CONSEIL DES INNUS DE EKUANITSHIT Applicant v. LE PROCUREUR GÉNÉRAL, 2013 FC 418
Opinion
Date: 20130423 Docket: T-778-12 Citation: 2013 FC 418 Ottawa , Ontario , April 23, 2013 PRESENT: The Honourable Mr. Justice Scott BETWEEN: CONSEIL DES INNUS DE EKUANITSHIT Applicant and LE PROCUREUR GÉNÉRAL DU CANADA, EN SA QUALITÉ DE JURISCONSULTE DU CONSEIL PRIVÉ DE SA MAJESTÉ POUR LE CANADA ET L’HONORABLE KEITH ASHFIELD, EN SA CAPACITÉ DE MINISTRE DES PÊCHES ET DES OCÉANS CANADA ET L’HONORABLE DENIS LEBEL, EN SA CAPACITÉ DE MINISTRE DES TRANSPORTS CANADA ET L’HONORABLE JOE OLIVER, EN SA CAPACITÉ DE MINISTRE DES RESSOURCES NATURELLES CANADA ET NALCOR ENERGY ET NEWFOUNDLAND AND LABRADOR HYDRO- ELECTRIC CORPORATION Respondents
REASONS FOR JUDGMENT AND JUDGMENT I.
Introduction [ 1 ] This is an application for judicial review filed on April 16, 2012 pursuant to sections 18 and 18.1 of the Federal Courts Act, RSC 1985, c-7 [FCA], by which the Applicant challenges the lawfulness of the Order in Council (C.P. 2012-285) taken by the Governor in Council (“the Order”) approving the federal government’s Response (“the Response”) to the Report of the Joint Review Panel, Lower Churchill Hydroelectric Generation Project, Nalcor Energy, Newfoundland and Labrador (“the Report”) and the related cause of action Decision dated March 16, 2012 (“the Decision”) by the responsible authorities, Fisheries and Oceans Canada [DFO], Natural Resources Canada [NRCan] and Transport Canada [TC] (collectively “the RAs”) pursuant to subsection 37(1) of the Canadian Environmental Assessment Act, SC 1992, c 37 [CEAA].
The Report was issued by a Joint Review Panel [JRP] as the culmination of its environmental assessment (“the EA”) of the Lower Churchill Hydroelectric Generation Project (“the Project”). The Order was made by the Governor in Council on March 12, 2012 pursuant to subsection 37(1.1) of the CEAA. [ 2 ] The Applicant is seeking, amongst other remedies: 1. a declaration that
a) the Governor in Council and RAs did not fulfill their duty to consult the Innus d’Ekuanitshit (the Ekuanitshit) on the elements of the Project liable to have a prejudicial effect on their traditional rights;
b) the Governor in Council and RAs did not seek to accommodate the Ekuanitshit in a spirit of reconciliation consistent with the honour of the Crown;
c) despite the requirements of paragraph 4(1) (
a) of the CEAA , the Governor in Council and RAs did not possess sufficient information to assess the potential negative impact that the Project is liable to have on the current use of the land and resources for traditional purposes by the Ekuanitshit;
d) the Project proposed by Nalcor Energy (“Nalcor”) is no longer the project proposed for evaluation under the CEAA due to subsequent changes in the implementation process;
e) the Project and the Labrador-Island Transmission Link Project (Transmission Link) constitute a single project under the CEAA ; and
f) the Governor in Council and RAs did not have sufficient information in order to judge the economic benefits of the Project or whether there are other economically and technically feasible means of meeting energy requirements that are less environmentally harmful; 2. an order quashing the Order and the Decision; 3. an order returning the Report to the Governor in Council and RAs so that they may:
a) fulfill their duty to consult and accommodate the Ekuanitshit pursuant to
section 35 of The Constitution Act, 1982 regarding the potential negative impacts of the Project on their traditional rights in a manner consistent with the honour of the Crown;
b) ask that further information be supplied regarding the necessity and negative impacts of the Project;
c) determine whether, in light of the supplementary information mentioned above, the Project’s negative impacts are still justifiable in the circumstances; 4. a writ of prohibition preventing the ministers of the DFO and TC from:
a) issuing permits under the Fisheries Act , RSC 1985, c F-14 and the Navigable Waters Protection Act , RSC 1985, c N-22; and
b) taking any other irrevocable decision in their roles as RAs with regards to the Project 5) Costs, regardless of the result of the application. [ 3 ] For the reasons that follow, the Court is dismissing this application.
II. Background A. The parties (
i) The Applicant [ 4 ] Le Conseil des Innus d’Ekuanitshit (“the Applicant”) is a registered Indian band within the meaning of
section 2 of the Indian Act, RSC 1985, c I-5. [ 5 ] The Applicant participated throughout the EA process for the Project, and was awarded funding through the Canadian Environmental Assessment Agency’s (“the Agency”) Participant Funding Program to facilitate its participation in different phases of the EA. (ii) The Respondents [ 6 ] The Respondents are: (1) the Attorney general of Canada [AGC] named in lieu of the Governor in Council, whose approval of the Response is required pursuant to subsection 37(1.1) of the CEAA ; (2) the Minister of Fisheries and Oceans, who, together with (3) the Minister of Transport and (4) the Minister of Natural Resources, constitute the Responsible Authorities [RAs] related to the Project; (the Government Respondents);
(5) Nalcor; and
(6) Newfoundland and Labrador Hydro-Electric Corporation. [ 7 ] Fisheries and Oceans Canada [DFO] and Transport Canada [TC] identified themselves from the beginning as RAs with respect to the Project. DFO found that certain components of the Project would result in the harmful alteration, disruption or destruction of fish habitat and would consequently require authorizations under subsection 35(2) of the Fisheries Act, RSC 1985, c F-14.
Transport Canada determined that the Project would require formal approval under subsection 5(1) of the Navigable Waters Protection Act, RSC 1985, c N-22 [NWPA] because the Project’s dams constitute works under that Act. [ 8 ] Natural Resources Canada became a responsible authority on August 19, 2011, when a decision was taken by the Government of Canada to provide financial assistance to Nalcor in the form of a loan guarantee for a part of the Project. [ 9 ] Nalcor is a Crown Corporation incorporated pursuant to the Energy Corporation Act, SNL 2007, c E-11.01.
It is wholly owned by the Government of Newfoundland and Labrador (“the Province”), and was constituted to “engage in and carry out activities pertaining to the Province’s energy resources, including hydro-electric generation” . Nalcor is responsible for the implementation of the Province’s energy policy, and is governed in that respect by: the Energy Corporation Act, above; the Province’s long term energy policy, Focusing Our Energy (“the Energy Plan”); and the Electrical Power Control Act, 1994 , SNL 1994, c E-5.1. B.
The Project [ 10 ] Nalcor’s proposed Project consists of: “hydroelectric generating facilities at Gull Island and Muskrat Falls, and interconnecting transmission lines to the existing Labrador grid. The Project will be the subject of engineering design and marketing studies that will be conducted concurrently with the environmental assessment. As part of the environmental assessment, alternative means of carrying out the Project will be evaluated including its capacity, design, layout, and technology.
The Project as currently planned is presented and, as with any project, will require optimization to reflect current market and business opportunities. Nevertheless, the Project will be very similar to previous concepts. Optimization will determine details such as the size and number of turbines within each powerhouse, and construction sequencing pending access to the
south side of the river. Such changes and refinements will be relatively slight, and consistent with the normal process leading to final Project sanction. The Gull Island facility will consist of a generating station with a capacity of approximately 2,000 MW and include: - a dam 99 m high and 1,315m long; and - a reservoir 200 km 2 in area at an assumed full supply level of 125 m asl. The dam will be a central till-cored, rock-fill, zone embankment. The reservoir will be 225 km long, and the area of inundated land will 85 km 2 at full supply level. The powerhouse will contain four to six Francis turbines.
The Muskrat Falls facility will consist of a generating station that will be approximately 800 MW in capacity and will include: - a concrete dam with two sections on the north and south abutments of the river; - a 107 km 2 reservoir at an assumed full supply level of 39 m asl. The north
section of the dam will 32 m high and 180 m long, while the south
section will be 29 m high and 370 m long. The north
section will serve as a spillway in extreme precipitation events. The reservoir will be 60 km long and the area of inundated land will be 36 km 2 at full supply. The powerhouse will contain four to five propeller or Kaplan turbines, or a combination of both. The interconnecting transmission lines will consist of: - a 735 kV transmission line between Gull Island and Churchill Falls; and - two 230 kV transmission lines between Muskrat Falls and Gull Island. The 735 kV transmission line will be 203 km long and the 230 kV transmission lines will be 60kn long. Both lines will likely be lattice- type steel structures.
