that the registration of the claim for lienand the registration of the certificate of action be vacated; ...
(4) Money paid into court, or a bond or other security for securing the amount and satisfactory to the court, takes the place of theproperty discharged and is subject to the claims of every person who has at the time of the application an existing claim for lien or givennotice of the claim under subsection 12(6) or under
section 15 to the same extent as if the money, bond or other security were realized bya sale of the property in an action to enforce the lien, but the amount that the court finds to be owing to the person whose lien has been sovacated is a first charge upon the money, bond or other security. ...
(6) Where money has been paid into court or a bond deposited in court under an order under subsection (2), the court may, upon noticeto the parties that the court may require, order the money to be paid out to the persons entitled to the money or the delivery up of thebond for cancellation. ... Application of the Legislation Section 23(4) of the Act [11] Mastec submits that an order may be made under section 23(4) of the Act to deliver up for cancellation a bond, which wasdeposited pursuant to section 26(2) in substitution for the lien and which resulted in the lien being vacated.
In making this submission,Mastec is relying on the authority in section 23(4) for an “interested person” to apply to vacate a certificate of action and lien where “thecertificate of action has been registered for 1 year or more in the registry and no appointment has been taken out for the trial of theaction”. The basis for the submission is that the bond takes the place of the lien, and should, therefore, be treated similarly to a lien. [12] That submission is not persuasive. The potential prejudicial effects of a lien and a bond are different.
A lien has the effect of“one party encumbering another’s property before validity of the claim has been judicially determined” (Pennecon Energy Ltd. v. MetalWorld Inc., 2013 NLCA 67, 344 Nfld. & P.E.I.R. 32, at paragraph 40). The owner’s ability to deal with the property pending adetermination of the claim is accordingly restricted.
For this reason, special provision is made in section 23(4) for vacating a lien basedon the passage of a specified period of time. [13] However, section 23(4) does not include reference to cancelling a bond which, as distinguished from a lien on property, is afinancial obligation involving a promise to pay if certain circumstances arise. Given the difference in effect, the legislature has provideda separate means for cancelling a bond; that is, section 26(6) of the Act. It is this provision that is engaged when an application is madefor delivery up of a bond for cancellation.
Section 26(6) of the Act General Principles [14] While the court has discretion to order delivery up of the bond for cancellation pursuant to section 26(6) of the Act, no factors arelisted that would circumscribe the scope of that discretion. The applications judge considered three factors: inordinate delay, excuse forthe delay, and prejudice to the parties. In identifying these factors, the judge made reference to the decision in Penney v. Lush (1996), (NL CA), 139 Nfld. & P.E.I.R. 113 (Nfld. C.A.).
That decision is concerned with dismissal of an action for want ofprosecution (rule 40.11 of the Rules of the Supreme Court, 1986). At issue in this appeal is whether those are appropriate factors to be
considered in respect of cancelling a bond and, if so, how they are to be assessed. [15] In Penney, Gushue J.A., for the Court, quoted from the decision in Allen v. Sir Alfred McAlpine & Sons Limited, [1968] 1 AllE.R. 543, in defining a test to be applied where an application is made for dismissal of an action for want of prosecution: [12] ... In order for such an application to succeed, the defendant must show: (
i) that there has been an inordinate delay. ... What is or is not inordinate delay must depend on the facts of each particular case. These vary infinitely from case to case, but it should not be too difficult to recognize inordinate delay when it occurs. (ii) that this inordinate delay is inexcusable. As a rule, until a credible excuse is made out, the natural inference would be that it isinexcusable. (iii) that the defendants are likely to be seriously prejudiced by the delay.
This may be prejudice at the trial of issues betweenthemselves and the plaintiff, or between each other, or between themselves and the third parties. ... [13] In my view, counsel for the appellant is correct in his submission that the above must be demonstrated and that, if the first tworequirements are satisfied, the onus still rests generally on the defendant to demonstrate that his or her right to a fair trial has beenprejudiced by such untoward delay. ... [16] Gushue J.A. went on to caution that “whether the principles as enunciated in McAlpine are relevant depends completely on thefacts of any particular case”, and that the “surrounding facts must always be carefully considered” (Penney, at paragraph 15). [17] Application of the criteria as they are stated and discussed in Penney must be considered taking into account the context in whichthey arise; that is, dismissal of a cause of action, which amounts to a final determination of litigation without adjudication of the issues.
For that reason, dismissal for want of prosecution is available in very limited circumstances, and a high threshold must be met, asreferenced in Penney. [18] In considering how the Penney criteria may be of assistance in the context of cancelling a bond, it is helpful to review thepurpose of mechanics’ lien legislation. The Court in Pennecon referenced the rationale underlying the statutory right to register a lien: [35] ... In Northern Electric Company Limited v.
The Manufacturers Life Insurance Company, (SCC), [1977] 2S.C.R. 762, at page 773, Laskin C.J.C., for the majority, noted parenthetically that the object of mechanics’ lien legislation is “to offerprotection to persons doing work or providing services or furnishing materials in respect of any building or improvement”. However, inNoranda Exploration Co. Ltd. v.
Sigurdson, (SCC), [1976] 1 S.C.R. 296, Spence J., for the majority, included potentialprejudice to the person against whom the lien is registered, and accepted that “the mechanics’ lien statutes enacted in the variousprovinces of Canada have always contained this protection of the owner as well as protection of the labourer and material-men” (page302).
It is for this reason that, to obtain the benefit provided by the Act, the claimant is required to verify the claim as true. ... [19] Given the difference between dismissing a proceeding for want of prosecution, which terminates a cause of action, andcancellation of a bond under section 26(6) of the Act, I am satisfied that it would not be appropriate to apply the criteria enumerated inPenney in the same manner as discussed in that case, which sets a high bar regarding “inordinate delay” that is “inexcusable”.
However,if applied with due consideration for the context of mechanics’ lien legislation, the three criteria are of assistance in assessing whetherthe court’s discretion should be exercised to order a bond to be delivered up for cancellation. [20] In conducting the analysis, all relevant factors must be considered. Where delay may be a factor regarding an order to deliver upthe bond for cancellation, adjectives applied to “delay” such as unreasonable, excessive, unacceptable, inordinate, or prejudicial may behelpful in assessing the application.
The causes of delay or reasons that explain it, as well as an excuse or responsibility for delay mayalso be relevant factors. The cost of maintaining the bond may be relevant to the analysis insofar as delay in the proceeding may resultin prejudice to the party that deposited the bond. [21] In
summary, in an application under section 26(6) of the Act, delay in proceeding with the claim, reasons for the delay, andprejudice to either party in maintaining or cancelling the bond are valid factors to be assessed, along with any other considerations thatmay be relevant in the particular circumstances. Application of the Principles [22] In this case, the applications judge, while referencing Penney, applied the criteria, in context, to the facts of the case.
In her oraldecision, she accepted that delay was a relevant concern, but was satisfied that “the parties have engaged on a process advancing thislitigation” (transcript, at page 25).
The judge explained, at pages 24 to 25 of the transcript, that she was ... cognizant and agree[s] that one must look at the facts of each case, and on the facts of this case, while there has been a period ofconsiderable time, 2017 to the present, relating to the setting of a trial date, I must also be guided by the procedural history which I haveset out and that that satisfies me that regular steps have been taken in this matter with the agreement of all the parties to the litigation. ... [D]iscoveries have been held, lists of documents have been filed ... . [23] Regarding reasons or excuses for the delay, the judge referred to the impact of court closures and delays related in particular tothe covid-19 pandemic, and the fact that the parties were taking steps to move the matter forward, including consideration of a
summarytrial which “is a more expeditious type of proceeding” (transcript, at page 27). The judge indicated that she understood that “somepriority” applies in the case of mechanics’ lien litigation (transcript, at page 27). [24] The applications judge also considered the question of prejudice (transcript, at page 27):
Serious prejudice, I think ... without doubt [Mastec] is expending money to keep its bond in place and has set out, I believe, that that’s to a tune now of $75,000. [FMR Management] points out ... nonetheless this as being an appropriate matter to be recovered in the trial proceedings. [ 25 ] Considering all these factors, the judge concluded that this was not an appropriate case to grant the application for cancellation of the bond, adding (transcript, at page 29): ...
Nonetheless, [Mastec] is not precluded, should this matter not advance in a satisfactory manner, it is open to [Mastec] to again come back to the court with respect to this issue. [ 26 ] I am satisfied that the applications judge considered appropriate factors, that is, delay in the proceedings, reasons for the delay, and prejudice to Mastec, in refusing to grant Mastec’s application. There is no basis on which to find that she erred. Costs [ 27 ] The applications judge ordered costs in the cause. Given the nature of this uncompleted matter, I would make the same order in this appeal.
SUMMARY AND DISPOSITION [ 28 ] In
summary: 1. Section 23(4) of the Act does not authorize an order for delivery up of a bond for cancellation; the provision that is engaged is section 26(6) which specifically provides for an application to cancel a bond; 2. The applications judge did not err in assessing Mastec’s application.