The location of the transmission lines will be north of the Churchill River; the final route is the subject of a route selection study that will be included in the environmental assessment. The lines between Muskrat Falls and Gull Island may be on separate towers, or combined on double-circuit structures”. (See Affidavit of Stephen Chapman, Exhibit SC-4, Federal Respondents Representations, Vol. 1, pages 270-271) [ 11 ] The Project has a long history. Since 1978, three different versions of the Project have been contemplated. Two versions involved diversions of rivers and an agreement with Hydro Québec.
As the negotiations failed with Hydro-Québec and it was determined that the diversion of rivers upstream of Churchill Falls was unfeasible, Nalcor focused on a project that did not entail the diversion of rivers. The version of the Project that was defined and registered by Nalcor for environmental assessment in November of 2006 is as described above; it does not rely on the diversion of rivers and is predicated on meeting identified needs within the Province and generating surplus energy to access export markets. C.
The CEAA Environmental Assessment Process [ 12 ] It is important to describe the framework that applied to this EA under the CEAA . There are five stages involved. This application for judicial review was filed at the conclusion of the fourth stage. [ 13 ] The Applicant submitted that correspondence related to phase V should be allowed in the record despite the fact that it was
exchanged after the application. The Court decided that it should not be accepted in the record because phase V is still ongoing and, more importantly, the record should be confined to what was before the decision maker at the time the application was filed. [ 14 ] The Project was registered in November 2006 and the RAs determined that the CEAA applied to the Project in February 2007. [ 15 ] In June 2007, the Minister of the Environment referred the assessment to a review panel.
Since the Province of Newfoundland and Labrador had also concluded that public hearings would be required under provincial legislation, the two Governments agreed to set up a JRP in January 2009. [ 16 ] It is important to note that the CEAA provides for three types of environmental assessments: screening, comprehensive study and panel review. A panel review calls for a more comprehensive assessment and extended involvement by participants.
The assessment was conducted by the JRP after the “Agreement for the Establishment of a Panel for the Environmental Assessment of the Lower Churchill Hydroelectric Generation Project” was concluded in January 2009.
The federal Minister of the Environment, together with the provincial Ministers of Environment and Conservation and the Minister of Intergovernmental Affairs, appointed the five member panel responsible for the panel review. [ 17 ] In order to better comprehend the scope and degree of involvement required under the EA, the Court believes that reproducing substantive extracts from the JRP Agreement that defined the Terms of Reference for the Panel’s EA will facilitate the comprehension of the issues raised by this application.
The JRP Agreement specified that: “2.0 Establishment of the Panel 2.1 A process is hereby established for the creation of a Panel, pursuant to sections 40, 41 and 42 of the CEAA and
section 73 of the EPA and, for the purposes of the review of the Project/Undertaking. 3.0 Constitution of the Panel 3.1 The Minister of the Environment and the Lieutenant-Governor in Council of the Province of Newfoundland and Labrador shall jointly establish the Panel. 3.2 The Panel shall consist of five members. 4.0 Conduct of the Environmental Assessment by the Panel 4.1 The Panel shall have all the powers and duties of a panel set out in
section 35 of the CEAA and sections 64 and 65 of the EPA and applicable regulations. 4.2 The Panel shall conduct the EA in a manner that discharges the requirements set out in the CEAA , the EPA and in the Terms of Reference for the Panel set out in
Schedule 1. 6.0 Record of environmental Assessment and Panel Report 6.1 A Project File containing all records produced, collected or submitted with respect to the EA of the Project/Undertaking shall be maintained by the Agency from the appointment of the Panel until the report of the Panel is submitted to the Ministers. The Public Registry shall be operated in a manner to ensure convenient public access to the records for the purposes of compliance with
section 55 of the CEAA and the practices of the Department.
6.2 On completion of the EA of the Project/Undertaking, the Panel shall prepare a report and submit it to the Ministers who will make it public. 6.3 The report will address the factors required to be considered under
section 16 of the CEAA and
section 65 of the EPA, will set out the rationale, conclusions and recommendations of the Panel relating to the EA of the Project/Undertaking, including any mitigation measures and follow-up program, and include a
summary of issues raised by Aboriginal groups, governments and other interested parties. [Emphasis added] 6.4 The Parties agree to coordinate, to the extent possible, the timing and announcements of decisions on the Project/Undertaking. 6.5 Once the report is submitted to the Minister of the Environment, responsibility for the maintenance of the Public Registry in accordance with
section 55 of the CEAA will be transferred to Fisheries and Oceans Canada as responsible authority. 8.0 Participant Funding 8.1 The Agency will administer a participant funding program to facilitate the participation of Aboriginal groups and the public in the EA of the Project/Undertaking. [Emphasis added]
Part I – Scope of the Project/Undertaking The Proponent proposes a project/undertaking consisting of hydroelectric generating facilities at Gull Island and Muskrat Falls, and interconnecting transmission lines to the existing Labrador grid. The Project/Undertaking includes the following components as described by the Proponent. The specific dimensions/characteristics of the proposal are subject to change as a result of the findings of the environmental assessment.
The Gull Island facility consisting of a generating station with a capacity of approximately 2,000 MW that includes: • A dam 99 m high and 1,315 m long; and • A 215 km 2 reservoir in area at an assumed full supply level of 125 m above sea level (asl). The dam is to be a concrete faced, rock fill dam. The reservoir is to be 230 km long, and the area of inundated land is to be in the order of 85 km 2 at full supply level. The powerhouse is to contain five Francis turbines.
The Muskrat Falls facility consisting of a generating station with a capacity of approximately 800 MW that includes: • A concrete dam with two sections on the north and south banks of the river; and • A 100 km 2 reservoir in area at an assumed full supply level of 39 m asl. • The north and south dams will be constructed or roller compacted concrete. The north
section dam is to be in the order of 32 m high and 432 m long, while the south
section is to be in the order of 29 m high and 125 m long. The reservoir is to be 60 km long and the area of inundated land is to be in the order of 41 km 2 at full supply level.
The powerhouse is to contain four propeller or Kaplan turbines, or a combination of both. Interconnecting transmission lines consisting of: • A 735 kV transmission line between Gull Island and Churchill Falls; and • Two 230 kV transmission lines between Muskrat Falls and Gull Island. The 735 kV transmission line is to be 203 km long and the 230 kV transmission lines are to be 60 km long. Both lines will be lattice-type steel structures. The location of the transmission lines is to be north of the Churchill River; the final route is the subject of a route selection study that will be combined on double-circuit structures.
Part II – Scope of the Environmental Assessment The panel shall consider the following factors in the EA of the Project/Undertaking as outlined in Sections 16(1) and 16(2) of the CEAA and Sections 57 and 69 of the EPA: 1. Purpose of the Project/Undertaking; 2. Need for the Project/Undertaking; 3. Rationale for the Project/Undertaking; 4. Alternative means of carrying out the Project/Undertaking that are technically and economically feasible and the environmental effects of any such alternative means; 5. Alternatives to the Project/Undertaking; 6.
Extent to which biological diversity is affected by the Project/Undertaking; 7. Description of the present environment which may reasonably be expected to be affected, directly or indirectly, by the Project/Undertaking, including adequate baseline characterisation; 8. Description of the likely future condition of the environment within the expected life span of the Project/Undertaking if the Project/Undertaking was not approved; 9.
Environmental Effects of the Project/Undertaking, including the Environmental Effects of Malfunctions, accidents or unplanned events that may occur in connection with the Project/Undertaking; 10. Any cumulative Environmental Effects that are likely to result from the Project/Undertaking in combination with other projects or activities that have been or will be carried out; 11. The significance of the Environmental Effects as described in items 9 and 10; 12.
Mitigation measures that are technically and economically feasible and that would mitigate any significant adverse Environmental Effects of the Project/Undertaking, including the interaction of these measures with existing management plans; 13. Proposals for environmental compliance monitoring; 14. Measures to enhance any beneficial Environmental Effects; 15. Need for and requirements of any follow-up program in respect of the Project/Undertaking; 16.