She considered, in the context of these circumstances, appropriate factors, that is, delay in the proceedings, reasons for the delay, and prejudice to Mastec, in determining that it would not be appropriate to grant Mastec’s application to have the bond delivered up for cancellation. [ 29 ] Accordingly, I would dismiss the appeal, and order costs in the cause. Concurring Opinion of Butler J.A.: INTRODUCTION [ 30 ] I agree with my colleagues that this appeal should be dismissed but I would take a different approach. [ 31 ] On this appeal the Court must address the
interpretation and application of sections 23(4) and 26(6) of the Mechanics’ Lien Act (the “ Act ”) with respect to an application brought to vacate a certificate of action and to deliver a bond for cancellation.
BACKGROUND [ 32 ] NSP Maritime Link Incorporated (“NSP”) is the owner of land known as the Bottom Brook Maritime Link Construction Site (the “Site”). [ 33 ] Mastec Canada Inc. and Mastec Canada Projects Inc. (together, “Mastec”) contracted with FMR Management Inc. (“FMR”) for the supply of materials and labour relating to construction work performed on the Site. [ 34 ] Claiming that it was owed $1,906,932.00 for the supply of materials and services to the Site pursuant to its contract with Mastec, FMR registered a lien against the Site on August 18, 2017 pursuant to
section 17 of the Act . On September 8, 2017 FMR filed its related statement of claim in the Supreme Court which issued a certificate of action.
This certificate was registered at the registry of deeds on September 19, 2017. [ 35 ] On September 21, 2017 a judge of the Supreme Court, Trial Division, ordered: Pursuant to section 26(2) of the Mechanics’ Lien Act , Mechanics’ Lien No. 18564 is vacated and in place thereof security in the form of a bond … in the amount of $2,193,000.00, which includes $286,068.00 in respect of costs, … shall take place of the Property upon which … the subject Mechanics’ Lien is claimed… (Emphasis Added.) [ 36 ] The judge did not vacate the certificate of action. [ 37 ] On October 24, 2019, Mastec filed two applications.
One sought
summary trial pursuant to rule 17A of the Rules and the other requested cancellation of the posted bond pursuant to section 26(6) of the Act . In its section 26(6) application Mastec alleged that the “entirety of FMR’s claim against Mastec was for delay costs” which it asserted were “beyond the scope of those rights recognized in
section 6 of the Act ” (the “First section 26(6) Application”). [ 38 ] Subsequently on August 7, 2020, on the sole basis that FMR had failed to cause the matter to be placed on the trial list within one year of the registration of the certificate of action, Mastec applied:
…pursuant to section 23(4) and 26(6) of the Mechanics’ Lien Act , R.S.N.L. 1990 c. M-3 (the “ Act ”) for vacating of the Certificate of Action and the delivery up of the bond placed as security in this action on the grounds that the Plaintiff has failed to cause this matter to be placed on the trial list within one year of the Registration of the Certificate of Action… (Appeal Book, Tab 7, at para. 2) [ 39 ] On November 3, 2020, a judge of the Supreme Court, Trial Division, gave directions on all three applications. The application for
Summary Trial and the First section 26(6) application were adjourned sine die . The application for relief under both sections 23(4) and 26(6) of the Act was ordered to be set down for a hearing at the earliest available date after December 1, 2020 (Appeal Book, Tab 9, at para. 2). [ 40 ] Memorandums of Fact and Law were filed on November 16 and December 3, 2020 respectively. Of note, Mastec did not respond to FMR’s position on the law either in a Reply Memorandum or at the hearing held on January 27, 2021. [ 41 ] The judge gave her decision orally on January 27, 2021.
Relying solely upon the Memorandums of Fact and Law, the judge denied Mastec’s application and ordered costs in the cause. [ 42 ] Mastec’s appeal alleges that the judge erred in the standard she applied to determine whether to exercise her discretion on the application. ISSUE [ 43 ] In light of this background, the question is not, as my colleagues suggest, whether the legislation authorizes the Court to order a bond deposited pursuant to section 26(2) , to be delivered up for cancellation under section 23(4) of the Act .
This misconstrues the pleadings and the approach which the judge took on the application. [ 44 ] I would characterize the issue to be determined on this appeal as whether the judge erred in dismissing the application. This requires a determination of the appropriate considerations on applications made under both sections 23(4) and 26(6) of the Act . Mastec and FMR agree that this is properly characterized as a pure question of law to be reviewed by this Court on appeal on a standard of correctness ( Ring v. Canada (Attorney General) , 2010 NLCA 20 , 297 Nfld. & P.E.I.R. 86 , at para. 6 , citing Housen v.