Capacity of renewable resources that are likely to be significantly affected by the Project/Undertaking to meet the needs of the present and those of the future; 17. Extent of application of the precautionary principle to the Project/Undertaking; 18. Comments received from Aboriginal persons or groups, the public and interested parties by the Panel during the EA; 19. Factors related to climate change including greenhouse gas emissions; 20. Proposed public information program.
To assist in the analysis and consideration of these issues, in addition to the Secretariat established by Canada and Newfoundland and Labrador to support the Panel, the Panel may retain, within its approved budget, independent expertise to provide information on and help interpret technical and scientific issues and matters related to traditional knowledge and community knowledge.
Aboriginal Rights Considerations The Panel will have the mandate to invite information from Aboriginal persons or groups related to the nature and scope of potential or established Aboriginal rights or title in the area of the Project, as well as information on the potential adverse impacts or potential infringement that the Project/Undertaking will have on asserted or established Aboriginal rights or title.
The Panel shall include in its Report: 1. information provided by Aboriginal persons or groups related to traditional uses and strength of claim as it relates to the potential environmental effects of the project on recognized and asserted Aboriginal rights and title. 2. any concerns raised by Aboriginal persons or groups related to potential impacts on asserted or established Aboriginal rights or title. The Panel will not have a mandate to make any determinations or
interpretations of: • the validity or the strength of any Aboriginal group’s claim to Aboriginal rights and title or treaty rights; • the scope or nature of the Crown’s duty to consult Aboriginal persons or groups; • whether Canada or Newfoundland and Labrador has met its respective duty to consult and accommodate in respect of potential rights recognized and affirmed by
section 35 of the Constitution Act, 1982 ; • the scope, nature or meaning of the Labrador Inuit Land Claims Agreement. [Emphasis added]
Part III – Steps in the Environmental Assessment Process The main steps in the EA by the Panel will be as follows: 1. Site Visit; 2. Public Information Centres; 3. Submission of the EIS; 4. Review of the EIS; 5. Comments provided to the Proponent; 6. EIS Sufficiency; 7. Scheduling of Public Hearings; 8. Location of Public Hearings; 9. Conduct of Public Hearings; 10. Length of Public Hearings; 11. Delivery of Panel Report.”
[ 18 ] The final Environment Impact Statement [EIS Guidelines] were released by the Governments on July 15, 2008 after considering input provided by Aboriginal groups, including the Applicant, and other stakeholders between December 19, 2007 and February 27, 2008 on the scope of the Project and other issues (see Exhibit A-98 to Bennett Affidavit, Nalcor Representations [NR], Vol. 1 and Chapman Affidavit at paras 71 and 99, Federal Respondents Representations, Vol.1). [ 19 ] The EIS Guidelines is a 10,800 page document that addresses the need, alternatives and cumulative effects of the Project. [ 20 ] The EIS issues of concern were determined through: (
a) the EIS Guidelines; (
b) stakeholder and public consultation; (
c) local and existing knowledge of potential environmental effects of projects (including hydro-electric projects); (
d) Nalcor’s submissions describing the existing environment; and (
e) analysis of the Nalcor study team, comprised of 15 environmental consulting firms. (See Exhibits H, I, JJ, NN to Bennett Affidavit (NR, Vol 1, pages 421, 453 and 1737) [ 21 ] The Applicant received plain language summaries of the EIS, translated into French and the Québec dialect of Innu-aimun (“Innu-aimun”). (See Exhibit A-398 to Bennett Affidavit (NR, Vol. 1) [ 22 ] Between March 9, 2009 and April 15, 2011, the JRP conducted its information gathering process. They began by inviting the public and government agencies to comment on the adequacy of the EIS.
The Applicant was among the 52 parties who presented detailed submissions (see document entitled Legal Comments on the Adequacy of the Environmental Impact Statement of the Lower Churchill Hydroelectric Project dated June 22, 2009 (Applicant’s Record, Exhibit 12, page 996, NR, Vol. 3, page 490). (See Exhibit J to Bennett Affidavit (NR, Vol. 1, page 462) [ 23 ] These submissions led the JRP to issue Information Requests [“IRs”] to Nalcor. Between May 1, 2009 and March 21, 2010, the JRP sent 166 IRs in five separate rounds. The process was meant to enable the JRP and the public to: (
a) scrutinize the EIS; (
b) make additional requests for information; and (
c) comment on Nalcor’s IR responses. (See Exhibits A-251- A-432, K, L, pages 498 and 513 to Bennett Affidavit (NR, Vol. 1 and 3) [ 24 ] Nalcor implemented a planning framework for the Project called the “Gateway Process”. The process entails six sequential phases between opportunity evaluation and decommissioning. In essence, at each of the six phases, there is a decision gate with respect to the development or not of the asset.
Either the activity is stopped pending additional information or it can move to the next sequential phase or it is abandoned. [ 25 ] Further to an announcement by Premier Williams on October 25, 2010, regarding a possible change in the sequencing of the Project, Nalcor was asked to provide additional information with respect to the change in the sequencing and the corresponding potential impact and environmental effects. Responses IR#JRP.165 and IR#JRP.166 filed in January 2011 contain a total of 160 pages.
The main conclusion was to the effect that there are no material changes to the predicted environmental effects resulting from re- sequencing the Project phases (see Exhibit A-549 to Bennett Affidavit (NR, Vol 11, page 2756). These responses make no reference to the Applicant or to any other Quebec based innus. [ 26 ] The application for the Transmission Link was filed on January 29, 2009 and revised on September 15, 2009.
It called for the construction and operation of an approximately 1,100 km long transmission line and associated infrastructure within Labrador and the Island of Newfoundland and finally favoured the Gros Morne and the selection of the Long Range Mountains crossing as the proposed transmission corridor (see Applicant’s Record, V. Duro Affidavit, Exhibit 10, Vol. 3, Page 804). [ 27 ] The record reveals that Nalcor filed over 5,000 pages of additional documentation for consideration by the JRP and stakeholders by way of IR responses.
Thirteen of the IRs touched upon the Applicant’s specific concerns with respect to: (
a) Aboriginal consultation; (
b) caribou, including the Red Wine Mountain and Lac Joseph herds; (
c) monitoring and follow-up; and (
d) waterfowl survey methodology. (See Exhibits A-251, A-432, A-588, K, L, KK, LL to Bennett Affidavit (NR, Vol 1, 3 and 8)
[ 28 ] On two occasions, the JRP invited the public to comment on Nalcor’s IR responses. The Applicant filed detailed submissions on both occasions. (See Exhibits K, M, N to Bennett Affidavit (NR, Vol. 3, pages 498 and 544 and Exhibits 13, 17 to Duro Affidavit (Applicant’s Record, Vol. 4 and 5) [ 29 ] On January 14, 2011, the JRP determined that the EIS (including the additional information submitted by Nalcor) was sufficient to proceed to the Hearing. (See Exhibit A-544 to Bennett Affidavit (NR, Vol. 1) [ 30 ] On January 14, 2011, participants were informed that the Hearing would begin on March 3, 2011.
The Final Public Hearing Procedures were released on February 16, 2011, after consideration of extensive input from the public, including the Applicant. [ 31 ] The Hearing was conducted over 30 days between March 3 and April 15, 2011, in six different communities and in the Province of Quebec.
There were general, community and topic-specific hearing sessions. (See Exhibit A-1385 to Bennett Affidavit (NR, Vol. 12) [ 32 ] The Applicant, through its representatives, made oral submissions during the community Hearing session in Sept-Îles, Quebec, on April 7, 2011, during which a video and materials were presented to the JRP.
Simultaneous translation was provided (French and Innu-aimun). (See Exhibits A-1220, A-1244, A-1280, A-1284 to Bennett Affidavit (NR, Vol. 1 and Exhibits 20-25, 28, 43 to Duro Affidavit (Applicants Record, Vol. 5, 6 and 9) [ 33 ] After the conclusion of 30 days of hearings, the JRP declared the record closed. The Report [ 34 ] The 355 page JRP Report was released to the Governments and the public on August 23 and 25, 2011, respectively. (See Applicant’s Record, Affidavit V. Duro, Exhibit 3, Vol. 1, page 221) [ 35 ] As required by CEAA and the TOR, the Report contains: (
a) a description of the EA process, including public hearings; (
b) the rationale, conclusions and recommendations regarding the nature and significance of the potential environmental effects ; (
c) recommendations concerning, amongst others, the mitigation measures relating to the environmental management of the Project, caribou, monitoring and follow-up programs; (
d) a
summary of issues identified and comments and recommendations received from Aboriginal persons/groups; and (
e) a
summary of the issues raised and comments and recommendations received from the public, Governments and interested parties. The Decision and Response of the Federal Government [ 36 ] Pursuant to the CEAA and the EPA, the Governments jointly issued their responses and the decisions on March 15, 2012. (See Exhibits R, S and T to Bennett Affidavit, NR, Vol. 3 and V. Duro Affidavit, Applicant’s Record, Exhibits 1 and 3, Vol. I, pages 170 and 218) [ 37 ] The Response describes the Federal involvement in the Generation Project, the EA process, and the key considerations contained in the JRP Report.