Nikolaisen , 2002 SCC 33 , [2002] 2 S.C.R. 235 ). ANALYSIS Did the judge err in dismissing the application? Section 23(4) [ 45 ] At the commencement of her oral decision the judge stated: So we’re here today because the court has been asked to make a decision respecting whether the Certificate of Action in this matter should be vacated pursuant to subsection 23(4) of the Mechanics’ Lien Act . (Transcript, at 13-14) [ 46 ] The subsection states:
(4) Where a certificate of action has been registered for 1 year or more in the registry and no appointment has been taken out for the trial of the action, the judge may, upon the unilateral application of an interested person, make an order vacating the certificate of action and discharging all liens depending on the certificate of action.
The Distinction between a Certificate of Action and the Action Itself [ 47 ] A review of her oral decision reveals that the judge proceeded on the basis that the test which would apply to an application to strike a statement of claim should apply to both the request to vacate the certificate of action under section 23(4) and to cancel the bond under section 26(6). [ 48 ] In doing so the judge failed to appreciate the distinction between striking a statement of claim and vacating a certificate of action. [ 49 ] As this Court recognized in Pennecon , at para. 2 , when a lien is vacated but money is held in court (or a bond substituted), “the claim of lien” remains in effect. [ 50 ] The September 21, 2017 Order vacated the lien and replaced it with a bond; title to the Site was no longer encumbered but because the certificate of action was not vacated, notice of the lien claim remained on the public record. [ 51 ] However, the certificate of action is merely a notice that there is a legal action commenced under the Act .
Vacating it would have no effect on the litigation ( Pennecon , at para 2 ). The test which would apply to an application to strike a statement of claim has no relevance to a request to vacate a certificate of action. [ 52 ] Had Mastec sought to strike FMR’s statement of claim on the basis of delay, rule 40.11 would apply. Alternatively, that request could have been made under section 26(2) (
c) of the Act , which states:
(2) Upon application, the court may …
(
c) upon appropriate grounds, dismiss the action. [53] In either or both of these instances, Mastec would be required to establish that there had been inordinate delay, which isinexcusable and by which delay Mastec was likely to be seriously prejudiced (Penney, at paras. 12-13). I will refer to this as the“inordinate delay test”.
Distinguishable Jurisprudence [54] On this appeal, Mastec acknowledges that counsel had referred the judge to jurisprudence from other jurisdictions that led her toapply an incorrect test to the application under both sections 23(4) and 26(6) (Appellant’s Factum, at paras. 27 and 30-47; see alsoAppellant’s Memorandum of Fact and Law, Appeal Book, Tab 10, at para. 20, and Respondent’s Memorandum of Fact and Law, AppealBook, Tab 11, at paras. 3-11). [55] The appropriateness of the inordinate delay test to Mastec’s requests under both sections 23(4) and 26(6) was thereforeaddressed by the parties and is properly before this Court on appeal. [56] Mastec had referred the judge to Murray v.
Danielski, 2011 NBQB 173, but
section 52.1(1) of the New Brunswick Mechanics’Lien Act, RSNB 1973, c. M-6, upon which the New Brunswick Court relied provides for the deemed discontinuance of an action: 52.1(1) An action to enforce a lien shall be deemed to be discontinued one year after the action is commenced unless (
a) the action has been set down for trial, or (
b) an application has been made to a judge of The Court of Queen’s Bench of New Brunswick for an order continuing the action and acopy of the notice of application has been served on the defendant to the action. [57] In comparison, our section 23(4) neither uses mandatory language nor references discontinuance of the action. [58] With similar result, FMR had referred the applications judge to Omni-Mechel Ltd. v. 284800 Ontario Ltd. (1984), 24 A.C.W.S.(2d) 252, 5 C.L.R. 169 (Ont. S.C.), which relied upon Haugen v.
Farm Credit Corp. (1981), 34 A.R. 204, 11 A.C.W.S. (2d) 409 (Alta.C.A.), for the conclusion that the application to vacate the certificate should be “treated in much the same way as a motion to dismiss forwant of prosecution, by examining whether there had been ‘inordinate delay’”. [59] However, Haugen involved both an application to discharge liens under section 33(2) of the Builders’ Lien Act, RSA 1970, c. 35,(the predecessor
section to section 46(2) of Alberta’s current Builders’ Lien Act, RSA 2000, c. B-7) and an application under the AlbertaRules of Court to strike the statement of claim. The inordinate delay test was not applied to the section 33(2) portion of the application. [60] It is well established in mechanics lien jurisprudence that the inordinate delay test applicable to the dismissal of an action has norelevance on an application to vacate a certificate of action which merely gives public notice that a lien claim exists. In addition toHaugen see Westfab Homes Ltd. v.