It also sets out the conclusions of the Federal Government and the reasons for its conclusion that the significant adverse environmental effects of the Generation Project are justified by its benefits; it also describes the decisions required of
TC and DFO under their respective Acts and the CEAA and responds to each recommendation of the JRP. (See Exhibit R to Bennett Affidavit (NR, Vol. 1 and 3, Applicant’s Record, V. Duro Affidavit, Exhibit 1, Vol.1, page 170) [38] The Decision determined that the implementation of mitigation measures is required for the Project to address, inter alia:(
a) birds, fish and mammals and/or their habitat (the caribou); (
b) current Aboriginal use of land and resources for traditional purposes;(
c) socio-economic impacts; and (
d) physical and/or cultural heritage. The Decision also required the implementation of a follow-upprogram to verify the accuracy of the EA and to determine the effectiveness of any measures taken to mitigate adverse environmentaleffects of the Project for the period extending from October 1, 2012 to October 1, 2037. (See Exhibit S to Bennett Affidavit, NR. Vol. 3, and V. Duro Affidavit, Exhibit 2, Vol. 1, page 218) III.
Relevant legislation [39] The applicable sections of the Canadian Environmental Assessment Act, SC 1992, c 37 and of The Constitution Act, 1982,Schedule B to the Canada Act 1982 (UK), 1982, c 11, are appended to this decision. IV. The issues [40] The Court has framed the issues raised by this application as follows: 1. Is the Applicant’s challenge of the Project scoping decision statute barred? If not was it scoped in accordance with
section 15of the CEAA? 2. Did the Government Respondents properly consider
section 16 factors of the CEAA prior to issuing their Decision andResponse pursuant to s 37 of the CEAA? 3. Was the Applicant properly consulted and accommodated in relation to the Project? V. Standard of review and analysis of the first issue: 1. Is the Applicant’s challenge of the Project scoping decision statute barred? If not was it scoped in accordance with
section 15of the CEAA? A. Standard of review [41] Determining the scope of a project under
section 15 of the CEAA is a discretionary exercise to be reviewed on the standardof reasonableness (see Prairie Acid Rain Coalition v Canada (Minister of Fisheries and Oceans) [Prairie Acid Rain Coalition], 2004 FC1265 at para 42; Inverhuron & District Ratepayers Ass. v Canada (Minister of The Environment) [Inverhuron], 2001 FCA 203; BowValley Naturalists Society v Canada (Minister of Canadian Heritage) [Bow Valley], (FCA), [2001] 2 FC 461) at para55; Pembina Institute for Appropriate Development v Canada (Minister of Fisheries and Oceans), 2005 FC 1123). B.
Analysis [42] The Applicant challenges, albeit indirectly, the Minister of the Environment’s [the Minister] scoping decision, madepursuant to paragraph 15 (1)(b), to conduct separate EAs for the Project and the Transmission Link. The Applicant argues that this
amounted to “project splitting”. Citing subsections 15(1) and 15(3) of the CEAA, the Applicant argues that the Minister unreasonablyrefused to exercise his discretion to enlarge the scope of the Project’s EA by not including the Transmission Link. The Applicant submitsthat the Transmission Link is a related construction that was likely to be carried out in relation to the Project and is now an essentialelement. [43] According to the Applicant, an inevitable result of this failure to “scope in” the Transmission Link is that the true negativeeffects of the actual Project remain unknown. This, in turn, renders the responsible authorities’ determination (pursuant to paragraph37(1)(
a) of the CEAA) that the significant adverse environmental effects of the Project could be justified in the circumstances,unreasonable. [44] The Respondents counter that the judicial review of the Minister’s scoping decision is statute barred by subsection 18.1(2)of the FCA and that the Applicant is attempting to indirectly challenge the decision via its arguments based on paragraph 37(1)(
a) of theCEAA and that in any case, the decision to maintain the scope of the Project as proposed by Nalcor was reasonable. [45] A scoping decision made under
section 15 of the CEAA is unquestionably a decision made by a “federal board, commissionor other tribunal” within the meaning of subsection 18.1 (2) of the FCA (see Prairie Acid Rain Coalition, Inverhuron and Bow Valley,above). As such, the Applicant had to commence its application for judicial review within 30 days after the time the decision was firstcommunicated.
The Court may, however, in its discretion, grant an extension of time to commence an application (see subsection 18.1(2) FCA). [46] As a preliminary issue, the Court finds it is necessary to address the pertinence of the decision in Tzeachten First Nation vCanada (Attorney General), 2007 FC 1131 [Tzeachten 1], to the case at hand.
Applying the reasoning found in Krause v Canada, (FCA), [1999] FCJ No 179, Justice Lemieux found that “no extension of time is required […] when the object of thelitigation is to obtain relief in a case where the duty to consult and accommodate reserve and aboriginal interests is engaged” (Tzeachten1, above, at para 27).
The limit to file in subsection 18.1(2) FCA does not apply in such cases. [47] However, the decision in Tzeachten 1 is distinguishable from the present case because it dealt with the aboriginal group’sright to have the Crown’s consultation process judicially reviewed despite failure to file within the prescribed delay. Such is not the casein the present instance because if the Court declaring judicial review of the scoping decisions statute barred will not impact the judicialreview of the consultation process provided to the Applicant.
Subsection 18.1 (2) continues to apply. [48] The Project scoping decision was made by the Minister and communicated to the Applicant on January 8, 2009. It isimportant to note that the Applicant had been aware of the Project’s scope since December 2007 when the EIS Guidelines were released. As for the decision to conduct separate EAs for the Generation Project and the Transmission Link, Nalcor advised the Applicant of thescope in February 2009 and the decision was taken in November 2009.
Furthermore, the decision was re-confirmed and communicatedto the Applicant on multiple occasions afterwards, with the last relevant communication occurring on January 31, 2011. This lastconfirmation was made in response to a letter sent by the Applicant on December 16, 2010, conveying its concerns about the scopingdecisions to the Agency, the Province and the JRP.
Despite its concern, the Applicant only commenced its application for judicial reviewon April 16, 2012. [49] In Harold Leighton et al v Her Majesty in Right of Canada, 2007 FC 553 at paras 33 and 34, Justice Lemieux summarizedthe principles that should guide a decision to grant an extension of time to commence a judicial review: [33] To grant or refuse a request for an extension of time to launch a judicial review application is a matter of discretion which must beexercised on proper principles. Those principles are well known with the Federal Court of Appeal’s decision in Grewal v.
Canada(Minister of Employment and Immigration), (FCA), [1985] 2 F.C. 263, being the seminal case. [34] From Grewal, above, and other decisions of the Federal Court of Appeal, the task at hand is as follows: • A number of considerations or factors must be taken into account in the exercise of the discretion; • These factors include: (1) a continuing intention to bring the application, (2) any prejudice to the parties opposite, (3) a reasonableexplanation for the delay, (4) whether the application has merit i.e., discloses an arguable case (hereinafter the four-prong test) and (5)all other relevant factors particular to the case [emphasis mine], see James Richardson International Ltd. v.
Canada [2006] FCA 180 atparagraphs 33 to 35;
• As explained in Jakutavicius v. Canada (Attorney General) [2004] FCA 289, these factors or consideration are not rules that fetter thediscretionary power of the Court. Once the relevant consideration or factors are selected, sufficient weight must be given to each of thosefactors or considerations; • The weight to be given to each of the factors or considerations will vary with the circumstance of each case (Stanfield v. Canada, 2005FCA 107 , 2005 FCA 107); • The underlying consideration in an application to extend time is to ensure that justice is done between the parties.
The usualconsideration in the standard four-prong test of continuing intention, an arguable case, a reasonable explanation for the delay andprejudice to another party is a means of ensuring the fulfillment of the underlying consideration of ensuring that justice is done betweenthe parties. An extension of time can be granted even if one of the standard criteria is not satisfied (Minister of Human ResourcesDevelopment v.
Hogervrost, 2007 FCA 41; and • The factors in the test are not conjunctive (Grewal, above, at pages 11 and 13). [50] While the Court acknowledges that the Applicant has an arguable case, it will not grant an extension in the present case forthe following reasons. Firstly, the indirect challenge comes two years after the Transmission Link scoping decision was communicated tothe Applicant and the Applicant has failed to request such an extension.
Secondly, the Court is convinced that any delay attributable to areview of the scoping decision will result in a serious financial prejudice to the opposing parties (Nalcor and the GovernmentRespondents) and to the public in general. [51] The Applicant has not petitioned this Court for an extension of time to challenge the scoping decisions, nor has it offeredany reasonable explanation for the two years that have passed before bringing its application forward on this issue. This is not surprisinggiven that the Applicant is challenging the decisions indirectly through subsection 37(1) of the CEAA.
The Court underlines the fact thatthe Applicant was represented by able counsel throughout the relevant time frame and should have challenged the scoping decisions atthe first opportunity before even participating in the two EA processes that were based on them. [52] Because the Applicant neglected to challenge the Minister’s scoping decisions, the EA processes moved forward. Studieswere conducted, meetings were held and serious investments were made by the proponents to move the Project along.
As theRespondents explain: “To change the scope of the two projects at this time would require at least one new EA process, the preparation ofa new EIS, reconvening a JRP, scheduling new public hearings, and re-engaging hundreds of stakeholders, all at great cost,inconvenience and delay”. • Was the Minister’s decision not to expand the scope of the Project proposed by Nalcor reasonable? [53] Regardless of whether the Applicant’s scoping challenge is statute barred or not, this Court finds that the Minister’sdecision to maintain the scope of the Project as proposed by Nalcor to be reasonable. [54] Under
section 15 of the CEAA, the RAs ((under 15(1) (a)) or Minister (under 15(1) (b)) have the discretion to determinewhat elements of a proposed undertaking will make up a project for the purpose of an EA. In MiningWatch Canada v Canada (Fisheriesand Oceans), 2010 SCC 2, [2010] 1 SCR 6 at para 39 [MiningWatch], the Supreme Court of Canada set limits to this discretion bydeciding that “[…] the minimum scope is the project as proposed by the proponent, and the RA or Minister has the discretion to enlargethe scope when required by the facts and circumstances of the project”.
Subsections 15(2) and (3) are examples of situations where theRA or Minister may increase the scope of the project beyond the description proposed by the proponent. “In sum, while the presumedscope of the project to be assessed is the project as proposed by the proponent, under s. 15(2) or (3), the RA or Minister may enlarge thescope in the appropriate circumstances” (MiningWatch, above, at para 39).
The Minister may also enlarge the scope of projects pursuantto 15(1) where the conditions of 15(2) and (3) are not met. [55] One of the harms that subsections 15(2) and 15(3) seek to prevent is referred to as “project splitting”. The Supreme Courtexplained that “project splitting” occurs when a proponent “[…] represent[s] part of a project as the whole, or propos[es] several parts ofa project as independent projects in order to circumvent additional assessment obligations […]”. The Court then provided an example ofhow project splitting could be used to “circumvent additional assessment obligations”:
Where the RA or Minister decides to combine projects or to enlarge the scope under s. 15(2) or (3), it is conceivable that the project asproposed by the proponent might have only required a screening. However, when the RA or Minister considers all matters in relation tothe project as proposed, the resulting scope places the project in the [Comprehensive Study List]. Where this occurs, the project would besubject to a comprehensive study (MiningWatch at para 40). [56] In other words, project splitting can be used as a means to avoid a more rigorous EA.
In the case at bar, the Applicantargues that Nalcor is engaging in a form of project splitting. By having the Project and Transmission Link undergo separate EAs, Nalcor,according to the Applicant, is hiding the Project’s true environmental footprint and can therefore justify more readily its adverseenvironmental effects.
The Applicant also underlines that the negative impacts of the Project and the Transmission Link are consideredseparately, yet the government’s response considered their positive impacts cumulatively. [57] In order to guide the RAs or Minister in determining whether to expand the scope of a project beyond that advanced by aproponent, the Agency released an Operational Policy Statement [OPS] in February 2010, entitled Establishing the Project Scope andAssessment Type under the Canadian Environmental Assessment Act.
The OPS suggests that when two projects can be considered“connected actions”, they should generally be scoped together. Two projects are connected actions when (1) one project is automaticallytriggered by another; (2) one project cannot proceed without the other; or (3) both are part of a larger whole and have no independentutility if considered separately. [58] The Applicant argues that paragraph 15(3) (
b) required the Minister “tout au long de l’évaluation de se pencher sur laquestion de savoir s’il y a d’autres opérations susceptibles “d’être réalisées en liaison avec l’ouvrage” […] dont le promoteur propose laconstruction” (Applicant’s Record, Vol. 2, page 3663, at para 158). This
interpretation of subsection 15(3) is at odds with thejurisprudence on the issue of scoping. In Friends of the West Country Assn. v Canada (Minister of Fisheries and Oceans), (FCA), [2000] 2 FC 263 at para 14 [Sunpine], the Court of Appeal explained that “the words in subsection 15(3) do not have theeffect of rescoping a project to something wider than what was determined under subsection 15(1)”. That is to say, subsection 15(3) isonly relevant when the RA or Minister initially scopes the project under subsection 15(1).
Once the project is scoped, subsection 15(3)no longer imposes any obligation on the Minister to expand it. In the Court’s opinion, the real question to ask in this instance is whethersubsection 15(3) required the Minister to include the Transmission Link when he initially scoped the Project. The Court finds that he didnot have such an obligation for the following reasons. [59] The Transmission Link was not a “construction, operation, modification, decommissioning, abandonment or otherundertaking in relation to” the Project (subsection 15(3) of the CEAA).
The jurisprudence has interpreted these undertakings as works“that pertain to the life cycle of the physical work itself or that are subsidiary or ancillary to the physical work that is the focus of theproject as scoped” (Sunpine, above, at para 20).
The Court of Appeal in Sunpine offered some examples of the type of undertakingscontemplated in subsection 15(3): [F]or example, something as major as a coffer dam required to hold back water where the construction of a bridge required work on ariver bed, or of a lesser order, such as the construction of temporary living quarters for construction workers (Sunpine, at para 20). [60] The Court agrees with the Respondents that the Transmission Link was not initially a subsidiary or ancillary undertakingthat is part of the life cycle of the Project.
The Transmission Link will not be erected in order to fix, maintain or decommission theMuskrat Falls dam. [61] The two pertinent subsections are therefore 15(1) and (2). [62] Subsection 15 (2) clearly states that the RA or Minister can expand the scope of a project to include one or more otherprojects when they are “so closely related that they can be considered to form a single project”. Subsection 15(2) clearly contemplates asituation where a proponent attempts to register closely related projects for separate EAs at or around the same time.
As the Respondentspointed out to this Court, at the time when the Project was registered for its EA: “Nalcor was working to determine transmission options […] [and] had not yet determined: (
a) which market it would pursue (anoverland route through Québec to export markets, routes from Labrador to the Island and through to export markets in the Maritimesand/or United States, or industrial development in Labrador); or (the preferred option for meeting domestic Island needs” (NR, page3355, para 95). [63] While the Transmission Link project existed as one of several options that was included in the Energy Plan, no decision hadbeen taken when the Project was registered.
[ 64 ] The Applicant suggests that the Transmission Link was really a “ fait accompli ” and that Nalcor was engaging in project splitting. The evidence in the record, more specifically the sequence of events, does not support the allegation that Nalcor was attempting to split the Project in two. Hence, when the decision was taken by the Minister he properly applied section 15(1) of the CEAA by scoping the Project as proposed by Nalcor. The Transmission Link was not automatically triggered by the Project.
As the Respondents submit, “[t]he Generation project was technically and economically feasible on its own for the purpose of delivering electricity and interconnecting to the existing Labrador grid” (NR, page 3357, para 100). The initial option contemplated developing Gull Island first for export using the Quebec corridor. Furthermore, the harm that the Applicant is concerned with (i.e. that the full environmental effects of the Project not being considered cumulatively with the Transmission Link) is addressed by paragraph 16(1) (
a) of the CEAA which requires an EA to include “the environmental effects of the project […] and any cumulative effects that are likely to result from the project in combination with other projects […] that have or will be carried out”. [ 65 ] It is important to note that Nalcor registered the Transmission Link for a separate EA in January 2009 (two years after the Project was registered). The Transmission Link was initially tracked as a screening but was later upgraded to a comprehensive review after the release of the MiningWatch decision. The two projects were maintained as separate EAs, however.