Duncan, 1996 ABCA 382, at para. 4, 1361556 Alberta Ltd. v. Ristorante Cosa Nostra Inc., 2021ABQB 157, at paras. 31, 33, and 35-36, and Kaulback v. Burke, (NS SC), [2000] N.S.J. No. 256, 186 N.S.R. (2d)194, at para. 13 (NSSC).
No Appointment Has Been Taken out for the Trial [61] The initial onus on an application under section 23(4) lay with the applicant (Mastec) to establish that “a certificate of action hasbeen registered for 1 year or more in the registry and no appointment has been taken out for the trial of the action.” Without this factualfoundation, section 23(4) had no relevance. [62] The judge erred in failing to assess whether this factual foundation was established. [63]
Interpretation of “no appointment has been taken out for the trial” in section 23(4) requires consideration of the manner in whichmatters are set down for trial. Consistent with this Court’s note in Pennecon, at para. 54 (in the discussion of
section 36 of the Act), thelanguage of section 23(4) heralds back to a different time when matters were placed on a trial list at the request of the plaintiff. [64] The current rule 40 now speaks to a very different process. In particular rules 40.03 – 40.05 address what is required to make anapplication for a trial date. They reference disclosure of witnesses and documents, the filing of a Certificate of Readiness and therequirement of a pre-trial conference.
It is no longer a simple matter of making a request to be placed on a trial list. [65] The current Rules also provide for other means of dispute resolution which were not available when section 23(4) of the Act wasenacted and which include
summary trial under rule 17A. [66] As previously noted, Mastec had applied for
summary trial of FMR’s claim and its own counterclaim and this application wasadjourned sine die on November 3, 2020. [67] Section 23(4) does not require that the plaintiff be the party taking “the appointment ... for the trial of the action” and Mastec’sown application for
summary trial would, in my view, be akin to taking “the appointment”. [68] I conclude therefore that while the judge erred in treating the request to vacate the certificate of action as akin to striking thestatement of claim, her error did not make a material difference to the result. The factual foundation for the request to vacate thecertificate of action pursuant to section 23(4) was not established and it would have been appropriate to deny the requested relief on thisbasis. Section 26(6)
[69] Section 26(6) states: Where money has been paid into court or a bond deposited in court under an order under subsection (2), the court may, upon notice tothe parties that the court may require, order the money to be paid out to the persons entitled to the money or the delivery up of the bondfor cancellation. [70] Mastec sought to have the bond cancelled on the sole basis that “no appointment has been taken out for the trial of the action”. [71] I take a different approach from my colleagues but I reach the same conclusion that Mastec’s request to cancel the bond wasappropriately dismissed. [72] First, I have already determined that Mastec had not established that “no appointment has been taken out for the trial of theaction”. [73] Secondly, reliance upon an asserted failure to take an appointment for trial within one year as the basis to cancel a bond is notsupported by the wording of section 26(6).
Unlike section 23(4), section 26(6) makes no reference to a requirement to take anappointment for trial within one year. [74] Thirdly, section 26(3) specifically speaks against the requirement of expediency in proceeding with the lien claim once a bond issubstituted: Notwithstanding sections 23 and 24, where an order to vacate the registration of a lien is made under paragraph (2)(
a) or (b), the liendoes not stop existing for the reason that no certificate of action is registered. [75] For jurisprudence in support of my conclusion (that the requirement to proceed to trial within the time period specified when alien is in place has no relevance once a bond is substituted), see Re Driden Industries Ltd. v. Sieber et al, 1974 ALTASCAD 14 ,[1974] A.J. No. 251, 44 D.L.R. (3d) 629, at para. 12 (Alta. C.A.), and Lackie Industrial Contractors Ltd. v. Kinetics TechnologyInternational Corporation, (AB KB), [1985] A.J. No. 595, 65 A.R. 392, at paras. 1, 8 and 12-13 (Alta.
Q.B.)). [76] I would dismiss Mastec’s appeal respecting the request to cancel the bond on this basis. DISPOSITION [77] For these reasons I would dismiss the appeal. [78] I agree with my colleagues’ order for costs. Appeal dismissed.
Loading document…