Those decisions were communicated to the public on April 14 th , 2010. Was the decision to maintain separate EAs for the Project and the Transmission Link reasonable? [ 66 ] Although it is clear that, in April 2010, the two projects were so closely related (to the point where the Transmission Link could not proceed without the Project) that the RAs might have considered joining them, the Court finds that the decision to keep two separate EAs was reasonable for the following reasons.
First, given that the Transmission Link project had been upgraded to a comprehensive study, the harm that subsection 15(2) seeks to prevent (i.e. a less rigorous EA for one of the projects) was no longer an issue. In addition, paragraph 16(1) (
a) ensured that there was no risk that the two projects’ environmental impacts would be considered independently. In fact, the combined negative effects of the projects will be considered twice (once in the Project EA and a second time in the Transmission Link EA). [ 67 ] Second, it should be noted that, the Project’s EA was already well underway when the Transmission Link was registered as indicated by Nalcor: “the JRP Agreement was signed; the EIS Guidelines had been issued; Nalcor had filed its 11,000 page EIS and responded to 165 IRs. […] Restarting the Generation Project EA to include both projects would have been highly prejudicial to all parties: (
a) causing considerable delay and confusion among stakeholders; (
b) requiring Nalcor to restart the EIS and component studies (which had taken years to prepare), including, re-review by all stakeholders; and (c)_requiring Nalcor to adjust the construction schedules for both of the projects (NR, page 3358, para 106). [ 68 ] In short, the Court accepts the Respondents’ argument that there was no harm in maintaining separate EAs, whereas joining them would have wasted a substantial amount of work and cost a significant amount of money.
The main consideration under the CEAA is that the environmental impact of the Project and the Transmission Link are considered in a careful and precautionary manner and that there is meaningful public participation throughout the environmental assessment process. The Applicant has not convinced this Court that it was unreasonable not to proceed to a single EA for the Project and Transmission Link.
It is not clear that starting anew with a single EA in April 2010 (i.e. when the Transmission Link was upgraded to a comprehensive study) would have significantly increased the quality of the assessment of the environmental impacts of these projects. Hence, our conclusion that the decision to maintain the Project and the Transmission Link EAs separate is reasonable given the circumstances. VI. Standard of review and analysis of the second issue: 2) Did the Government Respondents properly consider
section 16 factors of the CEAA prior to issuing their Decision and Response pursuant to s 37 of the CEAA? A. Standard of review
Section 16 of the CEAA [69] In Pembina Institute for Appropriate Development v Canada (Attorney General), 2008 FC 302 at para 37 [Pembina],Justice Tremblay-Lamer summarized the jurisprudence regarding the standard of review to be applied to decisions taken under
section 16of the CEAA: All parties agree that to the extent that the issues posed involve the
interpretation of the CEAA, as questions of law, they are reviewableon a standard of correctness (Friends of West Country Assn. v. Canada (Minister of Fisheries and Oceans), (FCA),[2000] F.C. 263, [1999] F.C.J. No. 1515 (QL), at para. 10; Bow Valley Naturalists Society v. Canada (Minister of Canadian Heritage), (FCA), [2001] 2 F.C. 461, [2001] F.C.J. No. 18 (QL), at para. 55).
However, issues relating to weighing thesignificance of the evidence and conclusions drawn from that evidence including the significance of an environmental effect arereviewed on the standard of reasonableness simpliciter (Bow Valley, cited above, at para. 55; Inverhuron, cited above, at paras. 39-40). [70] The issue in the present case is whether the JRP could, despite a lack of certain information, validly conclude that theProject’s impact on the Applicant’s use of the land for traditional purposes would be negative but not significant after mitigating mattersare implemented.
This is clearly a question dealing with “weighing the significance of the evidence and conclusions drawn from thatevidence including the significance of an environmental effect”.
The standard of review on such a question is reasonableness (seePembina, cited above, at para 37). [71] It is also worth noting that much more recently, in Grand Riverkeeper, Labrador Inc v Canada (Attorney General), 2012FC 1520 [Grand Riverkeeper], Justice Near re-assessed the standard of review applicable to the same question in light of the four factorsdescribed in Dunsmuir v New Brunswick, 2008 SCC 9, [2008 ] SCJ No 9 [Dunsmuir], namely (1) the existence of a privative clause; (2)the purpose of the tribunal as determined by interpreting the enabling legislation; (3) the expertise of the tribunal; and (4) the nature ofthe question at issue (Dunsmuir, above, at para 64).
He also concluded that the standard of review on such questions is reasonableness(see Grand Riverkeeper, above, at para 40). 2. Subsections 37(1) and 37(1.1) [72] Decisions taken by responsible authorities upon receipt of an EA report are reviewable on a standard of reasonableness (seeInverhuron above, at para 32).
In Bow Valley, above, at para 78, Justice Linden described the level of deference owed to these decisionsas follows: The Court must ensure that the steps in the Act are followed, but it must defer to the responsible authorities in their substantivedeterminations as to scope of the project, the extent of the screening and the assessment of the cumulative effects in the light of themitigating factors proposed.
It is not for the judges to decide what projects are to be authorized, but, as long as they follow the statutoryprocess, it is for the responsible authorities. [73] A high level of deference for decisions under
section 37 was also suggested in Pembina, above: The assessment of the environmental effects of a project and of the proposed mitigation measures occur outside the realm of governmentpolicy debate, which by its very nature must take into account a wide array of viewpoints and additional factors that are necessarilyexcluded by the Panel’s focus on project related environmental impacts.
In contrast, the responsible authority is authorized, pursuant tos. 37(1)(a)(ii), to permit the project to be carried out in whole or in part even where the project is likely to cause significant adverseenvironmental effects if those effects “can be justified in the circumstances”.
Therefore, it is the final decision-maker that is mandated totake into account the wider public policy factors in granting project approval (Pembina, above, at para 74). [74] The Government Respondents agree with the findings in Bow Valley that decisions made by the Governor in Council[GIC] pursuant to subsection 37(1.1) are only reviewable in cases where the statutory process for the EA was not followed or otherwiseacted outside the boundaries of the statute.
They submit that such an understanding of the scope of review is consistent with the SupremeCourt of Canada’s decision in Thorne’s Hardware Ltd et al. v The Queen et al., (SCC), [1983] 1 SCR 106, and arguethat the motives behind the GIC’s approval of the federal government’s Response are beyond the Court’s reach. [75] In Canada (Wheat Board) v Canada (Attorney General), 2009 FCA 214 at para 37, Justice Noël described the limitsimposed on the Courts’ ability to review decisions made by the GIC pursuant to a legislative power given to it by statute as follows: It is well-settled law that when exercising a legislative power given to it by statute, the Governor in Council must stay within theboundary of the enabling statute, both as to empowerment and purpose.
The Governor in Council is otherwise free to exercise itsstatutory power without interference by the Court, except in an egregious case or where there is proof of an absence of good faith
(Thorne’s Hardware Ltd. et al. v. The Queen et al., (SCC), [1983] 1 S.C.R. 106, page 111; Attorney General of Canadav. Inuit Tapirisat of Canada et al., (SCC), [1980] 2 S.C.R. 735, page 752). [76] This Court agrees with the above formulation of Justice Noël. As a result, the Court will only intervene with the GIC andResponsible Ministers’ decisions under subsections 37(1.1) and 37(1) if it finds that: 1) the CEAA statutory process was not properlyfollowed before the
section 37 decisions were made; 2) the GIC or Responsible Ministers’ decisions were taken without regard for thepurpose of the CEAA or 3) the GIC or Responsible Ministers’ decisions had no reasonable basis in fact ;which is tantamount to anabsence of good faith. B. Analysis •
Section 16 challenge to the sufficiency of information before the Government Respondents in drafting the JRP andmaking the decisions under subsections 37(1) and 37(1.1). [77] The Applicant argues that the Government Respondents violated
section 16 of the CEAA by failing to properly consider thenegative impacts of the Project on the Applicant’s current use of the land for traditional purposes. It also claims that the JRP was unableto properly consider the negative impacts on the Applicant because it lacked certain information on the extent and location of theircurrent land use of the land.
As noted above, the Applicant blames Nalcor and the Government Respondents for the paucity ofinformation before the JRP. [78] Given the lack of information as to the negative impacts of the Project on the Applicant and other Quebec aboriginalgroups, the Applicant submits that the decisions taken pursuant to subsections 37(1.1) and 37(1) of the CEAA were unreasonable.
TheGovernor in Council and Responsible Ministers could not reasonably conclude that the negative environmental effects of the Projectwere justifiable in the circumstances without a complete and thorough understanding of the severity of those environmental effects. [79] While counsel for the Government Respondents acknowledge that the JRP did not have a full picture of the current land useby Quebec Aboriginal groups (including the Applicant) in the Project area, they submit that it possessed sufficient information to fulfillits mandate under
section 16 of the CEAA. Based on the information before it, the JRP noted that current use in the Project area appearedto be “seasonal, sporadic and of short duration.” It also noted that many of the areas reported to be used by Quebec Aboriginal groupswere outside the Project area and would not be affected. The JRP’s conclusion on the issue went as follows: Based on the information on current land and resource use identified through the environmental assessment process, there areuncertainties regarding the extent and locations of current land and resource use by Quebec Aboriginal groups in the Project area.
ThePanel recognizes that additional information could be forthcoming during government consultations.
To the extent that there are currentuses in the Project area, the Panel concludes that the Project’s impact on Quebec Aboriginal land and resource uses, afterimplementation of the mitigation measures proposed by Nalcor and those recommended by the Panel, would be adverse but notsignificant (see page 3148, NR, Vol. 12). [80] Counsel for the Government Respondents concludes that the JRP properly considered the impact that the Project wouldhave on the current use of the land by Quebec Aboriginal Groups and more importantly by the Applicant, as required by
section 16 ofCEAA. They submit that the Governor in Council and Responsible Ministers had sufficient information on this aspect of environmentaleffects to take a reasonable decision pursuant to subsections 37(1.1) and 37(1) of CEAA. [81] Nalcor, for its part, denies that the information available to the JRP was insufficient and argues that “[t]he reasonablenessof the information considered during the EA pursuant to
section 16 must be evaluated in light of the reasonableness of the EA process,which provided the Applicant with ample opportunities to provide relevant information” (NR, page 3364). They submit that thisargument must also fail if the federal government is found to have met its duty to consult. Finally, they remind the Court that the JRP inquestion was found to have met its obligations under
section 16 in a recent judgment rendered by Justice Near (see Grand Riverkeeper,above, at para 71). [82] The Court concludes that there is no reason to intervene in the present instance for the following reasons. Firstly, there is noevidence before this Court that the statutory process called for by the CEAA was breached. On the contrary, the CEAA was closelyfollowed and adhered to at every stage of the process. [83] Secondly, as the Applicant points out, the primary purpose of the CEAA is to ensure that projects are considered carefully
before they are sanctioned by federal authorities so that they do not cause significant adverse effects (para 4(1)(
a) of the CEAA ). The
preamble to the CEAA also clearly states that : “[….] the Government of Canada seeks to achieve sustainable development by conserving and enhancing environmental quality and by encouraging and promoting economic development that conserves and enhances environmental quality.” This goal is subject to the caveat that projects creating significant adverse environmental effects may still be approved if they are deemed to be justifiable in light of other considerations ( subsection 37(1) of the CEAA ). Consideration of the factors listed in
section 16 ensures that the responsible authorities will have a good appreciation for the potential/likely adverse environmental effects of a project. [ 84 ] The Court finds that on this subject, the JRP possessed sufficient information to properly assess the likelihood of significant adverse impacts of the Project on the Applicant’s (and other Quebec Aboriginal groups’) current use of the land for traditional purposes.
While some details on the extent and location of usage could have been supplemented, the JRP had sufficient documentation and information before it, namely, testimony from members of Quebec aboriginal groups and historical documents, to validly conclude that usage in the Project area is “seasonal, sporadic and of a short duration”.
A close review of the documentation filed by Nalcor with the JRP reveals that the studies conducted by Hydro-Québec as part of the La Romaine Project together with the Comtois study and the presentation made by the Applicant in Sept Îles adequately describes the Applicant’s ties to the caribou that roam on part of the Project’s footprint. The Court is also satisfied that reasonable efforts were made by the JRP to acquire a more complete picture of the Project’s impact on the Applicant.
The Court fails to see how further details would have significantly modified the JRP’s ultimate conclusion in this instance. [ 85 ] The JRP carefully considered the issues, noted that certain information was lacking but still felt confident that the Project’s negative impacts on Quebec Aboriginal land use in the Project area would be small after the proposed mitigating measures were put into place, particularly as they pertain to the caribou. Its conclusion “falls within a range of possible, acceptable outcomes which are defensible in respect of the facts and law” ( Dunsmuir , cited above, at para 47 ).
This finding also means that the GIC and RAs possessed sufficient information on the topic to make their decisions pursuant to subsections 37(1.1.) and 37(1) of the CEAA . • Benefits of the Transmission Link [ 86 ] The Applicant contends that the federal government’s response to the JRP report unreasonably considered the benefits of the Transmission Link in concluding that the Project’s negative consequences could be justified in the circumstances.
In its Response, the federal government lists the “replacement of non-renewable generation plants that produce significant green house, and air pollutants” among the benefits of the Project. The Applicant submits that the only generation plant the Government could be referring to is the Holyrood generation plant located on the Island of Newfoundland. They further argue that Holyrood could not be replaced without the Transmission Link. The Applicant therefore argues that it is unreasonable to consider the benefits of the Transmission Link while ignoring its negative impacts.
Since the two projects were scoped separately, the Applicant contends that they should not be considered together because the Transmission Link is still undergoing its EA and has yet to be approved. They posit that including the benefits of the Transmission Link was, therefore, premature. [ 87 ] According to the Applicant, the fact that the Response considers the benefits of the Transmission Link is also evidence that the Project has been substantially modified.
The Applicant argues that the “true project” that is being approved and intended on being built is not the one described in the Report but rather that of the Muskrat Falls dam with the Transmission Link. The Gull Island dam has, according to the Applicant, either been abandoned or indefinitely postponed. This situation creates a significant problem according to the Applicant because it entails an indefinite approval for Gull Island. The dam would hang over the land like “the sword of Damocles”.
It is further submitted that the George River caribou herd is currently experiencing an alarming decline in numbers and that the construction of Gull Island at a later date, without further assessment, could be potentially disastrous for the herd. [ 88 ] Nalcor and the Government Respondents both reply that there is nothing in the CEAA which prevents the government from considering the benefits of related or unrelated projects. On the contrary, both argue that it would be unreasonable to consider a project in isolation and ignore any benefits accruing from other projects.
In addition, Nalcor argues that “while the Response considers the Transmission Link, it does not focus on it exclusively” (NR, page 3366). The economic analysis conducted by NRCan (a study the federal government relied on) “considers the economic viability of the Generation Project as a whole, as well as an assumption that only one or the other component might proceed […] [and concluded that] any of these scenarios could be economically viable” (NR, page 3366). [ 89 ] Nalcor equally insists that it still intends to move forward with Gull Island but that it must clear its gateway process before moving any further.
The fact that there is currently no determined start date for the Gull Island dam does not mean that it will not be built. Nalcor considers that the only significant change that has occurred relates to the sequencing of the construction of the two dams. What is more, according to Nalcor the impact of switching the order of construction was already considered in detail during the EA. It referred the Court to IR JRP 165. Nalcor also points to
section 24 of the CEAA to substantiate its position that there is no indefinite approval of Gull Island. That section, according to Nalcor, is designed to prevent the precise harm that the Applicant is concerned about. If the construction of Gull Island does not proceed within a reasonable timeframe,
section 24 of the CEAA will apply and require that a
new EA be conducted. [ 90 ] The Court accepts the Respondents’ argument on this issue. In addition to the points they raised above, the Court adds the following. Under paragraph 16(1)(
a) of the CEAA , a JRP must take into account the cumulative environmental effects of prior and future projects. Given that the negative impacts of a future project must be taken into account in an EA, the Court considers that the positive impacts can also be weighed in just as well.
Section 16 does not preclude such an exercise. [ 91 ] The Applicant’s concerns regarding the approval of Gull Island is fundamentally a scoping argument which the Court has already concluded to be statute barred in this instance. The Applicant submits that Gull Island should have been removed or “scoped out” of the Project. The Supreme Court of Canada already decided that the minimum scope of a project “is the project as proposed by the proponent” ( see MiningWatch , above, at para 39 ). The scope of the Project can then be increased but not decreased. The rationale is easy to understand.
Why would a proponent propose a project larger than they intended to build? They would only be rendering the EA process more onerous for no valid reason. Furthermore,
section 24 of the CEAA will prevent the indefinite approval of any component of a project which is not built within a reasonable timeframe. • Economic Feasibility and Alternatives [ 92 ] The Applicant argues that the GIC and Responsible Ministers unreasonably ignored the JRP’s conclusions and recommendations regarding the adequacy of the economic studies produced by Nalcor and the need to examine alternatives. The JRP concluded in
section 4.2 as follows: The Panel concludes that Nalcor’s analysis that showed Muskrat Falls to be the best and least cost way to meet domestic demand requirements is inadequate and an independent of economic, energy and broad-based environmental considerations of alternatives is required. [ 93 ] In its Response, the federal government noted that it had two economic analyses (one by NRCan and another by Manitoba Hydro International [MHI]), which “concluded by supporting Nalcor’s assertions that the Project represents the least cost option for meeting anticipated electricity demand” (NR, Vol. 3, page 0601).
The Applicant contends that these studies could not corroborate each other because the analysis conducted by NRCan evaluated the Project as originally proposed (Gull Island followed by Muskrat) whereas MHI and Nalcor’s looked at Muskrat Falls together with the Transmission Link. [ 94 ] The Court cannot find a reviewable error on this issue. The JRP fulfilled its purpose under para 4(1)(
a) of the CEAA by alerting the responsible authorities to its conclusion that Nalcor’s economic analysis was inadequate. The federal government disagreed with the JRP on the basis that another analysis corroborated Nalcor’s. The federal government’s decision on this issue had, therefore, a reasonable factual basis. It is important to reiterate that it is not this Court’s role to decide whether or not the Nalcor and MHI’s analyses are correct and to reassess the weight to be assigned to one study over another, but rather to determine whether the federal government’s decision rests on a reasonable basis.
As Justice Sexton reasoned in Inverhuron , above: The environmental assessment process is already a long and arduous one, both for proponents and opponents of a project. To turn the reviewing Court into an "academy of science" - to use a phrase coined by my colleague Strayer J. (as he then was) in Vancouver Island Peace Society v. Canada [12] - would be both inefficient and contrary to the scheme of the Act ( Inverhuron , above, at para 36). [ 95 ] The evidence before the Court indicates that the federal government was properly informed on the potential negative environmental impacts of the Project.
Furthermore it reasonably justified its decision to proceed in this instance after having weighed the benefits against the negative environmental impacts from its national perspective. As the Court reviewed the Response and Decision, it is clear that both are carefully considered decisions that balance competing objectives. VII. Standard of review and analysis of the third issue: 3) Was the Applicant properly consulted and accommodated in relation to the Project? A. Standard of Review
[96] In Dunsmuir, above, at para 62, the Supreme Court of Canada indicated that the first step in determining the appropriatestandard of review is to “ascertain whether the jurisprudence has already determined in a satisfactory manner the degree of deference tobe accorded with regard to a particular category of question”.
If the case law has, then the inquiry ends there and the established standardof review should be followed. [97] The standard of review to be applied in cases where the “government’s conduct is challenged on the basis of allegationsthat it failed to discharge its duty to consult and accommodate pending claims resolution” was first discussed in Nation v BritishColumbia (Minister of Forests), 2004 SCC 73 at para 60 [Haida].
Applying the principles established by Haida, the consensus in thecase law is that a question regarding the existence and content of the duty to consult is a legal question that attracts the standard ofcorrectness. A decision as to whether the efforts of the Crown satisfied its duty to consult in a particular situation involves “assessing thefacts of the case against the content of the duty” (Ka’a’Gee Tu First Nation v Canada (Attorney General), 2007 FC 763 at para 91[Ka’a’Gee]).
This is a mixed question of fact and law to be reviewed on the standard of reasonableness. [98] It is clear from the facts of this case that the federal government understood its duty to consult the Applicant on the Project. Ultimately, the question to be answered on this issue is whether the federal government satisfied the Crown’s duty to consult andaccommodate the Applicant in the present case. The standard of review is reasonableness. The question is then: Did the Crown makereasonable efforts to satisfy the duty to inform and consult incumbent upon them? (See Haida, above, at para 62). B.
Analysis • What was the scope of the Crown’s duty to consult and accommodate? [99] In order to decide whether the Crown fulfilled its duty to consult, the Court needs to determine the scope or content of thatduty.
The Supreme Court, in Haida, above, found that the scope of the duty to consult it “is proportionate to a preliminary assessment ofthe strength of the case supporting the existence of the right or title, and to the seriousness of the potentially adverse effect upon the rightor title claimed” (Haida, above, at para 39). [100] At the low end of the spectrum, that is to say, where there is little evidence supporting the existence of a right, theimportance of the right to the Aboriginal peoples small, and the potential impact of the proposed action on that right limited, the dutymay only be “to give notice, disclose information and discuss any issues raised in response to the notice” (Haida at para 43).
When theopposite is true, that is when “a strong prima facie case for the claim is established, the right and potential infringement is of highsignificance to the Aboriginal peoples, and the risk of non-compensable damage is high” (Haida at para 44) then deep consultation maybe required. Deep consultation may involve “the opportunity to make submissions for consideration, formal participation in the decision-making process, and provision of written reasons to show that Aboriginal concerns were considered and to reveal the impact they had onthe decision.” (Haida at para 44).
Even in cases where the duty to consult is at the lower end of the spectrum, the duty requires thataboriginal peoples’ concerns be taken seriously and, where possible, mitigation measures implemented (Mikisew Cree First Nation vCanada (Minister of Canadian Heritage), 2005 SCC 69, [2005] 3 SCR 388 at para 64 [Mikisew]). [101] Regardless of where the Crown’s duty to consult lies on this spectrum, “the controlling question in all situations is what isrequired to maintain the honour of the Crown and to effect reconciliation between the Crown and the Aboriginal peoples with respect tothe interests at stake.
Pending settlement, the Crown is bound by its honour to balance societal and Aboriginal interests in makingdecisions that may affect Aboriginal claims” (Haida at para 45). A key requirement in honourable consultation is responsiveness (TakuRiver Tlingit First Nation v British Columbia (Project Assessment Director), 2004 SCC 74 at para 25 [Taku River]). [102] The case law has also clearly established that consultation is not a “one way street” and there exists an obligation for bothparties to actively engage in the process.
As Justice Finch explained in Halfway River First Nation v British Columbia (Ministry ofForests), 1999 BCCA 470 at para 161 [Halfway River]: There is a reciprocal duty on aboriginal peoples to express their interests and concerns once they have had an opportunity to consider theinformation provided by the Crown, and to consult in good faith by whatever means are available to them. They cannot frustrate theconsultation process by refusing to meet or participate, or by imposing unreasonable conditions: see Ryan et al v. Fort St.
James ForestDistrict (District Manager) (25 January, 1994) Smithers No. 7855, affirmed (1994), (BC CA), 40 B.C.A.C. 91. Preliminary assessment of the strength of the claim
[ 103 ] The Applicant has filed a number of documents testifying to the Ekuanitshit’s traditional use of the land in and around the Project area for hunting small and large game, particularly caribou. Such documents include: 1) A 1983 study by Robert Comtois, Occupations et utilisation du territoire par les Montagnais de Mingan conducted in support of the Ekuanitshit’s claims in the federal government’s comprehensive land claims process (the “Conseil Attikamek Montagnais [CAM] negotiations); 2) an archeological study by Hydro-Québec (Applicant’s Record, Vol.
X, page 3181); 3) historical and archeological reports produced by Nalcor (Applicant’s Record, Vol. X, pages 3113, 3121 and 3122). [ 104 ] The federal government has never questioned the strength of the Ekuanitshit’s claim and, as the Applicant points out, already accepted it for the purpose of negotiating a treaty in 1979 (the CAM negotiations). While Nalcor initially claimed that the information they possessed did not provide any evidence of the Applicant’s historical or contemporary use of the land in the Project area, they later submitted a number of documents testifying to it.
Those documents include: 1) the CAM; (2) 11 Aboriginal consultation updates filed by Nalcor with the JRP; and
(3) Nalcor’s responses to information requests number JRP.2 and 1S/2S. In light of the uncontradicted evidence adduced, the Court concludes that t
[…]
Loading document…